             Lightweight scaffolding systems will be utilized to facilitate the installation of roofing and cladding materials.
              These systems will be designed to minimize ground disturbance and potential damage to tree roots.
              Additionally, careful planning will be undertaken to ensure that scaffolding erection and dismantling
              activities do not interfere with the protected tree zones.
             Where possible, prefinished panels/cladding will be used, therefore reducing the need for additional on-
              site finishing works. Material selections will ensure lifecycle durability, minimising the need for
              maintenance and replacement. Material fixing methods will also be considered to minimise installation
              time and loose fixing elements.
             Regular monitoring and inspections will be conducted to ensure that the roofing and cladding works adhere
              to the project's environmental objectives and comply with relevant building codes and regulations.

      Boardwalks:
          The connecting raised walkways serve to move people through the site during and post-construction. They
            provide a key form of site access.
          The raised walkways and support sub-frames on flexible pier foundations or spider footings will be used
            to minimize disturbance to the tree root systems and surrounding soil. Services will be suspended
            whenever possible to avoid excavation.
          The boardwalk decking will be selected from recycled materials with low VOC, lifecycle warranties and
            durability, limiting replacement requirements. Integrated fixings can be specified to reduce loose fixing
            elements.
          These raised boardwalks are to be constructed with the project arborist on site to oversee the installation
            of the footings as per the Post-hole Dig Works Methodology (ATTACHMENT C).
          The commencement of the construction of a boardwalk could be considered as each cabin is nearing
            structural completion, to allow off-the-ground personnel access for the internal fit-out.

      Internal Fit-out:
           To ensure minimal impact on the environment and efficient project delivery, a comprehensive plan for
              internal fit-out works will be developed in conjunction with the overall construction schedule. This plan will
              account for the staged construction approach and the sequential completion of boardwalks.
           It is anticipated that the full internal fit-out works for each cabin will be completed once the boardwalks are
              in place. By completing the boardwalks, the fit-out trades will have unhindered access to the site and the
              environmental impacts will be minimal.
           All large items, baths, toilets, cabinetry, fixtures, etc. could be delivered to site prior as part of the main
              building material deliveries and stored in designated lay-down areas.
           To reduce waste generation, prefabricated components and prefinished modular systems will be
              considered where feasible. The selection of materials and finishes will prioritize sustainability, energy
              efficiency, and low VOC emissions.

      Services – Fire protection systems, Electrical, Plumbing and Drainage
          Services where possible, are devised to avoid excavation and will be suspended under the dwelling
             framework and raised access walkways. The raised access walkways will interconnect and service the
             units commencing at the car parking area on the northern side adjacent to the existing resort and access
             roadway. Refer to the Hydraulic Review for a detailed outline of the proposed services methodology.




Construction and Tree Management Plan - REV03                                                                   Page 57 of 45

Used in these records

About this file

File size
10.8 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Approved Document Construction & Tree Management Plan OPW25-0206.pdf · 10.8 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.