6.6 POST-CONSTRUCTION
6.1. Site Demobilisation
Post Stage 3 Carpark and Road completion, the remaining Site Set-up and Contractors' facilities will be
removed from the site, this could include the removal of:
o Construction site offices and amenities.
o Laydown Areas.
o Site Fencing; and
o Tree Protection Fencing.
Removal of all temporary utilities and the connection of permanent services to council systems.
6.2. Environmental Rehabilitation and Landscaping
Post site demobilisation, the rehabilitation of all impacted areas to be completed.
Guidance will be available from the project arborist and ecologist.
All works are to be completed as detailed by the site-based rehabilitation and landscaping plans.
Monitoring and reporting by contractors and the project ecologist regarding the rehabilitation progress.
6.3. Post Construction Arborist Report
A Post Construction Arborist Report will be prepared by the Project Arborist for the retained trees. A Visual
Tree Assessment will be carried out detailing each tree's condition and vigour, damage or disturbance
which may have occurred, and remedial works undertaken.
The Project Arborist may at any time implement new or additional procedures as may be required for the
site in the best interest of the trees and the development as a whole.
6.4. Hand-Over Documentation
After the final inspection, a Certification of Compliance shall be supplied by the Project Arborist for the
retained trees along with any monitoring or deviation documentation as required.
Detailed instructional information will be handed over to the resort management team to ensure the
ongoing site maintenance and protection measures.
This will then be included in the RACV Resort’s current and ongoing tree maintenance strategy including
the Native Foresters’ Weed & Rehabilitation Management Plan.
Construction and Tree Management Plan - REV03 Page 59 of 45
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Approved Document Construction & Tree Management Plan OPW25-0206.pdfRelated documentApplication case desk ↗
About this file
- File size
- 10.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.