7.6 ONGOING TASKS
These tasks are identified as ongoing through all stages - PRE-CONSTRUCTION, CONSTRUCTION, and POST-
CONSTRUCTION.

7.1. Collaboration:
           Throughout the project process, close collaboration will be maintained between the project manager, architect,
            contractor, project arborist, and project ecologist. Regular site meetings will ensure construction processes and
            facilities are located and constructed with minimal impact on the retained trees and ecology.

7.2.       Exclusion Zones:
           Access to the Exclusion Zones is prohibited or restricted to those with permission. The site project arborist is
            required to attend the site when works are to be undertaken that may affect trees or their roots which are being
            protected. The project arborist shall oversee, advise and assist as and where required. Details of any works
            carried out are to be recorded by the project arborist and made available upon request and or in accordance with
            the approval conditions. If access is required within the Exclusion Zones, the project arborist is required to be
            informed and actions agreed upon and permission gained before access.

7.3.       Site Vegetation Monitoring:
           Site monitoring and auditing will be conducted throughout the construction timeframe. The project arborist will
            conduct regular site visits and maintain communication with the contractor to ensure proper tree protection
            measures are being implemented and maintained.

7.4.       Weed & Rehab Management:
           Continue weed management and begin rehabilitation works around completed cabin sites.
           Regular inspections conducted by the project ecologist.

7.5.       Environmental Protection Measures:
           These measures will focus on preserving the natural environment, protecting sensitive ecosystems, and
            complying with local environmental regulations.
           Erosion and sediment control measures, such as silt fences, sediment traps, and temporary revegetation, will be
            implemented to prevent soil erosion and water pollution.
           Stormwater runoff will be managed to prevent erosion and pollution of nearby water bodies.
           A waste management plan will be implemented to minimize waste generation and promote recycling and proper
            disposal.




Construction and Tree Management Plan - REV03                                                                 Page 5 of 45

Used in these records

About this file

File size
10.8 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Approved Document Construction & Tree Management Plan OPW25-0206.pdf · 10.8 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.