231031 - 66 Seaview Terrace - Construction Environmental Management Plan · OPW23/0175

Attached to the e-mail Operational Works Application OPW23/0175 - DA Form 1, Plans, Construction Environment Management Plan - 66 Seaview Tce_ Sunshine Beach.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
3.4.3 Car Parking
The project should be timed to ensure traffic disruptions are minimised by excessive contractors
attending the site. Adequate staff parking shall be provided on the site and supplemented by lawful
street parking along the western side of Seaview Terrace.


3.4.4 Delivery Management
The project manager and contractors shall coordinate deliveries to prevent traffic disturbance. The
following shall be given consideration:
     • Time of day and distance travelled for deliveries
     • Size and weight of delivery
     • Aids available for lifting of materials (crane, etc)
     • Material storage location

The recommended delivery loading and unloading zone is in the road reserve fronting the property. No
parking or standing of contractor vehicles is permitted over yellow curb lines.


3.5     Communication Plan
The Project Manager is to communicate with relevant stakeholders to advise of agreed construction
times, impacts on traffic, services and other relevant issues. A preliminary communication protocol is
presented in Table 1.

Table 1: Preliminary Communication Protocol
 Stakeholder                                Communication                          Timing
 Emergency services                         Email of to notify of proposed         At start and end of site works
 (Noosa Heads Police Station,               works and access points
 Noosa Heads Fire & Rescue,
 Noosa Heads Ambulance Service)
 Residences in the end leg of               Letter box drop of proposed            3-4 weeks prior to site works
 Seaview Terrace                            works, expected time frames, site      commencing
                                            contact, agrees parking
                                            arrangements and traffic impacts
 Residences in the end leg of               Notification of one-off temporary      As required, with suitable notice
 Seaview Terrace                            traffic condition changes (ie,
                                            temporary blockage from large
                                            delivery truck)
 Residences in the end leg of               Service interruptions (eg,             As required, with suitable notice
 Seaview Terrace and other                  electricity, water supply)
 affected residences

Figure 6 outlines the location of the key neighbours.




Preliminary Construction and Environmental Management Plan                   66 Seaview Terrace Sunshine Beach QLD 4567
Taylor Environmental (Australia) Pty Ltd                                                                   Page 10 of 38

Used in these records

About this file

File size
4.8 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

231031 - 66 Seaview Terrace - Construction Environmental Management Plan.pdf · 4.8 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.