231031 - 66 Seaview Terrace - Construction Environmental Management Plan · OPW23/0175
Attached to the e-mail Operational Works Application OPW23/0175 - DA Form 1, Plans, Construction Environment Management Plan - 66 Seaview Tce_ Sunshine Beach.
Plans and drawings: the text below has words only, no drawings.
4 Environmental Management
4.1 Erosion and Sediment Control
An Erosion and Sediment Control Plan (ESCP) is to be prepared for the Operational Works permit with
the aim of avoiding degradation of receiving waters and erosion of soil by implementing control
measures during the construction phase.
Table 2 below details the strategies for erosion and sediment control. The Project Manager is the
responsible person and is to undertake regular monitoring.
Table 2: Erosion and Sediment Control Strategy
Strategy Actions Monitoring
Site Management • Strategically locate site facilities, access points and stockpiles to • Contractor to
avoid or minimise potential impacts conduct regular
• Locate clear of drainage pathways and/or water bodies audits and complete
• Ensure perimeter controls (i.e., silt fencing, accesses etc.) are Form 3: Stormwater
established, maintained & functioning effectively Management,
Erosion and Sediment
Control (Appendix D).
• Regular visual
inspections of site
and Contractor
records held by PM.
Minimise exposed areas • Staging of earthwork activities • Regular visual
of earthworks • Ensure erosion control measures are added, modified and/or inspections by PM.
repositioned in progress with works
• Cover exposed areas with turf/grassing, mulch or protective
covers
• Ensure surface cover is maintained & grass cover is adequately
watered
• Revegetate slopes and surface upon completion
• Ensure regular irrigation and maintenance until established
Avoid erosive slopes • Identify areas of the site with high erosion or sediment • Regular visual
generation potential prior to commencing works inspections by PM.
• Limit embankment slopes to 1:4 where practical
• Ensure suitable protection & controls are implemented and
maintained
• Provide physical protection (i.e., reinforced matting etc.) to
steeper slopes)
• Ensure protective covering remains secured
• Ensure vegetation cover is established where required
Divert upstream runoff • Construct bunds or diversion channels around earthworks • Regular visual
away from construction • Provide scour erosion protection at discharge points (i.e., inspections by PM.
areas stormwater discharge outlet and creek bank protection)
• Ensure devices & controls operate effectively
Minimise sediment loss • Construct silt fences, gravel check dams, bunds, sediment traps, • Regularly maintain as
from disturbed rip rap protection or other control devices (i.e., cover matting, necessary (i.e.,
construction areas mulch etc.) to reduce sediment loss & transport weekly or after storm
• Ensure all devices and measures are installed and operating events).
effectively • Regular visual
inspections by PM.
Avoid/reschedule • Do not carry out works likely to result in excessive • Inspect works to
construction activities erosion/sediment loss ensure erosion risks
during wet weather • Do not undertake concreting works during unfavourable weather are minimized.
• Remove sediment from roadways, gutters, and drainage systems
• Review works program during unfavourable weather
Minimise runoff • Construct silt fences, gravel check dams, bunds, basins, retention • Inspect works to
velocities and volume systems and other approved devices in flow paths ensure erosion risks
from disturbed areas • Ensure measures are installed and operating effectively are minimized.
• Clean when necessary (weekly or after storm events)
Preliminary Construction and Environmental Management Plan 66 Seaview Terrace Sunshine Beach QLD 4567
Taylor Environmental (Australia) Pty Ltd Page 12 of 38
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
231031 - 66 Seaview Terrace - Construction Environmental Management Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 4.8 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.