231031 - 66 Seaview Terrace - Construction Environmental Management Plan · OPW23/0175

Attached to the e-mail Operational Works Application OPW23/0175 - DA Form 1, Plans, Construction Environment Management Plan - 66 Seaview Tce_ Sunshine Beach.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
4     Environmental Management
4.1     Erosion and Sediment Control
An Erosion and Sediment Control Plan (ESCP) is to be prepared for the Operational Works permit with
the aim of avoiding degradation of receiving waters and erosion of soil by implementing control
measures during the construction phase.

Table 2 below details the strategies for erosion and sediment control. The Project Manager is the
responsible person and is to undertake regular monitoring.

Table 2: Erosion and Sediment Control Strategy
 Strategy                    Actions                                                                     Monitoring
 Site Management              • Strategically locate site facilities, access points and stockpiles to    • Contractor to
                                avoid or minimise potential impacts                                        conduct regular
                              • Locate clear of drainage pathways and/or water bodies                      audits and complete
                              • Ensure perimeter controls (i.e., silt fencing, accesses etc.) are          Form 3: Stormwater
                                established, maintained & functioning effectively                          Management,
                                                                                                           Erosion and Sediment
                                                                                                           Control (Appendix D).
                                                                                                         • Regular visual
                                                                                                           inspections of site
                                                                                                           and Contractor
                                                                                                           records held by PM.
 Minimise exposed areas       • Staging of earthwork activities                                          • Regular visual
 of earthworks                • Ensure erosion control measures are added, modified and/or                 inspections by PM.
                                repositioned in progress with works
                              • Cover exposed areas with turf/grassing, mulch or protective
                                covers
                              • Ensure surface cover is maintained & grass cover is adequately
                                watered
                              • Revegetate slopes and surface upon completion
                              • Ensure regular irrigation and maintenance until established
 Avoid erosive slopes         • Identify areas of the site with high erosion or sediment                 • Regular visual
                                generation potential prior to commencing works                             inspections by PM.
                              • Limit embankment slopes to 1:4 where practical
                              • Ensure suitable protection & controls are implemented and
                                maintained
                              • Provide physical protection (i.e., reinforced matting etc.) to
                                steeper slopes)
                              • Ensure protective covering remains secured
                              • Ensure vegetation cover is established where required
 Divert upstream runoff       • Construct bunds or diversion channels around earthworks                  • Regular visual
 away from construction       • Provide scour erosion protection at discharge points (i.e.,                inspections by PM.
 areas                          stormwater discharge outlet and creek bank protection)
                              • Ensure devices & controls operate effectively
 Minimise sediment loss       • Construct silt fences, gravel check dams, bunds, sediment traps,         • Regularly maintain as
 from disturbed                 rip rap protection or other control devices (i.e., cover matting,          necessary (i.e.,
 construction areas             mulch etc.) to reduce sediment loss & transport                            weekly or after storm
                              • Ensure all devices and measures are installed and operating                events).
                                effectively                                                              • Regular visual
                                                                                                           inspections by PM.
 Avoid/reschedule             • Do not carry out works likely to result in excessive                     • Inspect works to
 construction activities        erosion/sediment loss                                                      ensure erosion risks
 during wet weather           • Do not undertake concreting works during unfavourable weather              are minimized.
                              • Remove sediment from roadways, gutters, and drainage systems
                              • Review works program during unfavourable weather
 Minimise runoff              • Construct silt fences, gravel check dams, bunds, basins, retention       • Inspect works to
 velocities and volume          systems and other approved devices in flow paths                           ensure erosion risks
 from disturbed areas         • Ensure measures are installed and operating effectively                    are minimized.
                              • Clean when necessary (weekly or after storm events)
Preliminary Construction and Environmental Management Plan                         66 Seaview Terrace Sunshine Beach QLD 4567
Taylor Environmental (Australia) Pty Ltd                                                                         Page 12 of 38

Used in these records

About this file

File size
4.8 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

231031 - 66 Seaview Terrace - Construction Environmental Management Plan.pdf · 4.8 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.