Reduce sediment • Install sedimentation basins if required. • Regular visual
transport offsite • Placement of gravel/rubble grid or suitable alternative at site inspections by PM
entry and exit points to prevent tracking of material onto offsite
roads
• Sweep or otherwise clean offsite roads which may have been
impacted by site activities
4.2 Stormwater Quality Management
Spills and contaminates management shall be undertaken to prevent unintended releases to the
environment and contamination to stormwaters. Table 3 below details the strategies. The Project
Manager is the responsible person and is to undertake regular monitoring.
Table 3: Stormwater Quality Management Strategy
Strategy Actions Monitoring
Storage of chemicals • Store on site in a secured, roofed, bunded area and minimal • Regular visual
and/or fuel quantities stored. Bunding to be in accord with Australian inspections by PM
Standards AS1940.
• Ensure storage is safe, secured and locked after hours.
Refuelling of Equipment • Conduct refuelling using a spill tray and spill kit. • Regular visual
& Machinery • Ensure apparatus and kits are available at equipment refuelling inspections by PM
stations.
Routine maintenance of • Provide all maintenance off-site or if unavoidable within • Regular visual
vehicles or plant appropriately bunded areas. inspections by PM
• Ensure all vehicles and plant on-site are well maintained.
Spillages of • Contain and collect contaminated material using of spill kits, as • Regular visual
contaminants required and dispose of contaminated material to an approved inspections by PM
facility with all approvals.
• Management to occur as soon as practicable. Obtain permits for
transport and disposal.
• Cover transported loads
Use of herbicides, • Prepare & apply using suitable apparatus, equipment & • Regular visual
insecticides, and protective gear as required. Apply to manufacturer’s inspections by PM
fertilisers. specification & in an environmentally sound manner.
• Ensure chemicals used in a safe manner and without
inappropriate exposure to any personnel, drainage paths or
water bodies. Provide training where appropriate.
4.3 Water Conservation and Reuse
The overall objective of these strategies is to ensure that the use of potable water supplies is minimised
during construction activities at the site. Table 4 indicates the recommended strategies for water
minimisation and reuse. The sources of alternative water supplies for construction activities may
include rainwater, stormwater, etc. from site activities and/or imported recycled water if allowable.
Table 4: Water Conservation and Reuse Strategy
Strategy Actions Monitoring
Minimize consumption of • Utilise alternative water supplies (imported treated effluent, • Monitor and maintain
potable water supplies rainwater, etc.) for dust management/ vehicle washing etc. if records of the usage
during construction by lawfully available. of potable water
using water efficient • Adopt practices to minimize water consumption, such as: supplies during
appliances and fixtures o minimize the area of exposed area requiring dust control construction.
(equivalent to 3 STAR o sweep rather than hose to clean construction areas • Records to be
WELS Rating). including paths & gutters provided to the PM.
o use buckets of water to clean tools instead of running
Ensure compliance with water
any water restrictions
that may be in place
Educate staff and • Include section on water reuse and conservation in • PM to conduct
subcontractors on water environmental site induction training. regular audits of
Preliminary Construction and Environmental Management Plan 66 Seaview Terrace Sunshine Beach QLD 4567
Taylor Environmental (Australia) Pty Ltd Page 13 of 38
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
231031 - 66 Seaview Terrace - Construction Environmental Management Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 4.8 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.