231031 - 66 Seaview Terrace - Construction Environmental Management Plan · OPW23/0175

Attached to the e-mail Operational Works Application OPW23/0175 - DA Form 1, Plans, Construction Environment Management Plan - 66 Seaview Tce_ Sunshine Beach.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
Table of Contents
1    Introduction ............................................................................................................................................4
  1.1     Background ........................................................................................................................................... 4
  1.2     Purpose.................................................................................................................................................. 4
2    Project Details .........................................................................................................................................5
  2.1     Property Details ..................................................................................................................................... 5
  2.2     Approvals .............................................................................................................................................. 5
  2.3     Proposed Works .................................................................................................................................... 6
  2.4     Key Considerations ................................................................................................................................ 6
3    Construction Management ......................................................................................................................7
  3.1     Security and Access ............................................................................................................................... 7
  3.2     Safety .................................................................................................................................................... 7
  3.3     Work Hours ........................................................................................................................................... 7
  3.4     Traffic Management ............................................................................................................................. 8
     3.4.1 Existing traffic conditions .................................................................................................................. 8
     3.4.2 Temporary Signage and Traffic Control Measures ........................................................................... 9
     3.4.3 Car Parking ...................................................................................................................................... 10
     3.4.4 Delivery Management .................................................................................................................... 10
  3.5     Communication Plan ........................................................................................................................... 10
  3.6     Complaints and Incidents .................................................................................................................... 11
4    Environmental Management .................................................................................................................12
  4.1     Erosion and Sediment Control ............................................................................................................. 12
  4.2     Stormwater Quality Management....................................................................................................... 13
  4.3     Water Conservation and Reuse ........................................................................................................... 13
  4.4     Waste Management and Minimisation .............................................................................................. 14
  4.5     Flora and Fauna Protection ................................................................................................................. 15
  4.6     Noise and Air Controls ......................................................................................................................... 16
  4.7     Amenity ............................................................................................................................................... 16
  4.8     Cultural Heritage ................................................................................................................................. 17
5    Incidents and Reporting ........................................................................................................................18
  5.1     Incidences ............................................................................................................................................ 18
  5.2     Reporting ............................................................................................................................................. 18
Appendix A      Plans of Proposed Works .......................................................................................................19
Appendix B      Form 1: Incident Report..........................................................................................................31
Appendix C      Form 2: Complaint Report ......................................................................................................33
Appendix D      Form 3: Daily Log Sheet..........................................................................................................35
Appendix E      Form 4: Stormwater Management, Erosion and Sediment Control ...........................................37




Preliminary Construction and Environmental Management Plan                                               66 Seaview Terrace Sunshine Beach QLD 4567
Taylor Environmental (Australia) Pty Ltd                                                                                                Page 3 of 38

Used in these records

About this file

File size
4.8 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

231031 - 66 Seaview Terrace - Construction Environmental Management Plan.pdf · 4.8 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.