LATE RFI - SCG 33114 (SWM) Rev A
Original PDF page 8, section 1. The text section number identifies this passage in the reader.
If the proposed development maintains pre-development flow conditions, the lawful point of discharge
for the subject site is the existing drainage reserve to the rear of the property Kauri Street kerb and
channel. The proposed lawful point of discharge is considered to be compliant with the criteria outlined
in QUDM 2017 see below: -
1. The proposed development stormwater discharge will not alter the existing site’s
stormwater discharge characteristics.
2. The location of the proposed discharge point is under the lawful control of the local
government.
3. Authority to discharge over affected properties will not be required as the proposed
development will discharge as per existing drainage conditions.
SCG Consulting Engineers Page 6 SCG Ref: 33114(SWMP)
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.