Changed Approval MCU140060.01

of 7

Page text shows just the words. Original shows the document exactly as it was published.

                                                                                    MCU14/0060.01
19.   Prior to the completion of the development, all site surfaces must be effectively
      stabilised using methods which have achieved effective short-term stabilisation and
      which will continue to achieve effective stabilisation in the medium to long-term. For the
      purpose of this condition, an effectively stabilised surface is defined as one that does
      not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully
      erosion or lead to sedimentation, or lead to water contamination.
20.   The supervising engineer and applicant are responsible to ensure that the implemented,
      short and long term, erosion controls measures are effective and regularly maintained to
      cater for all weather conditions.
After Completion of Works
21.   Prior to the commencement of use and the engineering certification of the works by the
      supervising engineer (RPEQ), a combined inspection of the completed works by
      Council’s Inspector/s and the supervising engineer is required. Please contact Council
      on 5329 6244 to arrange the inspection.
Waste
22.   The developer must provide adequate waste storage and disposal facilities.
23.   Refuse bins must not be placed on the existing road formation of Holts Road. A suitably
      sized all-weather pad shall be constructed adjacent the driveway entrances to provide
      for waste bin collection.
1     REFERRAL AGENCIES

Not applicable.
2     ADVISORY NOTES

The following notes are included for guidance and information purposes only and do not form
part of the assessment manager conditions:
Engineering Certification
Council has undertaken an audit check of the submitted plans in relation to the proposed
works. A detailed check of the calculations and drawings has not been undertaken, as they
have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of the
engineering design. Council reserves the right to require further amendments and/or additions
at a later date should design errors become apparent.
General Environmental Advisory Note
The Environmental Protection Act 1994 states that a person must not carry out any activity
that causes, or is likely to cause, environmental harm unless the person takes all reasonable
and practicable measures to prevent or minimise the harm. Environmental harm includes
environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
construction and landscaping phases of this development are to adhere to their ‘general
environmental duty’ to minimise the risk of causing environmental harm.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003.

The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
carries out an activity must take all reasonable and practicable measures to ensure the activity
does not harm Aboriginal cultural heritage.” It is an offence to fail to comply with the duty of
care. Substantial monetary penalties may apply to individuals or corporations breaching this
duty of care. Injunctions may also be issued by the Land and Resources Tribunal, and the
Minister administering the Act can also issue stop orders for an activity that is harming or is

                                                                                      Page 4 of 7
Log in to download the original file

Changed Approval MCU140060.01.pdf · 265 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.