Att 4 - SWMP · MCU21/0117
Figure 3.1 – Existing stormwater network catchment
The peak storm events for the development were modelled in 12D, with the catchment
hydrology configured in accordance the Bureau of Meteorology’s IFD curves (increased by
the climate change factor) for the locality and a minimum time of concentration of 5 minutes
for each catchment. The model was run for the ensemble of storm events for storm durations
up to 12 hours to simulate the pipe hydraulics under a range of different rainfall patterns.
The developed site and the external catchments as described above that have been used
in the modelling are shown below in Table 3.1-Development Catchment Areas.
Table 3.1-Development Catchment Areas
Catchment Area (Ha) Fraction Impervious
C1 0.017 100
C2 0.020 100
C3 0.028 100
Page 8 of 26
P +61 7 5211 1003 A 37 Mary St, Noosaville Qld 4566 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Att 4 - SWMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 5.7 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.