4. 1. C O N S T R U C T I O N P H A S E
4.1.1 Erosion and Sediment Control Measures
During construction it is necessary to manage the stormwater run-off to avoid pollution of
downstream waterways from sediments and gross pollutants from the site. Best practice
erosion and sediment controls shall be installed to minimise the discharge of typically
sediment heavy run-off from the site in accordance with the objectives of Appendix 2 of the
SPP (July 2017) shown below in Figure 4.1.
Figure 4.1 SPP 2017 Construction Phase Stormwater Management Design Objectives
Refer to Appendix A Proposed Development Plans which contains the site-specific ESC Plan
prepared for the development. The measures proposed for the site include:
1. Sediment fencing is to be installed along the northern and eastern boundaries of the
site to capture sediment from leaving the site. Drainage paths are to be inspected to
ensure the sediment fences are not being bypassed as a result.
2. A shakedown area to be installed at the construction entry/exit to the site to minimise
sediment being transported to and from the site.
Page 10 of 26
P +61 7 5211 1003 A 37 Mary St, Noosaville Qld 4566 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Att 4 - SWMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 5.7 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.