Decision Notice - RAL21 0035 [As Published]

of 9

Page text shows just the words. Original shows the document exactly as it was published.

                                                                                   Officer:            Nadine Gorton
                                                                                   Direct Telephone:   07 5329 6215
                                                                                   Our Reference:      RAL21/0035
                                                                                   Your Reference:     n/a

               31 July 2023


               Mr IW Rowe & Ms JR Rowe
               C/- Brennan Planning Pty Ltd
               44 Maple St
               COOROY QLD 4563
               [email protected]



               Dear Sir/Madam,
                                                         Decision Notice
                                                         Planning Act 2016

               I refer to your application and advise that on 24 July 2023, Council decided to approve the
               application, subject to conditions.
               Details of the decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:              RAL21/0035

                   Street address:              21 Jirrima Cresent, Cooroibah

                   Real property description:   Lot 46 RP 136461

                   Planning Scheme:             Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
               •       Development Permit for Reconfiguring a Lot - Rural Residential (1 into 2 Lots)
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

               When Conditions Must Be Complied With
               1.      Unless otherwise stated, all works required by the conditions of this Decision Notice must be
                       completed prior to submission of the subdivision plan to Council for compliance assessment.




               ABN 97.969.214.121                                                                PO Box 141
               noosa.qld.gov.au                                                           Tewantin QLD 4565
               [email protected]                                                           07 5329 6500
                                                                                                            Page 1 of 9
Document Set ID: 22524862
Version: 3, Version Date: 31/07/2023
Log in to download the original file

Decision Notice - RAL21 0035 [As Published].pdf · 161 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 8 pages

Page 2

                      Approved Plans
               2.     Development authorised by this approval must be undertaken generally in accordance with
                      the Approved Plans listed in the table below. The plans must be amended to incorporate the
                      amendments listed within the table below and resubmitted to Council prior to the issue of any
                      Development Permit for Operational Works*

                        Plan No.              Rev.   Plan/Document Name                             Date

                        21-5581AA                    Plan of Proposed Reconfiguration Prepared 18.11.2021
                                                     by Max Watterson and Associates

                      Currency Period
               3.     This development approval lapses if the requirements of the conditions have not been
                      completed and an application for plan seal is not lodged with Council by 24th July 2027,
                      unless an application to extend the currency period is approved by Council.
               4.     All lot numbering on the subdivision plan to be submitted to Council for compliance
                      assessment must remain as shown on the Approved Plans.
                      Building Envelope
               5.     All future dwellings and associated ancillary buildings and structures on proposed Lot 2 must
                      be wholly located within the approved building envelope as shown on the Approved Plans.
                      A copy of the approved Plan of Development must be included in the contract of sale for Lot
                      2, together with a clause which requires future dwellings and associated ancillary buildings
                      and structures to be constructed in accordance with it.
                      The following property notation or similar will be added to Council’s rates records for
                      proposed Lot 2:
                      A house site has been specified for this property as part of the conditions of subdivision
                      approval. The approved site for the construction of a future dwelling and associated ancillary
                      buildings and structures is shown on the attached plan. (refer to Council Approval
                      RAL21/0035).
               6.     The applicant must prepare a metes and bounds building envelope plan indicating the
                      approved building envelope for Lot 2. The areas must be generally in accordance with the
                      approved plans. The plans must be submitted in both hardcopy and digital format (dwg) on
                      GDA 94 zone 56 coordinates. The applicant must submit the plans to Council for approval
                      prior to the endorsement of the Plan of Survey.
               ENGINEERING
                      Site Access and Driveways
               7.     An access driveway must be provided extending from the formation in Jirrima Crescent to
                      the common boundary of proposed Lots 1 and 2. The works must be undertaken in
                      accordance with an Operational Works approval and must include in particular:
                      a.      the works generally as shown on drawings numbered C30-C33 (Revision 2) prepared
                              by RECOR Consulting dated 15 May 2023
                      b.      any sections of the existing gravel formation that will be affected by flooding up to the
                              1% AEP event must be sealed
                      c.      all works must be constructed to achieve the flood immunity and trafficability as
                              described in section 3 of the submitted Stormwater Management Plan – reference
                              20220089 prepared by Recor Consulting dated May 2023
                      d.      any necessary safety measures or warning signage in the proximity of the watercourse
                              crossing
                      e.      underground service conduits for all utility services.



                                                                                                           Page 2 of 9
Document Set ID: 22524862
Version: 3, Version Date: 31/07/2023

Page 3

               8.     The party benefitted by the existing easement (Emt A on SP315440) must provide written
                      approval of the improvements to the access driveway proposed by the applicant. A copy of
                      the approval must be provided to Council as part of the required operational works
                      application.
                      Stormwater Drainage
               9.     Stormwater runoff from the development must be disposed of on-site without causing scour
                      or damage to the subject site or any adjoining property.
                      Services
               10.    Reticulated electricity and telecommunication services must be provided to each lot in
                      accordance with the standards and requirements of the relevant service provider. Any
                      services within the easement for access and services must be provided underground.
               11.    Unless otherwise stipulated by telecommunications legislation at the time of construction, the
                      development must be provided with all necessary conduits, pits and pipes to accommodate
                      the future connection of optic fibre technology telecommunications.
               12.    Certification must be submitted to Council from all relevant service providers (Energex and
                      NBN) which certifies that the development has met the requirements of this Decision Notice
                      and all applicable legislation at the time of construction.
                      Easements
               13.    An easement for access and services must be registered against the title of proposed Lot 1
                      in favour of proposed Lot 2. The easement must be located generally in accordance with the
                      approved plan.
               14.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               15.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               16.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.
                      Earthworks and Retaining Walls
               17.    All earthworks and associated batters must be undertaken in accordance with an Operational
                      Works approval, and contained entirely within the subject site unless written permission from
                      the respective landowner(s) is provided to Council.
                      Damage to Services and Assets
               18.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.




                                                                                                       Page 3 of 9
Document Set ID: 22524862
Version: 3, Version Date: 31/07/2023

Page 4

               ENVIRONMENTAL MANAGEMENT
                      Land Rehabilitation
               19.    A vegetation protection covenant must be registered against the title of the property over the
                      land area identified as riparian protection on the western side of the waterway as well as the
                      10 metre wide rehabilitation area on the eastern side of the waterway pursuant to Section
                      97A of the Land Title Act 1994. The covenant document and a survey plan must be submitted
                      to Council for endorsement prior to lodgement with the relevant titles authority for registration
                      of title. The covenant document must:
                      a.      incorporate the requirements of this Decision Notice
                      b.      include Noosa Council as Covenantee.
                      c.      reference Queensland Land Title Registry Standard Terms Document No. 715597513
                      Works within Protected Land
               20.    The following works must be undertaken within the covenant area in accordance with the
                      conditions of this approval prior to the submission of the sealing of the survey plan:
                      a.      Control of pest plants listed in Planning Scheme Policy 2 Landscaping and Councils
                              Biosecurity Plan 2020 pest plants listed in Schedule 1 part 3, Schedule 2 and non -
                              scheduled invasive species;
                      b.      Removal of any structures, debris or materials foreign to a natural environment
                      c.      Rehabilitation and restoration to achieve the equivalent floristic composition of the pre
                              clearing undisturbed regional ecosystem as per the rehabilitation areas .
                      d.      The planting of canopy species with local provenance in Regional Ecosystem 12.3.14a,
                              including threatened Eucalyptus conglomerata. The trees must be planted at a ratio of
                              1 tree per every 10m².
                      The works must be undertaken in accordance with an Operational Works approval.
               21.    The land area 30 metres west of the defined waterway bank and 10 metres east of the
                      defined bank of the waterway must be rehabilitated and revegetated and removed of all weed
                      species listed in the following standards and legislation:
                      a.      Control of pest plants as listed in Planning Scheme Policy 2 Landscaping and Council’s
                              Biosecurity Plan 2020 pest plants listed in Schedule 1 part 3, Schedule 2 and Non-
                              scheduled invasive species; and
                      b.      The works must be undertaken in accordance with an Operational Works approval.
                      *(Refer to Advisory Note)
               22.    If a provision included in the covenant document is requisitioned or refused registration by
                      the relevant titles authority, a substitute provision must be included in the document which
                      as nearly as practicable addresses the objective sought by the requisitioned or refused
                      provision. The wording of the substitute provision must be agreed by Council.
                      Fencing to Protected Land
               23.    A permanent fence must be constructed along the entire length of the western and eastern
                      covenant boundaries. The fence must be constructed in accordance with an Operational
                      Works approval and must be to the following specifications:
                      a.      Min 1.2 metres high
                      b.      allow adequate clearance at ground level for local macropods
                      c.      not include any use of barbed wire or similar materials
                      d.      be constructed of fire proof materials




                                                                                                          Page 4 of 9
Document Set ID: 22524862
Version: 3, Version Date: 31/07/2023

Page 5

                      e.      include A5 signage with the wording “Vegetation Protection Area – No Domestic
                              animals” every 15m. The signage must be durable, weather resistant and be visually
                              complementary to the natural environment.
                      Bushfire Management – Reconfiguration Requirements
               24.    All reconfiguration works must be carried out in accordance with the Bushfire Hazard
                      Assessment & Management Plan listed within this Decision Notice, with the exception of the
                      following:
                      a.      Appendix A must be updated to the final version which includes a 21 meter wide APZ
                              on the western side of the Lot 2 building envelope.
                      The report must be resubmitted to Council incorporating the above amendments prior to the
                      issue of any Development Permit for Operational Works. *
                      *(Refer Advisory Note)
               25.    Certification must be submitted to Council from a qualified person* which certifies that the
                      development has been constructed in accordance with the bushfire management conditions
                      of this Decision Notice.
                      *(Refer Advisory Note)
               26.    A clause must be included in the contract of sale for Lot 2 which requires future dwellings to
                      be constructed within the building envelopes shown on the Approved Plans listed within this
                      Decision Notice.
               5.     PLANS/ DOCUMENTS REQUIRING AMENDMENT

               The following plans require amendment prior to becoming Approved Plans for the development.

                Plan No.               Rev.      Plan/Document Name                                    Date

                -                      -         Riparian Rehabilitation     Plan,   prepared    by, -
                                                 Equilibrium Ecology

                Amendment              Incorporate the following:
                                              • 30 metres of rehabilitation on the western side of the waterway
                                              • 10 metres of rehabilitation on the eastern side of the waterway
                                              • Vegetation protection covenant over the entire riparian protection area
                                                  on the western side of the waterway
                                              • Vegetation protection covenant over the 10 metres of rehabilitation
                                                  on the eastern side of the waterway
                                       Fauna friendly fencing along the western and eastern boundaries of the
                                       vegetation protection covenant between the covenant and the Lots

                Plan No.               Rev.      Plan/Document Name                                      Date

                                       1         Bushfire Hazard Assessment & Management Plan            3 December
                                                 prepared by, Equilibrium Ecology                        2021

                Amendment                  Appendix A must be updated to the final version which includes a 21-meter
                                           wide APZ on the western side of the Lot 2 building envelope.




                                                                                                           Page 5 of 9
Document Set ID: 22524862
Version: 3, Version Date: 31/07/2023

Page 6

               6.     REFERENCE DOCUMENTS

                Plan No.               Rev.   Plan/Document Name                                     Date

                20220089               -      Stormwater Management Plan prepared by Recor May 2023
                                              Consulting

                C01                    2      Cover sheet and locality Plan Prepared by Recor        15.05.2023

                C30                    2      Proposed Driveway crossover layout and details 15.05.2023
                                              prepared by Recor

                C30                    2      Driveway long sections prepared by Recor               15.05.2023

                C32                    2      Driveway cross sections prepared by Recor              15.05.2023

                C33                    2      Stormwater Long sections prepared by Recor             15.05.2023

               7.     REFERRAL AGENCIES

               Not applicable.
               8.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      Resubmission of Amended Documents Required
               1.     The conditions of this Decision Notice require resubmission of the referenced Bushfire
                      Assessment and Management Plan to Council with amendments. Please address the
                      amended document to Council’s Development Assessment Branch with the Reference No.
                      RAL21/0035, separate to any Operational Works application. To avoid delays and
                      assessment issues with the Operational Works application, it is recommended the document
                      be resubmitted prior to lodgement of any Operational Works application. Should the
                      amended document not be submitted, the applicant is advised that a Preliminary Approval
                      may be issued in lieu of a Development Permit.
                      Qualified Person
               2.     For the purpose of preparing a Rehabilitation Plan, a qualified person is considered to be a
                      landscape architect or ecologist with a minimum of 3 years current experience in the field of
                      landscape design.
               3.     For the purpose of preparing a Bushfire Management Plan, and for certifying compliance
                      with the bushfire requirements of this Decision Notice, a qualified person is considered to be
                      an ecologist with a minimum of 3 years current experience in the field of bushfire assessment
                      and management.
                      Building and Construction Industry (Portable Long Service Leave) Levy
               4.     The QLeave levy must be paid prior to the issue of a development permit where it is required.
                      Council will not be able to issue a Decision Notice without receipt of details that the Levy has
                      been paid.
                      Co-ordination of Operational Works Assessment
               5.     Additional application fees apply to Operational Work applications where the different
                      aspects of the works are lodged separately. Significant savings in application fees will result
                      if all works are lodged in a single application.




                                                                                                        Page 6 of 9
Document Set ID: 22524862
Version: 3, Version Date: 31/07/2023

Page 7

                      Preparation of a Preliminary Construction Management Plan
               6.     A preliminary Construction Management Plan must be submitted with the Operational Works
                      application and must address the following:
                      a.      appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
                              Devices (MUTCD)
                      b.      provision for safe vehicle and pedestrian access across the frontage of the site both
                              during daily construction and after daily construction has ceased.
                      Private Infrastructure
               7.     All private infrastructure for the development must be designed to meet the planning scheme
                      requirements unless otherwise agreed by the relevant authority.
                      Infrastructure Charges
               8.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further       information,     please        refer to https://www.noosa.qld.gov.au/planning-
                      development/development-tools-guidelines/infrastructure-charges
               9.     PROPERTY NOTES

               The following property notes will be placed against the subject property in Council’s property record
               system:
                      RAL21/0035 – Vegetation Protection Covenant
               1.     The following notation applies to approved lot 1:
                      A Vegetation Protection Covenant applies to this lot. No clearing of vegetation is to occur
                      within the covenanted area, except where in accordance with the terms of the covenant.
                      RAL21/0035 – Bushfire Management
               2.     The following notation applies to approved lot 2:
                      To ensure the safety of people and property on this property is maintained, all buildings and
                      structures must be sited and constructed in accordance with the bushfire management
                      conditions of Council Approval RAL21/0035 and associated Operational Work approvals
                      RAL21/0035 – BUILDING ENVELOPE
               3.     The following notation applies to approved lot 2:
                      A house site has been specified for this property as part of the conditions of subdivision
                      approval. The approved site for the construction of a future dwelling and associated ancillary
                      buildings and structures is shown on the attached plan. (refer to Council Approval
                      RAL21/0035).
               10.    VARIATION APPROVAL DETAILS

               Not applicable.
               11.    FURTHER DEVELOPMENT PERMITS REQUIRED

                Type of Development Permit Required              Subject of the required Development Permit

                Development Permit for Operational Works         Road work, Stormwater, Drainage work,
                                                                 Earthworks, Landscaping, Signage, Vegetation
                                                                 Clearing.

               12.    SUBMISSIONS

               Not applicable.


                                                                                                       Page 7 of 9
Document Set ID: 22524862
Version: 3, Version Date: 31/07/2023

Page 8

               13.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If
               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.
               14.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available on line at
               www.noosa.qld.gov.au or at Council Offices.


               Yours faithfully,




               Nadine Gorton
               Acting Coordinator Planning



               Enc:   Appeal Rights
                      Infrastructure Charge Notice
                      Approved Plans/Documents
               cc.    Unitywter




                                                                                                       Page 8 of 9
Document Set ID: 22524862
Version: 3, Version Date: 31/07/2023

Page 9

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                   (b) succinctly states the grounds of the appeal.                           (2) However, the P&E Court may hear and decide an appeal even if
                                                                                                  the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                    Page 9 of 9
Document Set ID: 22524862
Version: 3, Version Date: 31/07/2023

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.