Skip to the record
The definitive source for everything Noosa Council.

Original source · versioned page text

2021-03-15 GC Agenda - Item 9 - Attachment 5 - MCU19-0114 & RAL19 0027 Infrastructure Agreement (44 pages)

of 44

Page text shows just the words. Original shows the document exactly as it was published.

Very large file: it may take a few minutes

The original of this document is very large (38.9 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

                                                                  13



                7.4         If the Council decides to apply the Security to complete the uncompleted
                            Works Contributions it may enter the Land for that purpose.
                7.5         The Council must return the Security (or the reduced amount of the Security
                            if the Security has already been called upon) within 10 business days after
                            the Works Contributions are completed.


                8.          Dispute resolution generally
                8.1         Dispute
                            If there is a dispute between the parties, a party may give a Dispute Notice
                            referring the dispute for determination by the Expert.
                8.2         Notice as bar
                            The giving of a Dispute Notice operates as a complete and unconditional bar
                            and waiver to the commencement of a proceeding or any litigation in respect
                            of a dispute until after the actions in this clause 9 have been taken and
                            followed.
                8.3         Identity of expert
                            If within 14 Calendar Days from the giving of a Dispute Notice the parties
                            are not able to agree on the identity of the Expert, the Expert is to be
                            appointed at the request of any party by the President for the time being of
                            the Queensland Law Society Incorporated.
                8.4         Experience and expertise
                            The Expert is to be a qualified civil engineer with extensive experience in
                            dispute resolution and construction practices.
                8.5         Non arbitrator
                            The Expert is to determine the procedure to be adopted to determine the
                            dispute and is to act as an expert and not as an arbitrator.
                8.6         Submissions
                            (a)        A party may make a submission to the Expert in respect of the dispute
                                       within 14 Calendar Days after the appointment of the Expert.
                            (b)        A party making a submission to the Expert in respect of the dispute is
                                       to give a copy of the submission to each other party within 7 Calendar
                                       Days after the submission is given to the Expert.
                            (c)        The Expert is to take account of any submission received in respect of
                                       the dispute under clause 9.6(a).
                8.7         Costs
                            The parties are to pay the Expert’s costs (including the cost of engaging and
                            consulting advisers) equally.




Document Set ID: 21379346
Version: 1, Version Date: 27/01/2021
Log in to download the original file

2021-03-15 GC Agenda - Item 9 - Attachment 5 - MCU19-0114 & RAL19 0027 Infrastructure Agreement (44 pages)(PDF, 37MB).pdf · 38.9 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.