8.8 Co-operation
(a) The parties are to at all times do all things which the Expert requires of
them in respect of the Expert’s determination of the dispute and are to
co-operate and assist the Expert in every reasonable way.
(b) A party is not to wilfully do or cause to be done any act to delay or
prevent the determination of the dispute by the Expert.
8.9 Determination
The Expert’s determination:
(a) is to be made within 14 Calendar Days after the earlier of:
(i) each party has made a submission to the Expert in respect of the
dispute;
(ii) the expiry of the time for a party to make a submission to the
Expert in respect of the dispute;
(b) is to be given in writing as soon as possible;
(c) is to contain the reasons for the making of the determination;
(d) is final and binding on the parties.
9. Force Majeure
9.1 Notice of Force Majeure
If a party is unable by reason of Force Majeure to perform and fulfil an
obligation, the party is to, as soon as is reasonably practicable after the Force
Majeure, give to each other party a Notice which states the following:
(a) that Force Majeure is in existence; and
(b) full particulars of the Force Majeure.
9.2 Suspension of an obligation
An obligation of a party so far as it is affected by Force Majeure is suspended
during the following:
(a) the continuance of Force Majeure; and
(b) a further period which is reasonable in the circumstances.
9.3 Removal or amelioration of Force Majeure
The party giving a Notice of Force Majeure is to, as soon as is reasonably
practicable, use its best endeavours to remove the Force Majeure or
ameliorate its effect.
9.4 Dispute resolution process to apply
If the parties are unable to agree on the existence of a party’s Force Majeure
or the period during which an obligation is suspended during the continuance
of Force Majeure the dispute is to be resolved under clause 9.
Document Set ID: 21379346
Version: 1, Version Date: 27/01/2021
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.