Appendix F. Civil Engineering Report Part 2

Attached to the e-mail Retail Bus Type 5 & Type 2 & Op Works -Civil Eng Report Pt 2 MCU17/0572 & OPW17/0611.

of 138

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (11.0 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Original PDF page 23, section 1. The text section number identifies this passage in the reader.

Noosa Shire Council – The Noosa Plan
Erosion and Sediment Control Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                                           ACCEPTABLE OUTCOMES                                          COMMENTS

  14.124 Effects of works
 Erosion and drainage control, sediment capture                 S1.1
 and stormwater runoff                                          Construction works are designed, planned and
                                                                                                                                               ✓
 O1                                                             executed with respect to the principles of erosion
                                                                reduction, drainage management and sediment capture
 Development design, density, layout, and staging provide for   in accordance with Appendix 2, Table A of the                To be complied with at detailed
 erosion control, drainage control and sediment capture and     Queensland State Planning Policy and International           design / construction stages.
 treatment during the construction phase.                       Erosion Control Association Best Practice Erosion and
                                                                Sediment Control (BPESC) 2008;
                                                                S1.2                                                                           ✓
                                                                Construction works are designed and managed to restrict
                                                                the extent of clearing and soil exposure to that necessary
                                                                for access, and safe construction;                           To be complied with at detailed
                                                                                                                             design / construction stages.
                                                                                                                             Refer to civil engineering report, in
                                                                                                                             specific stormwater quality section
                                                                                                                             prepared by this office.
                                                                 S1.3                                                                          ✓
                                                                 Clean stormwater is diverted or managed around or
                                                                 through the site without increasing the concentration of
                                                                 total suspended solids or other contaminants in the flow    To be complied with at detailed
                                                                 and without causing erosion (onsite or offsite);            design / construction stages.
                                                                                                                             Refer to civil engineering report, in
                                                                                                                             specific stormwater quality section
                                                                                                                             prepared by this office.




 Solution:    ✓     =   Acceptable Solution
              A/S   =   Alternative Solution
              N/A   =   Not applicable to this proposal


Page 1 of 3
July 2017
Log in to download the original file

Appendix F. Civil Engineering Report Part 2.pdf · 11.0 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗