Appendix F. Civil Engineering Report Part 2
Attached to the e-mail Retail Bus Type 5 & Type 2 & Op Works -Civil Eng Report Pt 2 MCU17/0572 & OPW17/0611.
The original of this document is very large (11.0 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Original PDF page 52, section 1. The text section number identifies this passage in the reader.
State Planning Policy (April 2016)
Appendix 3, SPP Code: Water Quality
Construct to avoid/minimise new impacts
PO6 AO6.1
Construction activities An erosion and sediment control plan (ESCP) An erosion and sediment
for the development demonstrates that release of sediment-laden control plan (ESCP) will
avoid or minimise stormwater is avoided for the nominated design be prepared as part of a
adverse impacts on storm, and minimised when the nominated design future operational works
stormwater quality. storm is exceeded, by addressing design objectives application.
listed below in Table A (construction phase) or local
equivalent, for:
a. drainage control, and
b. erosion control, and
c. sediment control, and
d. water quality outcomes, and
AO6.2 A06.2 – N/A
Erosion and sediment control practices (including any
proprietary erosion and sediment control products)
are designed, installed, constructed, operated,
monitored and maintained, and any other erosion
and sediment control practices are carried out in
accordance with local conditions and appropriate
recommendations from a suitably qualified person, or
AO6.3 A06.3 – N/A
The ESCP demonstrates how stormwater quality will
be managed in accordance with an acceptable
regional or local guideline so that target contaminants
are treated to a design objective at least equivalent to
Acceptable Outcome AO6.1.
PO7 AO7.1
Operational activities Development incorporates stormwater flow control Further details of
for the development measures to achieve the design objectives set out construction controls will
avoid or minimises below in Table A (construction phase) and Table B be provided as part of
changes to waterway (post construction phase). Both the construction and future operational works
hydrology from operational phases for the development comply with applications. Please
adverse impacts of design objectives in Table A (construction phase), refer to the ADG
altered stormwater and Table B (post construction phase), or current Engineers Civil
quality and flow. best practice environmental management, including Engineering Report for
management of frequent flows, peak flows, and operational compliance.
construction phase hydrological impacts.
PO8 AO8.1
Any treatment and See AO2.1 Not applicable.
disposal of waste Development does not
water to a waterway include on-site waste
accounts for: water treatment. Existing
Council sewer
• the applicable water
infrastructure to service
quality objectives for the proposed
the receiving waters, development.
and
• adverse impact on
ecosystem health or
receiving waters,
Project Address – Project Description
ADG Engineers Aust. Pty Ltd
Page 3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.