Appendix C - Stormwater Management Report
Original PDF page 11, section 1. The text section number identifies this passage in the reader.
CONCLUSION
This Concept Stormwater Management Report has outlined how the stormwater run-off from the site is to be
managed to comply with the relevant requirements to minimise any adverse impacts to the downstream catchments.
• The legal point of discharge for the proposed development is the existing inlet at the north-eastern corner
of the site.
• Both stormwater quality and quantity for the operational phase of the proposed development have
previously been managed as part of the subdivision creating the individual lots (RAL2007/165). The existing
end of line treatment including detention basin and bioretention basin achieve the stormwater objectives
for the proposed development, therefore no additional management is required for the proposed
development.
• During construction, erosion and sediment control measures in accordance with best practice standards are
to be implemented to minimise potential contaminants impacting the downstream receiving environment.
An erosion and sediment control plan shall be developed as part of a submission for Operational Works
approvals.
• The proposed stormwater solution is considered to minimise any adverse impacts to the downstream
environment arising from the stormwater run-off while also meeting the stormwater quality targets required
for the development.
Project number 20210216 Page 11 of 13
File RECOR Preliminary Stormwater Management Report - 20210216.docx, 2022-02-01
Revision 0
P +61 7 5211 1003 A 37 Mary St, Noosaville Qld 4566 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.