Existing submains running to the existing Distribution boards located in the Clubhouse and
Maintenance shed will need to be located to ensure that no essential services (Water Pumps) are
disturbed during the proposed works.


NBN / TELECOMMUNICATIONS
The site has an existing NBN fibre connection located in the shed with the MSB. This connection
should be suitable for the proposed use for site.


PROPOSED SITE RETICLUATION
The site has existing bore pumps which will need to be maintained and reinstated when the new
MSB and Substation are installed. There are 2 existing maintenance sheds which will remain as is.
These will need to be reconnected to the new MSB. The Distribution boards in the maintenance
sheds don’t need to be upgraded unless there are going to be modifications. In the case of
modifications both boards will need to be removed and new supplied to suit.


New submains will need to be run from the new MSB to the Distribution Boards for the following
proposed areas:
Staff Area
Rec Area
Kitchen and Dining area
Village 1
Village 2
Village 3
Submains to these new Boards can be run either underground or overhead via a series of property
poles.


SITE MAXIMUM DEMAND
A very preliminary calculation based on floor area has been done for site maximum demand which
takes the following into consideration
3x Villages with Air conditioning in both sleeping and activity areas
A new Kitchen suitable for providing for over 300 people.
Staff area with Air conditioning
Main dining and Rec Room area all with Air conditioning.
The estimated maximum demand for site is 550A - 750A three phase.
This is very preliminary and will become more apparent during design phase.
                                                    2
                                                                                   © RCA Consulting 2022
Log in to download the original file

Att10 - Electrical Services Plans.pdf · 1.4 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.