RA6-N Response with conditions 2005-16658 SRA (approved plan version)

Attached to the e-mail SARA Referral agency response with conditions - MCU20/0027 & RAL20/0004.

of 7
                                                                                                2005-16658 SRA




Attachment 2—Advice to the applicant

General advice
1.            Terms and phrases used in this document are defined in the Planning Act 2016 its
              regulation or the State Development Assessment Provisions (SDAP) v2.6. If a word
              remains undefined it has its ordinary meaning.

Stormwater condition
2.            The concurrence agency conditions include a requirement for the Applicant to provide
              RPEQ certification to the District Director (North Coast District) within the Department of
              Transport and Main Roads addressing stormwater drainage impacts from the development
              to the state-controlled road (Cooroy Connection Road).

              Please ensure that any submission is addressed to the District Director (North Coast
              District) within the Department of Transport and Main Roads is sent to
              [email protected] and contains sufficient supporting hydraulic
              calculations/documentation to address stormwater management relative to the state-
              controlled road.

              For any queries or further information about this matter, please contact the Department of
              Transport and Main Roads’ Maroochydore Office via email to
              [email protected] and quote 'TMR20-030017'.

Roadworks in a state-controlled road
3.            It is noted in the submitted stormwater report that road works, specifically the installation of
              a 450mm diameter stormwater pipe, is proposed within the state-controlled road corridor.

              Under Section 33 of the Transport Infrastructure Act 1994, written approval is required
              from the Department of Transport and Main Roads to carry out road works on a state-
              controlled road. Road works includes the installation of stormwater related infrastructure.

              This approval must be obtained prior to commencing any works on the state-controlled
              road reserve. The approval process takes time and will require the approval of engineering
              designs of the proposed works, certified by a Registered Professional Engineer of
              Queensland (RPEQ).

              It is highly recommended that you contact the Department of Transport and Main Roads’
              as soon as possible to ensure that gaining approval does not delay construction.




State Assessment and Referral Agency                                                                Page 4 of 7

Log in to download the original (RA6-N Response with conditions 2005-16658 SRA (approved plan version).pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.