Construction Management Plan_OPW25_0036_45 Cormorat Crescent Peregian Beach
Plans and drawings: the text below has words only, no drawings.
- Verge reinstated with 100mm topsoil and turf/seed.
- No removal of street trees without approval.
5. Environmental Controls
- Prescribed water contaminants must not enter stormwater.
- Erosion and sediment controls in place per best practice.
- Exposed soil areas to be stabilised before rainfall.
- Runoff must not affect neighbouring properties or road.
6. Public Safety and Signage
- Safety fencing and mesh installed during excavation and pour.
- Signage in accordance with TGS.
- Maintain access and reinstate kerb and verge areas to match existing.
7. Utility and Service Coordination
- Clearance of 500mm from Unitywater/Energex/Telstra assets unless otherwise approved.
- Service conflicts to be resolved with authority before commencement.
- Public liability and works insurance certificates submitted pre-start.
8. Neighbour Communication
- Neighbours notified at least 5 business days prior to start.
- Notice includes scope, duration, contacts, and impacts.
9. Emergency Contacts
Builder Gold Leaf Constructions 0407 778 238 [email protected]
Site Supervisor Ashley Spooner 0401 327 365 [email protected]
Project Manager Klint Grabbe 0474 764 761 [email protected]
-
Noosa Shire Council - (07) 5329 6500 [email protected]
Dial Before You Dig - 1100 www.1100.com.au
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.