Decision Notice - Concurrence Agency - Q.T (Maritime Safety) [As Published] · 142008.1704
2008/1704
SCE07-67 1H of 38 Fixed Jetty & Regatta Stair Layout – Schwabe 13 March
Consulting Engineers 2009
SCE07-67 2H of 38 Fixed Jetty & Regatta Stair Fixity Details – 13 March
Schwabe Consulting Engineers 2009
and as may be amended by these conditions.
2. The level of the jetty deck shall not exceed RL1.06 AHD (Highest Astronomical Tide plus
500mm).
3. The pontoon must not exceed the maximum dimensions of 7 metres in length and 2 metres in
width.
4. The overall length of the regatta stairs shall not exceed the overall length of the pontoon.
5. The regatta stairs shall be of open construction as indicated on the Kidd and Co Designers’
architectural plan and shall not have vertical riser timbers as indicated on Schwabe Consulting
Engineers’ plans.
6. The regatta stairs shall be constructed as close as reasonably possible to the face of the rock
revetment wall.
7. All structures associated with the jetty and pontoon, including piles, must be constructed
wholly within the approved Resource Entitlement Area.
8. All parts of the existing jetty including paths and supporting elements below water level must
be completely removed.
9. A rigid handrail shall be fitted on one side of the jetty.
10. No posts or vertical supports of the proposed jetty are to extend vertically from the structure
unless they provide support for the handrails.
11. No boat lifting devices are to be attached or moored at the jetty structure for the purpose of
elevating a vessel above the water without Council approval.
12. The jetty shall be constructed in a manner to render the underside area vermin proof.
13. There shall be no electrical reticulation system carrying electricity in excess of 24 volts beyond
the revetment wall.
14. Lighting associated with the use shall be designed, installed, operated, and maintained in
accordance with Section 3 of AS4282 Control of the Obtrusive Effects of Outdoor Lighting.
15. The jetty and pontoon are to be used for private purposes only with no commercial operations
to be undertaken.
16. Boat repair activities will not be permitted on site.
17. Wastewater and sullage shall only be disposed of at approved pump out facilities.
18. The mooring facility shall not be utilised for live-aboard purposes.
19. Any construction and post construction activity is not to impact on the condition of the
waterway, and is to be conducted so as not to breach the Environmental Protection Act (EPA)
1994 and the Environmental Protection (Water) Policy 1997.
20. The approval or conditions do not constitute a ruling on structural safety and the applicant
must make their own arrangements to ensure adequacy of design and work. This approval
does not warrant that such plans and specifications have been checked in detail, nor does it
absolve the owner of the land from complying with all the conditions of this approval and/or
relevant Council By-Laws and Policies and/or relevant statutes and/or statutory regulations in
the execution and/or performance of said works. The Council does not accept any
responsibility for the accuracy of such plans and specifications as approved.
Page 2 of 13
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Concurrence Agency - Q.T (Maritime Safety) [As Published]Related documentApplication case desk ↗
001A63BA.002.pdfRelated documentPublic source context ↗
About this file
- File size
- 3.1 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.