Skip to the record
Search everything, all in one place.

Original source · versioned page text

Seaview Terrace Target Program Rev 2 MM

Attached to the e-mail MCU14/0084 & OPW16/0021 Construction Management Plan - 71 Seaview Terrace.

of 6

Page text shows just the words. Original shows the document exactly as it was published.

                                                                                                                                                                     SEAVIEW TERRACE
                                                                                                                                                              CONSTRUCTION PROGRAM - TARGET
                                                                                                                                                                          DRAFT
ID           Task Name                                                            Duration   Start          Finish              July      August September
                                                                                                                                                       OctoberNovember
                                                                                                                                                                    December
                                                                                                                                                                          January February
                                                                                                                                                                                         March April                 May      June    July    August September
                                                                                                                                                                                                                                                           OctoberNovember
                                                                                                                                                                                                                                                                        December
                                                                                                                                                                                                                                                                              January February
                                                                                                                                                                                                                                                                                             March April    May       June    July    August September
                                                                                                                                                                                                                                                                                                                                                   OctoberNovember
                                                                                                                                                                                                                                                                                                                                                                 December
                                                                                                                                                                                                                                                                                                                                                                       January February
                                                                                                                                                                                                                                                                                                                                                                                      Ma
                                                                                                                                  Jul      Aug    Sep    Oct   Nov   Dec    Jan    Feb     Mar  Apr                   May       Jun     Jul    Aug    Sep    Oct   Nov   Dec    Jan    Feb    Mar   Apr      May        Jun     Jul    Aug    Sep    Oct   Nov    Dec    Jan    Feb
     1       KEY DATES                                                            540 days   Tue 9/08/16    Thu 25/10/18                                                                                                                                                                                                                                  KEY DATES
     2          Op Works Approval                                                 0 days     Tue 9/08/16    Tue 9/08/16                     Op Works Approval
     3          Site Possession                                                   0 days     Tue 23/08/16 Tue 23/08/16                          Site Possession
     4          Target Practical Completion                                       0 days     Thu 27/09/18 Thu 27/09/18                                                                                                                                                                                                                              Target Practical Completion
     5          Trade / Weather Delays                                            4 wks      Fri 28/09/18   Thu 25/10/18                                                                                                                                                                                                                                  Trade / Weather Delays
     6          Completion                                                        0 days     Thu 25/10/18 Thu 25/10/18                                                                                                                                                                                                                                     Completion
     7
     8       OPWORKS HOLD POINTS / INSPECTIONS                                    10 days    Tue 9/08/16    Tue 23/08/16                        OPWORKS HOLD POINTS / INSPECTIONS
     9          Notify Council for Prestart (5 Days Notice)                       0 days     Thu 11/08/16 Thu 11/08/16                       Notify Council for Prestart (5 Days Notice)
     10         Prestart Meeting                                                  0 days     Thu 18/08/16 Thu 18/08/16                         Prestart Meeting
     11         Issue copies of Signed Engineering Drawings to Council            0 days     Thu 18/08/16 Thu 18/08/16                         Issue copies of Signed Engineering Drawings to Council
     12         Issue copy of Builders Insurances                                 0 days     Thu 18/08/16 Thu 18/08/16                         Issue copy of Builders Insurances
     13         Issue Construction Management Plan                                0 days     Thu 18/08/16 Thu 18/08/16                         Issue Construction Management Plan
     14         RPEQ Earthwork Report                                             0 days     Thu 18/08/16 Thu 18/08/16                         RPEQ Earthwork Report
     15         Install Open Space Conservation Fence                             0 days     Tue 16/08/16 Tue 16/08/16                        Install Open Space Conservation Fence
     16         Issue Landscape Installation Confirmation [Prior to Use]          0 days     Tue 9/08/16    Tue 9/08/16                     Issue Landscape Installation Confirmation [Prior to Use]
     17         RPEQ Inspect Erosion and Sediment Control                         0 days     Mon 22/08/16 Mon 22/08/16                         RPEQ Inspect Erosion and Sediment Control
     18         Council Inspect Erosion and Sediment Control                      0 days     Tue 23/08/16 Tue 23/08/16                          Council Inspect Erosion and Sediment Control
     19         Issue Bio Retention Basin Dissipators Design to Council           0 days     Tue 9/08/16    Tue 9/08/16                     Issue Bio Retention Basin Dissipators Design to Council
     20         Council Inspection of Impervious Liner to Bio Retention Basins    0 days     Tue 9/08/16    Tue 9/08/16                     Council Inspection of Impervious Liner to Bio Retention Basins
     21         Submit As-Constructed Drawings to Council                         0 days     Tue 9/08/16    Tue 9/08/16                     Submit As-Constructed Drawings to Council
     22
     23      PROCUREMENT / FABRICATION                                            130 days   Tue 9/08/16    Thu 23/02/17                                                                             PROCUREMENT / FABRICATION
     24         STRUCTURAL STEEL                                                  50 days    Tue 9/08/16    Wed 19/10/16                                       STRUCTURAL STEEL
     25            Procure Structural Steel                                       2 wks      Tue 9/08/16    Tue 23/08/16                       Procure Structural Steel
     26            Structural Steel Shop Drawings                                 2 wks      Wed 24/08/16 Tue 6/09/16                              Structural Steel Shop Drawings
     27            Submit Structural Steel Shop Drawings for Approval             0 days     Tue 6/09/16    Tue 6/09/16                             Submit Structural Steel Shop Drawings for Approval
     28            Structural Steel Shop Drawings Approval                        2 wks      Wed 7/09/16 Tue 20/09/16                                  Structural Steel Shop Drawings Approval
     29            Fabricate Structural Steel                                     4 wks      Wed 21/09/16 Wed 19/10/16                                         Fabricate Structural Steel
     30            Fabricate Steel Stair Treads                                   6 wks      Wed 7/09/16 Wed 19/10/16                                          Fabricate Steel Stair Treads
     31         ALUMINIUM WINDOWS                                                 90 days    Tue 9/08/16    Wed 14/12/16                                                       ALUMINIUM WINDOWS
     32            Procure Aluminium Windows                                      2 wks      Tue 9/08/16    Tue 23/08/16                       Procure Aluminium Windows
     33            Aluminium Window Shop Drawings                                 3 wks      Wed 24/08/16 Tue 13/09/16                               Aluminium Window Shop Drawings
     34            Submit Aluminium Window Shop Drawings                          0 days     Tue 13/09/16 Tue 13/09/16                                Submit Aluminium Window Shop Drawings
     35            Approve Aluminium Window Shop Drawings                         3 wks      Wed 14/09/16 Wed 5/10/16                                      Approve Aluminium Window Shop Drawings
     36            Fabricate Aluminium Windows                                    10 wks     Thu 6/10/16    Wed 14/12/16                                                      Fabricate Aluminium Windows
     37         CABINETWORK                                                       90 days    Tue 9/08/16    Wed 14/12/16                                                       CABINETWORK
     38            Procure Cabinetwork                                            2 wks      Tue 9/08/16    Tue 23/08/16                       Procure Cabinetwork
     39            Cabinetwork Shop Drawings                                      3 wks      Wed 24/08/16 Tue 13/09/16                               Cabinetwork Shop Drawings
     40            Submit Cabinetwork Shop Drawings                               0 days     Tue 13/09/16 Tue 13/09/16                                Submit Cabinetwork Shop Drawings
     41            Approva Cabinetwork Shop Drawings                              3 wks      Wed 14/09/16 Wed 5/10/16                                      Approva Cabinetwork Shop Drawings
     42            Fabricate Cabinetwork                                          10 wks     Thu 6/10/16    Wed 14/12/16                                                      Fabricate Cabinetwork
     43         PROCURE LIFT                                                      130 days   Tue 9/08/16    Thu 23/02/17                                                                             PROCURE LIFT
     44            Procure Lift                                                   2 wks      Tue 9/08/16    Tue 23/08/16                       Procure Lift
     45            Lift Shop Drawings                                             2 wks      Wed 24/08/16 Tue 6/09/16                              Lift Shop Drawings
     46            Submit Lift Shop Drawings                                      0 days     Tue 6/09/16    Tue 6/09/16                             Submit Lift Shop Drawings
     47            Approve Lift Shop Drawings                                     2 wks      Wed 7/09/16 Tue 20/09/16                                  Approve Lift Shop Drawings
     48            Manufacture / Deliver Lift                                     20 wks     Wed 21/09/16 Thu 23/02/17                                                                               Manufacture / Deliver Lift
     49         PROCURE HEMPCRETE                                                 80 days    Tue 9/08/16    Wed 30/11/16                                                   PROCURE HEMPCRETE
     50            Prepare Shop Drawings [NRA]                                    2 wks      Tue 9/08/16    Tue 23/08/16                       Prepare Shop Drawings [NRA]
     51            Fabrication and Delivery                                       14 wks     Wed 24/08/16 Wed 30/11/16                                                     Fabrication and Delivery
     52      ESTABLISHMENT                                                        15 days    Tue 9/08/16    Tue 30/08/16                          ESTABLISHMENT
     53         SITE ESTABLISHMENT                                                15 days    Tue 9/08/16    Tue 30/08/16                          SITE ESTABLISHMENT
     54            Dilapidation Survey                                            1 wk       Tue 9/08/16    Mon 15/08/16                     Dilapidation Survey
     55            Services Identification                                        1 wk       Tue 9/08/16    Mon 15/08/16                     Services Identification
     56            Establish Sheds                                                1 wk       Wed 24/08/16 Tue 30/08/16                           Establish Sheds
     57            Esrtablish Fences                                              1 wk       Wed 24/08/16 Tue 30/08/16                           Esrtablish Fences


                                     Task                                  Summary                                   External Milestone                              Inactive Summary                                Manual Summary Rollup                     Finish-only                           Critical Split
Project: Seaview Terrace Program
                                     Split                                 Project Summary                           Inactive Task                                   Manual Task                                     Manual Summary                            Deadline                              Progress
Date: Fri 5/08/16
                                     Milestone                             External Tasks                            Inactive Milestone                              Duration-only                                   Start-only                                Critical

                                                                                                                                                                                            Page 1
Log in to download the original file

Seaview Terrace Target Program Rev 2 MM.pdf · 654 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 5 pages

Page 2

                                                                                                                                                 SEAVIEW TERRACE
                                                                                                                                          CONSTRUCTION PROGRAM - TARGET
                                                                                                                                                      DRAFT
ID           Task Name                                      Duration   Start          Finish              July      August September
                                                                                                                                  OctoberNovember
                                                                                                                                                December
                                                                                                                                                      January February
                                                                                                                                                                     March April         May        June     July      August September
                                                                                                                                                                                                                                    OctoberNovember
                                                                                                                                                                                                                                                 December
                                                                                                                                                                                                                                                       January February
                                                                                                                                                                                                                                                                      March April    May       June    July    August September
                                                                                                                                                                                                                                                                                                                            OctoberNovember
                                                                                                                                                                                                                                                                                                                                         December
                                                                                                                                                                                                                                                                                                                                               January February
                                                                                                                                                                                                                                                                                                                                                              Ma
                                                                                                            Jul      Aug    Sep     Oct    Nov   Dec    Jan    Feb     Mar  Apr           May         Jun      Jul      Aug    Sep    Oct   Nov   Dec    Jan    Feb    Mar   Apr      May        Jun     Jul    Aug    Sep    Oct   Nov   Dec    Jan    Feb
     58         OFF-SITE ESTABLISHMENT                      5 days     Fri 19/08/16   Thu 25/08/16                         OFF-SITE ESTABLISHMENT
     59            Install Fences                           2 days     Fri 19/08/16   Mon 22/08/16                       Install Fences
     60            Install Shed                             3 days     Tue 23/08/16 Thu 25/08/16                          Install Shed
     61      CONSTRUCTION                                   516 days? Mon 15/08/16 Thu 27/09/18                                                                                                                                                                                                                             CONSTRUCTION
     62         CIVIL WORKS                                 225 days   Mon 15/08/16 Tue 18/07/17                                                                                                                     CIVIL WORKS
     63            REVETMENT RL51.0                         49 days    Wed 24/08/16 Tue 1/11/16                                             REVETMENT RL51.0
     64              Wall A                                 6 days     Wed 24/08/16 Wed 31/08/16                           Wall A
     65              Wall B                                 3 days     Thu 1/09/16    Mon 5/09/16                            Wall B
     66              Wall C                                 2 days     Tue 6/09/16    Wed 7/09/16                            Wall C
     67              Wall D                                 3 days     Thu 8/09/16    Mon 12/09/16                            Wall D
     68              Wall E                                 4 days     Tue 13/09/16 Fri 16/09/16                                Wall E
     69              Wall F                                 31 days    Mon 19/09/16 Tue 1/11/16
     70            REVETMENT RL49.10                        31 days    Wed 2/11/16 Wed 14/12/16                                                          REVETMENT RL49.10
     71              Wall G                                 3 days     Wed 2/11/16 Fri 4/11/16                                              Wall G
     72              Wall H                                 7 days     Mon 7/11/16 Tue 15/11/16                                               Wall H
     73              Wall I                                 5 days     Wed 16/11/16 Tue 22/11/16                                                Wall I
     74              Wall J                                 4 days     Wed 23/11/16 Mon 28/11/16                                                 Wall J
     75              Wall K                                 3 days     Tue 29/11/16 Thu 1/12/16                                                      Wall K
     76              Wall L                                 2 days     Fri 2/12/16    Mon 5/12/16                                                     Wall L
     77              Wall M                                 1 day      Tue 6/12/16    Tue 6/12/16                                                     Wall M
     78              Wall N                                 3 days     Wed 7/12/16 Fri 9/12/16                                                         Wall N
     79              Wall O                                 1 day      Mon 12/12/16 Mon 12/12/16                                                       Wall O
     80              Wall P                                 2 days     Tue 13/12/16 Wed 14/12/16                                                         Wall P
     81            REVETMENT RL 44.3                        20 days    Fri 27/01/17   Thu 23/02/17                                                                         REVETMENT RL 44.3
     82              Wall Q                                 4 days     Fri 27/01/17   Wed 1/02/17                                                                  Wall Q
     83              Wall R                                 5 days     Thu 2/02/17    Wed 8/02/17                                                                    Wall R
     84              Wall S                                 3 days     Thu 9/02/17    Mon 13/02/17                                                                    Wall S
     85              Wall T                                 5 days     Tue 14/02/17 Mon 20/02/17                                                                        Wall T
     86              Wall U                                 2 days     Tue 21/02/17 Wed 22/02/17                                                                           Wall U
     87              Wall V                                 1 day      Thu 23/02/17 Thu 23/02/17                                                                           Wall V
     88            PILING                                   59 days    Wed 26/04/17 Tue 18/07/17                                                                                                                     PILING
     89              Pool Screw Piling                      6 days     Wed 26/04/17 Thu 4/05/17                                                                                            Pool Screw Piling
     90              Basement Screw Piling                  6 days     Fri 23/06/17   Fri 30/06/17                                                                                                            Basement Screw Piling
     91              Level 1 Screw Piling                   12 days    Mon 3/07/17 Tue 18/07/17                                                                                                                      Level 1 Screw Piling
     92            EXCAVATION                               166 days   Mon 15/08/16 Mon 24/04/17                                                                                         EXCAVATION
     93              Site Prep / Turnaround                 1 wk       Mon 15/08/16 Mon 22/08/16
     94              Bulk Excavation to RL44.00             4 wks      Thu 15/12/16 Wed 25/01/17                                                                  Bulk Excavation to RL44.00
     95              Bulk Excavation to RL39.00             4 wks      Fri 24/02/17   Thu 23/03/17
     96              Excavate Pool Area to RL36.00          4 wks      Fri 24/03/17   Mon 24/04/17                                                                                      Excavate Pool Area to RL36.00
     97              Excavate Tanks                         1 wk       Fri 24/03/17   Thu 30/03/17
     98            BACKFILL                                 4 days     Mon 19/06/17 Thu 22/06/17                                                                                                             BACKFILL
     99              Backfill Basement / Pool               4 days     Mon 19/06/17 Thu 22/06/17                                                                                                            Backfill Basement / Pool
 100            STRUCTURAL WORKS                            219 days   Fri 5/05/17    Tue 3/04/18                                                                                                                                                                             STRUCTURAL WORKS
 101               POOL BASEMENT RL36.00                    27 days    Fri 5/05/17    Mon 12/06/17                                                                                                      POOL BASEMENT RL36.00
 102                 Excavate Footings                      2 days     Fri 5/05/17    Mon 8/05/17                                                                                              Excavate Footings
 103                 Reinforce Footings                     2 days     Tue 9/05/17    Wed 10/05/17                                                                                             Reinforce Footings
 104                 Pour Footings                          1 day      Thu 11/05/17 Thu 11/05/17                                                                                               Pour Footings
 105                 FRP Ground Slab                        4 days     Fri 12/05/17   Wed 17/05/17                                                                                               FRP Ground Slab
 106                 Reinforced Block Walls                 5 days     Thu 18/05/17 Wed 24/05/17                                                                                                   Reinforced Block Walls
 107                 Strip Suspended Slab                   3 days     Thu 8/06/17    Mon 12/06/17                                                                                                     Strip Suspended Slab
 108               WATER TANKS                              22 days    Thu 18/05/17 Fri 16/06/17                                                                                                            WATER TANKS
 109                 FRP Ground Slab                        3 days     Thu 18/05/17 Mon 22/05/17                                                                                                  FRP Ground Slab
 110                 FRP Tank Walls                         3 days     Tue 23/05/17 Thu 25/05/17                                                                                                   FRP Tank Walls
 111                 FRP Tank Lid                           5 days     Fri 26/05/17   Thu 1/06/17                                                                                                    FRP Tank Lid
 112                 Strip Tank Lid Formworks               1 day      Fri 16/06/17   Fri 16/06/17                                                                                                      Strip Tank Lid Formworks
 113               POOL                                     17 days    Thu 25/05/17 Fri 16/06/17                                                                                                            POOL
 114                 Form Pool Walls and Base               1 wk       Thu 25/05/17 Wed 31/05/17                                                                                                    Form Pool Walls and Base


                                    Task             Summary                                   External Milestone                           Inactive Summary                             Manual Summary Rollup                              Finish-only                       Critical Split
Project: Seaview Terrace Program
                                    Split            Project Summary                           Inactive Task                                Manual Task                                  Manual Summary                                     Deadline                          Progress
Date: Fri 5/08/16
                                    Milestone        External Tasks                            Inactive Milestone                           Duration-only                                Start-only                                         Critical

                                                                                                                                                                  Page 2

Page 3

                                                                                                                                                         SEAVIEW TERRACE
                                                                                                                                                  CONSTRUCTION PROGRAM - TARGET
                                                                                                                                                              DRAFT
ID           Task Name                                                  Duration   Start          Finish              July      August September
                                                                                                                                             OctoberNovember
                                                                                                                                                          December
                                                                                                                                                                January February
                                                                                                                                                                               March April   May      June July       August September
                                                                                                                                                                                                                                   OctoberNovember
                                                                                                                                                                                                                                                December
                                                                                                                                                                                                                                                      January February
                                                                                                                                                                                                                                                                     March April                       May       June    July    August September
                                                                                                                                                                                                                                                                                                                                              OctoberNovember
                                                                                                                                                                                                                                                                                                                                                           December
                                                                                                                                                                                                                                                                                                                                                                 January February
                                                                                                                                                                                                                                                                                                                                                                                Ma
                                                                                                                        Jul      Aug    Sep    Oct   Nov   Dec    Jan    Feb     Mar  Apr     May       Jun     Jul     Aug   Sep    Oct   Nov   Dec    Jan    Feb    Mar   Apr                         May        Jun     Jul    Aug    Sep    Oct   Nov   Dec    Jan    Feb
 115                 Reinforce Pool                                     1 wk       Thu 1/06/17    Wed 7/06/17                                                                                            Reinforce Pool
 116                 Services in Pool                                   1 wk       Thu 8/06/17    Wed 14/06/17                                                                                            Services in Pool
 117                 Spray Pool                                         2 days     Thu 15/06/17 Fri 16/06/17                                                                                              Spray Pool
 118               BASEMENT                                             31 days    Mon 3/07/17 Mon 14/08/17                                                                                                                  BASEMENT
 119                 Excavate, Reinforce and Pour Footings              8 days     Mon 3/07/17 Wed 12/07/17                                                                                                      Excavate, Reinforce and Pour Footings
 120                 FRP Ground Slab                                    8 days     Thu 13/07/17 Mon 24/07/17                                                                                                        FRP Ground Slab
 121                 FRP Concrete Walls                                 3 wks      Tue 25/07/17 Mon 14/08/17                                                                                                                 FRP Concrete Walls
 122                 S&I Reinforced Blockwork                           2 wks      Tue 25/07/17 Mon 7/08/17                                                                                                             S&I Reinforced Blockwork
 123               LEVEL 1                                              41 days    Tue 15/08/17 Wed 11/10/17                                                                                                                                LEVEL 1
 124                 Zone 1                                             6 days     Tue 15/08/17 Tue 22/08/17                                                                                                                   Zone 1
 125                     Excavate, Reinforce and Pour Footings          3 days     Tue 15/08/17 Thu 17/08/17                                                                                                                 Excavate, Reinforce and Pour Footings
 126                     FRP Ground Slab                                3 days     Fri 18/08/17   Tue 22/08/17                                                                                                                FRP Ground Slab
 127                 Zone 2                                             32 days    Fri 18/08/17   Tue 3/10/17                                                                                                                             Zone 2
 128                     Formwork to Arches                             2 wks      Fri 18/08/17   Thu 31/08/17                                                                                                                   Formwork to Arches
 129                     Reinforce Arches                               4 days     Fri 1/09/17    Wed 6/09/17                                                                                                                     Reinforce Arches
 130                     Spray Arches                                   1 day      Thu 7/09/17    Thu 7/09/17                                                                                                                     Spray Arches
 131                     Strip Arches                                   2 days     Fri 29/09/17   Tue 3/10/17                                                                                                                             Strip Arches
 132                 Zone 3                                             28 days    Fri 1/09/17    Wed 11/10/17                                                                                                                              Zone 3
 133                     Formwork to Arches                             8 days     Fri 1/09/17    Tue 12/09/17                                                                                                                      Formwork to Arches
 134                     Reinforce Arches                               4 days     Wed 13/09/17 Mon 18/09/17                                                                                                                         Reinforce Arches
 135                     Spray Arches                                   1 day      Tue 19/09/17 Tue 19/09/17                                                                                                                         Spray Arches
 136                     Strip Arches                                   1 day      Wed 11/10/17 Wed 11/10/17                                                                                                                                Strip Arches
 137                 Zone 4                                             7 days     Wed 20/09/17 Thu 28/09/17                                                                                                                             Zone 4
 138                     Excavate, Reinforce and Pour Footings          4 days     Wed 20/09/17 Mon 25/09/17                                                                                                                            Excavate, Reinforce and Pour Footings
 139                     FRP Ground Slab                                3 days     Tue 26/09/17 Thu 28/09/17                                                                                                                            FRP Ground Slab
 140               LEVEL 1                                              20 days    Fri 29/09/17   Fri 27/10/17                                                                                                                                    LEVEL 1
 141                 Form, Reinforce, Pour Concrete Walls               3 wks      Fri 29/09/17   Fri 20/10/17                                                                                                                                Form, Reinforce, Pour Concrete Walls
 142                 Reinforced Concrete Block Walls                    2 wks      Mon 16/10/17 Fri 27/10/17                                                                                                                                      Reinforced Concrete Block Walls
 143               LEVEL 2                                              61 days    Mon 30/10/17 Tue 13/02/18                                                                                                                                                                       LEVEL 2
 144                 ZONE 1                                             29 days    Mon 30/10/17 Thu 7/12/17                                                                                                                                                   ZONE 1
 145                     Form Suspended Slab and Beams                  6 days     Mon 30/10/17 Mon 6/11/17                                                                                                                                         Form Suspended Slab and Beams
 146                     Reinforce Suspended Slab                       4 days     Tue 7/11/17    Fri 10/11/17                                                                                                                                         Reinforce Suspended Slab
 147                     Pour Suspended Slab                            1 day      Mon 13/11/17 Mon 13/11/17                                                                                                                                           Pour Suspended Slab
 148                     Strip Suspended Slab                           3 days     Tue 5/12/17    Thu 7/12/17                                                                                                                                                 Strip Suspended Slab
 149                 ZONE 2                                             29 days    Tue 7/11/17    Fri 15/12/17                                                                                                                                                  ZONE 2
 150                     Form Suspended Slab and Beams                  6 days     Tue 7/11/17    Tue 14/11/17                                                                                                                                         Form Suspended Slab and Beams
 151                     Reinforce Suspended Slab                       4 days     Wed 15/11/17 Mon 20/11/17                                                                                                                                             Reinforce Suspended Slab
 152                     Pour Suspended Slab                            1 day      Tue 21/11/17 Tue 21/11/17                                                                                                                                             Pour Suspended Slab
 153                     Strip Suspended Slab                           3 days     Wed 13/12/17 Fri 15/12/17                                                                                                                                                   Strip Suspended Slab
 154                 ZONE 3                                             30 days    Wed 15/11/17 Tue 16/01/18                                                                                                                                                              ZONE 3
 155                     Form Arches                                    2 wks      Wed 15/11/17 Tue 28/11/17                                                                                                                                                Form Arches
 156                     Reinforce Arches                               5 days     Wed 29/11/17 Tue 5/12/17                                                                                                                                                  Reinforce Arches
 157                     Spray Arches                                   1 day      Wed 6/12/17 Wed 6/12/17                                                                                                                                                   Spray Arches
 158                     Strip Arches                                   2 days     Mon 15/01/18 Tue 16/01/18                                                                                                                                                              Strip Arches
 159                 ZONE 4                                             20 days    Wed 29/11/17 Tue 16/01/18                                                                                                                                                              ZONE 4
 160                     Form Arches                                    8 days     Wed 29/11/17 Fri 8/12/17                                                                                                                                                   Form Arches
 161                     Reinforce Arches                               4 days     Mon 11/12/17 Thu 14/12/17                                                                                                                                                   Reinforce Arches
 162                     Spray Arches                                   1 day      Fri 15/12/17   Fri 15/12/17                                                                                                                                                 Spray Arches
 163                     Strip Arches                                   2 days     Mon 15/01/18 Tue 16/01/18                                                                                                                                                              Strip Arches
 164                 ZONE 5                                             31 days    Mon 11/12/17 Tue 13/02/18                                                                                                                                                                       ZONE 5
 165                     Form Arches                                    2 wks      Mon 11/12/17 Fri 22/12/17                                                                                                                                                     Form Arches
 166                     Reinforce Arches                               4 days     Mon 15/01/18 Thu 18/01/18                                                                                                                                                              Reinforce Arches
 167                     Spray Arches                                   1 day      Fri 19/01/18   Fri 19/01/18                                                                                                                                                            Spray Arches
 168                     Strip Arches                                   2 days     Mon 12/02/18 Tue 13/02/18                                                                                                                                                                     Strip Arches
 169               LEVEL 2                                              15 days    Mon 15/01/18 Mon 5/02/18                                                                                                                                                                     LEVEL 2
 170                 FRP Walls                                          3 wks      Mon 15/01/18 Mon 5/02/18                                                                                                                                                                    FRP Walls
 171               ROOF                                                 39 days    Tue 6/02/18    Tue 3/04/18                                                                                                                                                                                   ROOF


                                   Task                          Summary                                   External Milestone                         Inactive Summary                       Manual Summary Rollup                          Finish-only                                         Critical Split
Project: Seaview Terrace Program
                                   Split                         Project Summary                           Inactive Task                              Manual Task                            Manual Summary                                 Deadline                                            Progress
Date: Fri 5/08/16
                                   Milestone                     External Tasks                            Inactive Milestone                         Duration-only                          Start-only                                     Critical

                                                                                                                                                                         Page 3

Page 4

                                                                                                                                                          SEAVIEW TERRACE
                                                                                                                                                   CONSTRUCTION PROGRAM - TARGET
                                                                                                                                                               DRAFT
ID           Task Name                                                    Duration   Start         Finish              July      August September
                                                                                                                                              OctoberNovember
                                                                                                                                                           December
                                                                                                                                                                 January February
                                                                                                                                                                                March April   May      June     July     August September
                                                                                                                                                                                                                                      OctoberNovember
                                                                                                                                                                                                                                                   December
                                                                                                                                                                                                                                                         January February
                                                                                                                                                                                                                                                                        March April                       May       June    July        August September
                                                                                                                                                                                                                                                                                                                                                     OctoberNovember
                                                                                                                                                                                                                                                                                                                                                                  December
                                                                                                                                                                                                                                                                                                                                                                        January February
                                                                                                                                                                                                                                                                                                                                                                                       Ma
                                                                                                                         Jul      Aug    Sep    Oct   Nov   Dec    Jan    Feb     Mar  Apr     May       Jun      Jul     Aug    Sep    Oct   Nov   Dec    Jan    Feb    Mar    Apr                        May        Jun     Jul        Aug    Sep    Oct   Nov   Dec    Jan    Feb
 172                 Form Roof                                            2 wks      Tue 6/02/18   Mon 19/02/18                                                                                                                                                       Form Roof
 173                 Reinforce Slab                                       2 wks      Tue 13/02/18 Mon 26/02/18                                                                                                                                                                         Reinforce Slab
 174                 Pour Slab                                            5 days     Tue 27/02/18 Mon 5/03/18                                                                                                                                                                            Pour Slab
 175                 Strip Suspended Slab                                 4 days     Tue 27/03/18 Tue 3/04/18                                                                                                                                                                                    Strip Suspended Slab
 176            SERVICES                                                  20 days    Wed 4/04/18 Wed 2/05/18                                                                                                                                                                                                SERVICES
 177               LIFT                                                   20 days    Wed 4/04/18 Wed 2/05/18                                                                                                                                                                                                LIFT
 178                 Install Structural Steel to Lift                     1 wk       Wed 4/04/18 Tue 10/04/18                                                                                                                                                                                        Install Structural Steel to Lift
 179                 Install Lift                                         3 wks      Wed 11/04/18 Wed 2/05/18                                                                                                                                                                                              Install Lift
 180            FAÇADE                                                    149 days   Wed 13/09/17 Tue 8/05/18                                                                                                                                                                                                 FAÇADE
 181               BASEMENT                                               23 days    Thu 12/10/17 Mon 13/11/17                                                                                                                                            BASEMENT
 182                 Install Structural Steel for Window Framing          5 days     Thu 12/10/17 Wed 18/10/17                                                                                                                                 Install Structural Steel for Window Framing
 183                 Waterproof Window and Door Openings                  3 days     Thu 19/10/17 Mon 23/10/17                                                                                                                                  Waterproof Window and Door Openings
 184                 Install Alumnium Windows and Doors                   3 wks      Tue 24/10/17 Mon 13/11/17                                                                                                                                           Install Alumnium Windows and Doors
 185               LEVEL 1                                                48 days    Wed 14/02/18 Tue 24/04/18                                                                                                                                                                                            LEVEL 1
 186                 Install Structural Steel for Window Framing          5 days     Wed 14/02/18 Tue 20/02/18                                                                                                                                                                        Install Structural Steel for Window Framing
 187                 Waterproof Window and Door Openings                  3 days     Wed 21/02/18 Fri 23/02/18                                                                                                                                                                        Waterproof Window and Door Openings
 188                 Install Alumnium Windows and Doors                   3 wks      Mon 26/02/18 Fri 16/03/18                                                                                                                                                                              Install Alumnium Windows and Doors
 189                 Install Timber Eyelids                               5 wks      Mon 19/03/18 Tue 24/04/18                                                                                                                                                                                           Install Timber Eyelids
 190               LEVEL 2                                                23 days    Wed 4/04/18 Tue 8/05/18                                                                                                                                                                                                  LEVEL 2
 191                 Install Structural Steel for Window Framing          5 days     Wed 4/04/18 Tue 10/04/18                                                                                                                                                                                        Install Structural Steel for Window Framing
 192                 Waterproof Window and Door Openings                  3 days     Wed 11/04/18 Fri 13/04/18                                                                                                                                                                                       Waterproof Window and Door Openings
 193                 Install Alumnium Windows and Doors                   3 wks      Mon 16/04/18 Tue 8/05/18                                                                                                                                                                                                Install Alumnium Windows and Doors
 194                 Install Panel Lift Garage Door                       1 wk       Wed 4/04/18 Tue 10/04/18                                                                                                                                                                                        Install Panel Lift Garage Door
 195                 Install Sliding Curved Garage Door                   1 wk       Wed 11/04/18 Tue 17/04/18                                                                                                                                                                                         Install Sliding Curved Garage Door
 196               MAIN FEATURE STAIR                                     77 days    Wed 13/09/17 Fri 19/01/18                                                                                                                                                              MAIN FEATURE STAIR
 197                 FRP Basement to Level 1                              2 wks      Wed 13/09/17 Tue 26/09/17                                                                                                                            FRP Basement to Level 1
 198                 Install Steel Treads                                 3 wks      Mon 30/10/17 Fri 17/11/17                                                                                                                                            Install Steel Treads
 199                 Tile Finish to Concrete Treads / Risers              2 wks      Wed 27/09/17 Wed 11/10/17                                                                                                                               Tile Finish to Concrete Treads / Risers
 200                 Install Glass Treads                                 1 wk       Mon 20/11/17 Fri 24/11/17                                                                                                                                              Install Glass Treads
 201                 Install Handrail Basement to Level 1                 2 wks      Mon 27/11/17 Fri 8/12/17                                                                                                                                                   Install Handrail Basement to Level 1
 202                 Install Handrail Level to Level 2                    2 wks      Mon 11/12/17 Fri 22/12/17                                                                                                                                                     Install Handrail Level to Level 2
 203                 Install Balustrade Level 2                           1 wk       Mon 15/01/18 Fri 19/01/18                                                                                                                                                             Install Balustrade Level 2
 204            FINISHES                                                  287 days? Mon 12/06/17 Thu 16/08/18                                                                                                                                                                                                                               FINISHES
 205               POOL BASEMENT                                          16 days    Mon 12/06/17 Tue 4/07/17                                                                                                      POOL BASEMENT
 206                 Watertight                                           0 days     Mon 12/06/17 Mon 12/06/17                                                                                             Watertight
 207                 Floor & Wall Finishes                                4 days     Tue 13/06/17 Fri 16/06/17                                                                                             Floor & Wall Finishes
 208                 Rough-In Plumbing                                    3 days     Mon 19/06/17 Wed 21/06/17                                                                                                 Rough-In Plumbing
 209                 Rough-In Electrical                                  3 days     Mon 19/06/17 Wed 21/06/17                                                                                                 Rough-In Electrical
 210                 Fit-Off Plumbing                                     3 days     Thu 22/06/17 Mon 26/06/17                                                                                                  Fit-Off Plumbing
 211                 Fit-Off Electrical                                   3 days     Thu 22/06/17 Mon 26/06/17                                                                                                  Fit-Off Electrical
 212                 Install Pool Equipment                               2 wks      Mon 19/06/17 Fri 30/06/17                                                                                                   Install Pool Equipment
 213                 Install Door D41                                     2 days     Mon 3/07/17 Tue 4/07/17                                                                                                      Install Door D41
 214               BASEMENT                                               53 days    Wed 11/10/17 Mon 15/01/18                                                                                                                                                             BASEMENT
 215                 Watertight                                           0 days     Wed 11/10/17 Wed 11/10/17                                                                                                                                Watertight
 216                 Install Hempcrete Walls                              5 days     Thu 12/10/17 Wed 18/10/17                                                                                                                                 Install Hempcrete Walls
 217                 Metal Wall Framing                                   5 days     Thu 19/10/17 Wed 25/10/17                                                                                                                                   Metal Wall Framing
 218                 Ceiling Framing                                      5 days     Thu 19/10/17 Wed 25/10/17                                                                                                                                   Ceiling Framing
 219                 Rough-In Hydraulic                                   3 days     Thu 26/10/17 Mon 30/10/17                                                                                                                                    Rough-In Hydraulic
 220                 Rough-In Electrical                                  3 days     Thu 26/10/17 Mon 30/10/17                                                                                                                                    Rough-In Electrical
 221                 Rough-In Mechanical                                  4 days     Thu 12/10/17 Tue 17/10/17                                                                                                                                 Rough-In Mechanical
 222                 Gyprock Wall Linings                                 6 days     Tue 31/10/17 Tue 7/11/17                                                                                                                                        Gyprock Wall Linings
 223                 Gyprock Ceiling Linings                              6 days     Tue 31/10/17 Tue 7/11/17                                                                                                                                        Gyprock Ceiling Linings
 224                 Waterproofing                                        4 days     Wed 8/11/17 Mon 13/11/17                                                                                                                                            Waterproofing
 225                 Carpentry - Doors and Hardware                       5 days     Wed 8/11/17 Tue 14/11/17                                                                                                                                             Carpentry - Doors and Hardware
 226                 Carpentry - Feature Timber Walls to Theatre          3 days     Wed 8/11/17 Fri 10/11/17                                                                                                                                            Carpentry - Feature Timber Walls to Theatre
 227                 Floor Tiling - Rec Room & Lounge                     5 days     Wed 8/11/17 Tue 14/11/17                                                                                                                                             Floor Tiling - Rec Room & Lounge
 228                 Floor Tiling - Wet Areas                             5 days     Tue 14/11/17 Mon 20/11/17                                                                                                                                             Floor Tiling - Wet Areas


                                    Task                           Summary                                  External Milestone                         Inactive Summary                       Manual Summary Rollup                           Finish-only                                        Critical Split
Project: Seaview Terrace Program
                                    Split                          Project Summary                          Inactive Task                              Manual Task                            Manual Summary                                  Deadline                                           Progress
Date: Fri 5/08/16
                                    Milestone                      External Tasks                           Inactive Milestone                         Duration-only                          Start-only                                      Critical

                                                                                                                                                                          Page 4

Page 5

                                                                                                                                                              SEAVIEW TERRACE
                                                                                                                                                       CONSTRUCTION PROGRAM - TARGET
                                                                                                                                                                   DRAFT
ID           Task Name                                                       Duration   Start          Finish              July      August September
                                                                                                                                                  OctoberNovember
                                                                                                                                                               December
                                                                                                                                                                     January February
                                                                                                                                                                                    March April   May      June    July    August September
                                                                                                                                                                                                                                        OctoberNovember
                                                                                                                                                                                                                                                     DecemberJanuary February
                                                                                                                                                                                                                                                                            March April                May        June     July      August September
                                                                                                                                                                                                                                                                                                                                                  OctoberNovember
                                                                                                                                                                                                                                                                                                                                                               December
                                                                                                                                                                                                                                                                                                                                                                     January February
                                                                                                                                                                                                                                                                                                                                                                                    Ma
                                                                                                                             Jul      Aug    Sep    Oct   Nov   Dec    Jan    Feb     Mar  Apr     May       Jun     Jul    Aug    Sep    Oct   Nov   Dec      Jan     Feb   Mar   Apr                  May         Jun      Jul      Aug    Sep    Oct   Nov   Dec    Jan    Feb
 229                 Terrace Tiling                                          4 days     Mon 4/12/17 Thu 7/12/17                                                                                                                                         Terrace Tiling
 230                 Sauna Fit-Off                                           2 wks      Wed 8/11/17 Tue 21/11/17                                                                                                                                        Sauna Fit-Off
 231                 Steam Room Fit-Off                                      2 wks      Wed 8/11/17 Tue 21/11/17                                                                                                                                        Steam Room Fit-Off
 232                 Ice Bath Fit-Off                                        3 days     Wed 15/11/17 Fri 17/11/17                                                                                                                                      Ice Bath Fit-Off
 233                 Kitchenette / Bar Joinery                               1 wk       Wed 15/11/17 Tue 21/11/17                                                                                                                                       Kitchenette / Bar Joinery
 234                 Wall Tiling Change Room                                 3 days     Tue 21/11/17 Thu 23/11/17                                                                                                                                       Wall Tiling Change Room
 235                 Wall Tiling WC                                          3 days     Fri 24/11/17   Tue 28/11/17                                                                                                                                       Wall Tiling WC
 236                 Wall Tiling Powder                                      3 days     Wed 29/11/17 Fri 1/12/17                                                                                                                                          Wall Tiling Powder
 237                 Install vanity Benches & Stone Tops                     2 days     Mon 4/12/17 Tue 5/12/17                                                                                                                                             Install vanity Benches & Stone Tops
 238                 Install Shower Screens & Mirrors                        2 days     Wed 6/12/17 Thu 7/12/17                                                                                                                                             Install Shower Screens & Mirrors
 239                 Paint Finish                                            2 wks      Fri 8/12/17    Thu 21/12/17                                                                                                                                             Paint Finish
 240                 Electrical Fit-Off                                      1 wk       Wed 6/12/17 Tue 12/12/17                                                                                                                                              Electrical Fit-Off
 241                 Hydraulic Fit-Off                                       1 wk       Wed 6/12/17 Tue 12/12/17                                                                                                                                              Hydraulic Fit-Off
 242                 Mechanical Fit-Off                                      1 wk       Fri 15/12/17   Thu 21/12/17                                                                                                                                             Mechanical Fit-Off
 243                 Carpet Installation                                     2 days     Fri 22/12/17   Mon 15/01/18                                                                                                                                                       Carpet Installation
 244               LEVEL 1                                                   105 days   Fri 16/03/18   Thu 16/08/18                                                                                                                                                                                                                        LEVEL 1
 245                 Watertight                                              0 days     Fri 16/03/18   Fri 16/03/18                                                                                                                                                                        Watertight
 246                 Install Hempcrete Walls                                 2 wks      Mon 19/03/18 Tue 3/04/18                                                                                                                                                                                Install Hempcrete Walls
 247                 Metal Wall Framing                                      3 wks      Wed 4/04/18 Tue 24/04/18                                                                                                                                                                                      Metal Wall Framing
 248                 Ceiling Framing                                         2 wks      Wed 4/04/18 Tue 17/04/18                                                                                                                                                                                    Ceiling Framing
 249                 Rough-In Hydraulic                                      1 wk       Thu 26/04/18 Wed 2/05/18                                                                                                                                                                                         Rough-In Hydraulic
 250                 Rough-In Electrical                                     2 wks      Thu 26/04/18 Thu 10/05/18                                                                                                                                                                                          Rough-In Electrical
 251                 Rough-In Mechanical                                     2 wks      Mon 19/03/18 Tue 3/04/18                                                                                                                                                                                Rough-In Mechanical
 252                 Gyprock Wall Linings                                    2 wks      Fri 11/05/18   Thu 24/05/18                                                                                                                                                                                              Gyprock Wall Linings
 253                 Gyprock Ceiling Linings                                 2 wks      Wed 4/04/18 Tue 17/04/18                                                                                                                                                                                    Gyprock Ceiling Linings
 254                 Waterproofing                                           1 wk       Fri 25/05/18   Thu 31/05/18                                                                                                                                                                                                Waterproofing
 255                 Carpentry - Doors and Hardware                          2 wks      Fri 25/05/18   Thu 7/06/18                                                                                                                                                                                                  Carpentry - Doors and Hardware
 256                 Floor Tiling - Living, Dining, Kitchen, Pantry          2 wks      Fri 8/06/18    Thu 21/06/18                                                                                                                                                                                                       Floor Tiling - Living, Dining, Kitchen, Pantry
 257                 Floor Tiling Bedrooms                                   4 wks      Fri 8/06/18    Thu 5/07/18                                                                                                                                                                                                           Floor Tiling Bedrooms
 258                 Floor Tiling Laundry                                    4 days     Fri 1/06/18    Wed 6/06/18                                                                                                                                                                                                  Floor Tiling Laundry
 259                 Floor Tiling Ensuites                                   18 days    Fri 1/06/18    Tue 26/06/18                                                                                                                                                                                                        Floor Tiling Ensuites
 260                 Terrace Tiling                                          1 wk       Fri 1/06/18    Thu 7/06/18                                                                                                                                                                                                  Terrace Tiling
 261                 Install Balustrade                                      1 wk       Fri 8/06/18    Thu 14/06/18                                                                                                                                                                                                   Install Balustrade
 262                 Wall Tiling - Ensuite Master                            4 days     Wed 27/06/18 Mon 2/07/18                                                                                                                                                                                                             Wall Tiling - Ensuite Master
 263                 Wall Tiling - Ensuite Bed 02                            4 days     Tue 3/07/18    Fri 6/07/18                                                                                                                                                                                                            Wall Tiling - Ensuite Bed 02
 264                 Wall Tiling - Ensuite Bed 03                            4 days     Mon 9/07/18 Thu 12/07/18                                                                                                                                                                                                               Wall Tiling - Ensuite Bed 03
 265                 Wall Tiling - Ensuite Bed 04                            4 days     Fri 13/07/18   Wed 18/07/18                                                                                                                                                                                                                Wall Tiling - Ensuite Bed 04
 266                 Wall Tiling - Ensuite Bed 05                            4 days     Thu 19/07/18 Tue 24/07/18                                                                                                                                                                                                                   Wall Tiling - Ensuite Bed 05
 267                 Wall Tiling - Powder                                    2 days     Wed 25/07/18 Thu 26/07/18                                                                                                                                                                                                                    Wall Tiling - Powder
 268                 Wall Tiling - Laundry                                   2 days     Wed 25/07/18 Thu 26/07/18                                                                                                                                                                                                                    Wall Tiling - Laundry
 269                 Install Master Robes, Ensuite & Stdy Joinery            4 days     Tue 3/07/18    Fri 6/07/18                                                                                                                                                                                                            Install Master Robes, Ensuite & Stdy Joinery
 270                 Install Bed 02 Robe, Ensuite & Study                    4 days     Mon 9/07/18 Thu 12/07/18                                                                                                                                                                                                               Install Bed 02 Robe, Ensuite & Study
 271                 Install Bed 03 Robe, Ensuite & Study                    4 days     Fri 13/07/18   Wed 18/07/18                                                                                                                                                                                                                Install Bed 03 Robe, Ensuite & Study
 272                 Install Bed 04 Robe, Ensuite & Study                    4 days     Thu 19/07/18 Tue 24/07/18                                                                                                                                                                                                                   Install Bed 04 Robe, Ensuite & Study
 273                 Install Bed 05 Robe, Ensuite & Study                    4 days     Wed 25/07/18 Mon 30/07/18                                                                                                                                                                                                                     Install Bed 05 Robe, Ensuite & Study
 274                 Install Laundry Joinery                                 3 days     Fri 27/07/18   Tue 31/07/18                                                                                                                                                                                                                   Install Laundry Joinery
 275                 Install Shower Screen and Mirrors                       5 days     Wed 25/07/18 Tue 31/07/18                                                                                                                                                                                                                     Install Shower Screen and Mirrors
 276                 Paint Finish                                            3 wks      Fri 27/07/18   Thu 16/08/18                                                                                                                                                                                                                       Paint Finish
 277                 Electrical Fit-Off                                      2 wks      Fri 3/08/18    Thu 16/08/18                                                                                                                                                                                                                       Electrical Fit-Off
 278                 Mechanical Fit-Off                                      2 wks      Fri 3/08/18    Thu 16/08/18                                                                                                                                                                                                                       Mechanical Fit-Off
 279                 Hydraulic Fit-Off                                       2 wks      Fri 3/08/18    Thu 16/08/18                                                                                                                                                                                                                       Hydraulic Fit-Off
 280               LEVEL 2                                                   52 days?   Wed 9/05/18 Thu 19/07/18                                                                                                                                                                                                                    LEVEL 2
 281                 Watertight                                              1 day?     Wed 9/05/18 Wed 9/05/18                                                                                                                                                                                            Watertight
 282                 Install Hempcrete Walls                                 5 days     Thu 10/05/18 Wed 16/05/18                                                                                                                                                                                            Install Hempcrete Walls
 283                 Metal Wall Framing                                      5 days     Thu 17/05/18 Wed 23/05/18                                                                                                                                                                                                Metal Wall Framing
 284                 Ceiling Framing                                         5 days     Thu 17/05/18 Wed 23/05/18                                                                                                                                                                                                Ceiling Framing
 285                 Rough-In Hydraulic                                      3 days     Thu 24/05/18 Mon 28/05/18                                                                                                                                                                                                 Rough-In Hydraulic


                                    Task                              Summary                                   External Milestone                         Inactive Summary                       Manual Summary Rollup                     Finish-only                                         Critical Split
Project: Seaview Terrace Program
                                    Split                             Project Summary                           Inactive Task                              Manual Task                            Manual Summary                            Deadline                                            Progress
Date: Fri 5/08/16
                                    Milestone                         External Tasks                            Inactive Milestone                         Duration-only                          Start-only                                Critical

                                                                                                                                                                              Page 5

Page 6

                                                                                                                                                            SEAVIEW TERRACE
                                                                                                                                                     CONSTRUCTION PROGRAM - TARGET
                                                                                                                                                                 DRAFT
ID           Task Name                                                     Duration   Start          Finish              July      August September
                                                                                                                                                OctoberNovember
                                                                                                                                                             December
                                                                                                                                                                   January February
                                                                                                                                                                                  March April   May      June    July    August September
                                                                                                                                                                                                                                      OctoberNovember
                                                                                                                                                                                                                                                   December
                                                                                                                                                                                                                                                         January February
                                                                                                                                                                                                                                                                        March April         May        June July       August September
                                                                                                                                                                                                                                                                                                                                    OctoberNovember
                                                                                                                                                                                                                                                                                                                                                 December
                                                                                                                                                                                                                                                                                                                                                       January February
                                                                                                                                                                                                                                                                                                                                                                      Ma
                                                                                                                           Jul      Aug    Sep    Oct   Nov   Dec    Jan    Feb     Mar  Apr     May       Jun     Jul    Aug    Sep    Oct   Nov   Dec    Jan    Feb    Mar   Apr           May         Jun    Jul      Aug   Sep    Oct   Nov   Dec    Jan    Feb
 286                 Rough-In Electrical                                   3 days     Thu 24/05/18 Mon 28/05/18                                                                                                                                                                                        Rough-In Electrical
 287                 Rough-In Mechanical                                   4 days     Thu 10/05/18 Tue 15/05/18                                                                                                                                                                                   Rough-In Mechanical
 288                 Gyprock Wall Linings                                  6 days     Tue 29/05/18 Tue 5/06/18                                                                                                                                                                                          Gyprock Wall Linings
 289                 Gyprock Ceiling Linings                               6 days     Tue 29/05/18 Tue 5/06/18                                                                                                                                                                                          Gyprock Ceiling Linings
 290                 Waterproofing                                         4 days     Wed 6/06/18 Mon 11/06/18                                                                                                                                                                                            Waterproofing
 291                 Carpentry - Doors and Hardware                        5 days     Wed 6/06/18 Tue 12/06/18                                                                                                                                                                                            Carpentry - Doors and Hardware
 292                 Floor Tiling - Entry Lobby                            5 days     Wed 13/06/18 Tue 19/06/18                                                                                                                                                                                             Floor Tiling - Entry Lobby
 293                 Floor Tiling - Workshop / Study                       5 days     Wed 20/06/18 Tue 26/06/18                                                                                                                                                                                               Floor Tiling - Workshop / Study
 294                 Floor Tiling Bed 06                                   5 days     Wed 27/06/18 Tue 3/07/18                                                                                                                                                                                                   Floor Tiling Bed 06
 295                 Floor Tiling - Bathroom                               5 days     Tue 12/06/18 Mon 18/06/18                                                                                                                                                                                            Floor Tiling - Bathroom
 296                 Floor Tiling - Guest Ensuite                          5 days     Tue 19/06/18 Mon 25/06/18                                                                                                                                                                                               Floor Tiling - Guest Ensuite
 297                 Wall Tiling Bathroom                                  3 days     Tue 19/06/18 Thu 21/06/18                                                                                                                                                                                             Wall Tiling Bathroom
 298                 Wall Tiling Guest Ensuite                             3 days     Tue 26/06/18 Thu 28/06/18                                                                                                                                                                                               Wall Tiling Guest Ensuite
 299                 Install vanity Benches & Stone Tops                   2 days     Fri 29/06/18   Mon 2/07/18                                                                                                                                                                                                 Install vanity Benches & Stone Tops
 300                 Install Shower Screens & Mirrors                      2 days     Fri 29/06/18   Mon 2/07/18                                                                                                                                                                                                 Install Shower Screens & Mirrors
 301                 Paint Finish                                          2 wks      Fri 29/06/18   Thu 12/07/18                                                                                                                                                                                                  Paint Finish
 302                 Electrical Fit-Off                                    1 wk       Fri 13/07/18   Thu 19/07/18                                                                                                                                                                                                    Electrical Fit-Off
 303                 Hydraulic Fit-Off                                     1 wk       Fri 13/07/18   Thu 19/07/18                                                                                                                                                                                                    Hydraulic Fit-Off
 304                 Mechanical Fit-Off                                    1 wk       Fri 13/07/18   Thu 19/07/18                                                                                                                                                                                                    Mechanical Fit-Off
 305               ROOF                                                    121 days   Thu 12/10/17 Tue 24/04/18                                                                                                                                                                             ROOF
 306                 Waterproof Basement Roof Gardens                      2 wks      Thu 12/10/17 Wed 25/10/17                                                                                                                              Waterproof Basement Roof Gardens
 307                 Waterproo Level 1 Roof Gardens                        2 wks      Wed 17/01/18 Wed 31/01/18                                                                                                                                                    Waterproo Level 1 Roof Gardens
 308                 Waterproof Level 2 Roof Gardens                       2 wks      Wed 4/04/18 Tue 17/04/18                                                                                                                                                                           Waterproof Level 2 Roof Gardens
 309                 Install Glass Skylights                               1 wk       Wed 18/04/18 Tue 24/04/18                                                                                                                                                                            Install Glass Skylights
 310                 Install Solar Panels to Roof                          1 wk       Wed 18/04/18 Tue 24/04/18                                                                                                                                                                            Install Solar Panels to Roof
 311               EXTERNAL                                                11 days    Tue 6/03/18    Tue 20/03/18                                                                                                                                                                 EXTERNAL
 312                 Bin Store Structure                                   3 days     Tue 6/03/18    Thu 8/03/18                                                                                                                                                           Bin Store Structure
 313                 Turning Bay Retaining Wall                            6 days     Tue 6/03/18    Tue 13/03/18                                                                                                                                                               Turning Bay Retaining Wall
 314                 FRP Turning Bay Stairs                                5 days     Tue 6/03/18    Mon 12/03/18                                                                                                                                                           FRP Turning Bay Stairs
 315                 Split Face Blockwork Wall to Boundary                 10 days    Tue 6/03/18    Mon 19/03/18                                                                                                                                                                Split Face Blockwork Wall to Boundary
 316                 FRP Plantroom Slab                                    3 days     Tue 6/03/18    Thu 8/03/18                                                                                                                                                           FRP Plantroom Slab
 317                 FRP Driveway                                          8 days     Tue 6/03/18    Thu 15/03/18                                                                                                                                                               FRP Driveway
 318                 Plantroom Structure                                   5 days     Tue 6/03/18    Mon 12/03/18                                                                                                                                                           Plantroom Structure
 319                 Plantroom Roof                                        3 days     Tue 13/03/18 Thu 15/03/18                                                                                                                                                                 Plantroom Roof
 320                 Plantroom Screens                                     3 days     Fri 16/03/18   Tue 20/03/18                                                                                                                                                                Plantroom Screens
 321                 FRP Footings Bin Store / Gate Walls                   2 days     Tue 6/03/18    Wed 7/03/18                                                                                                                                                           FRP Footings Bin Store / Gate Walls
 322                 Split Face Blockwork Bin Store / Gate Walls           5 days     Fri 9/03/18    Thu 15/03/18                                                                                                                                                               Split Face Blockwork Bin Store / Gate Walls
 323            LANDSCAPING                                                148 days   Thu 12/10/17 Mon 4/06/18                                                                                                                                                                                           LANDSCAPING
 324               Waterproof Basement Roof                                10 days    Thu 12/10/17 Wed 25/10/17                                                                                                                              Waterproof Basement Roof
 325               Waterproof Level 1 Roof                                 10 days    Wed 14/02/18 Tue 27/02/18                                                                                                                                                          Waterproof Level 1 Roof
 326               Waterproof Level 2 Roof                                 10 days    Wed 4/04/18 Tue 17/04/18                                                                                                                                                                           Waterproof Level 2 Roof
 327               Install tiered garden metalwork to front entry          5 days     Wed 18/04/18 Tue 24/04/18                                                                                                                                                                            Install tiered garden metalwork to front entry
 328               Install Wire Landscape Terllis                          10 days    Wed 28/02/18 Tue 13/03/18                                                                                                                                                                 Install Wire Landscape Terllis
 329               Install Vegetable Garden Planters                       5 days     Tue 8/05/18    Mon 14/05/18                                                                                                                                                                                Install Vegetable Garden Planters
 330               Install roof angles                                     15 days    Wed 28/02/18 Tue 20/03/18                                                                                                                                                                  Install roof angles
 331               Install Roof Drainage                                   10 days    Wed 21/03/18 Thu 5/04/18                                                                                                                                                                        Install Roof Drainage
 332               Install Soil Mediums                                    20 days    Fri 6/04/18    Fri 4/05/18                                                                                                                                                                              Install Soil Mediums
 333               Install Planting                                        20 days    Tue 8/05/18    Mon 4/06/18                                                                                                                                                                                        Install Planting
 334            COMMISSION & HANDOVER                                      105 days   Thu 3/05/18    Thu 27/09/18                                                                                                                                                                                                                         COMMISSION & HANDOVER
 335               Commission & Test Electrical                            2 wks      Fri 17/08/18   Thu 30/08/18                                                                                                                                                                                                                 Commission & Test Electrical
 336               Commission & Test Mechanical                            2 wks      Fri 17/08/18   Thu 30/08/18                                                                                                                                                                                                                 Commission & Test Mechanical
 337               Commission & Test Hydraulic                             2 wks      Fri 17/08/18   Thu 30/08/18                                                                                                                                                                                                                 Commission & Test Hydraulic
 338               Commission & Test Lift                                  2 wks      Thu 3/05/18    Thu 17/05/18                                                                                                                                                                                 Commission & Test Lift
 339               Builders Quality Review                                 4 wks      Fri 31/08/18   Thu 27/09/18                                                                                                                                                                                                                         Builders Quality Review
 340               Client Inspections                                      0 days     Thu 27/09/18 Thu 27/09/18                                                                                                                                                                                                                           Client Inspections




                                      Task                          Summary                                   External Milestone                         Inactive Summary                       Manual Summary Rollup                     Finish-only                                Critical Split
Project: Seaview Terrace Program
                                      Split                         Project Summary                           Inactive Task                              Manual Task                            Manual Summary                            Deadline                                   Progress
Date: Fri 5/08/16
                                      Milestone                     External Tasks                            Inactive Milestone                         Duration-only                          Start-only                                Critical

                                                                                                                                                                            Page 6

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.