Seaview Terrace Target Program Rev 2 MM
Attached to the e-mail MCU14/0084 & OPW16/0021 Construction Management Plan - 71 Seaview Terrace.
SEAVIEW TERRACE
CONSTRUCTION PROGRAM - TARGET
DRAFT
ID Task Name Duration Start Finish July August September
OctoberNovember
December
January February
March April May June July August September
OctoberNovember
December
January February
March April May June July August September
OctoberNovember
December
January February
Ma
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
58 OFF-SITE ESTABLISHMENT 5 days Fri 19/08/16 Thu 25/08/16 OFF-SITE ESTABLISHMENT
59 Install Fences 2 days Fri 19/08/16 Mon 22/08/16 Install Fences
60 Install Shed 3 days Tue 23/08/16 Thu 25/08/16 Install Shed
61 CONSTRUCTION 516 days? Mon 15/08/16 Thu 27/09/18 CONSTRUCTION
62 CIVIL WORKS 225 days Mon 15/08/16 Tue 18/07/17 CIVIL WORKS
63 REVETMENT RL51.0 49 days Wed 24/08/16 Tue 1/11/16 REVETMENT RL51.0
64 Wall A 6 days Wed 24/08/16 Wed 31/08/16 Wall A
65 Wall B 3 days Thu 1/09/16 Mon 5/09/16 Wall B
66 Wall C 2 days Tue 6/09/16 Wed 7/09/16 Wall C
67 Wall D 3 days Thu 8/09/16 Mon 12/09/16 Wall D
68 Wall E 4 days Tue 13/09/16 Fri 16/09/16 Wall E
69 Wall F 31 days Mon 19/09/16 Tue 1/11/16
70 REVETMENT RL49.10 31 days Wed 2/11/16 Wed 14/12/16 REVETMENT RL49.10
71 Wall G 3 days Wed 2/11/16 Fri 4/11/16 Wall G
72 Wall H 7 days Mon 7/11/16 Tue 15/11/16 Wall H
73 Wall I 5 days Wed 16/11/16 Tue 22/11/16 Wall I
74 Wall J 4 days Wed 23/11/16 Mon 28/11/16 Wall J
75 Wall K 3 days Tue 29/11/16 Thu 1/12/16 Wall K
76 Wall L 2 days Fri 2/12/16 Mon 5/12/16 Wall L
77 Wall M 1 day Tue 6/12/16 Tue 6/12/16 Wall M
78 Wall N 3 days Wed 7/12/16 Fri 9/12/16 Wall N
79 Wall O 1 day Mon 12/12/16 Mon 12/12/16 Wall O
80 Wall P 2 days Tue 13/12/16 Wed 14/12/16 Wall P
81 REVETMENT RL 44.3 20 days Fri 27/01/17 Thu 23/02/17 REVETMENT RL 44.3
82 Wall Q 4 days Fri 27/01/17 Wed 1/02/17 Wall Q
83 Wall R 5 days Thu 2/02/17 Wed 8/02/17 Wall R
84 Wall S 3 days Thu 9/02/17 Mon 13/02/17 Wall S
85 Wall T 5 days Tue 14/02/17 Mon 20/02/17 Wall T
86 Wall U 2 days Tue 21/02/17 Wed 22/02/17 Wall U
87 Wall V 1 day Thu 23/02/17 Thu 23/02/17 Wall V
88 PILING 59 days Wed 26/04/17 Tue 18/07/17 PILING
89 Pool Screw Piling 6 days Wed 26/04/17 Thu 4/05/17 Pool Screw Piling
90 Basement Screw Piling 6 days Fri 23/06/17 Fri 30/06/17 Basement Screw Piling
91 Level 1 Screw Piling 12 days Mon 3/07/17 Tue 18/07/17 Level 1 Screw Piling
92 EXCAVATION 166 days Mon 15/08/16 Mon 24/04/17 EXCAVATION
93 Site Prep / Turnaround 1 wk Mon 15/08/16 Mon 22/08/16
94 Bulk Excavation to RL44.00 4 wks Thu 15/12/16 Wed 25/01/17 Bulk Excavation to RL44.00
95 Bulk Excavation to RL39.00 4 wks Fri 24/02/17 Thu 23/03/17
96 Excavate Pool Area to RL36.00 4 wks Fri 24/03/17 Mon 24/04/17 Excavate Pool Area to RL36.00
97 Excavate Tanks 1 wk Fri 24/03/17 Thu 30/03/17
98 BACKFILL 4 days Mon 19/06/17 Thu 22/06/17 BACKFILL
99 Backfill Basement / Pool 4 days Mon 19/06/17 Thu 22/06/17 Backfill Basement / Pool
100 STRUCTURAL WORKS 219 days Fri 5/05/17 Tue 3/04/18 STRUCTURAL WORKS
101 POOL BASEMENT RL36.00 27 days Fri 5/05/17 Mon 12/06/17 POOL BASEMENT RL36.00
102 Excavate Footings 2 days Fri 5/05/17 Mon 8/05/17 Excavate Footings
103 Reinforce Footings 2 days Tue 9/05/17 Wed 10/05/17 Reinforce Footings
104 Pour Footings 1 day Thu 11/05/17 Thu 11/05/17 Pour Footings
105 FRP Ground Slab 4 days Fri 12/05/17 Wed 17/05/17 FRP Ground Slab
106 Reinforced Block Walls 5 days Thu 18/05/17 Wed 24/05/17 Reinforced Block Walls
107 Strip Suspended Slab 3 days Thu 8/06/17 Mon 12/06/17 Strip Suspended Slab
108 WATER TANKS 22 days Thu 18/05/17 Fri 16/06/17 WATER TANKS
109 FRP Ground Slab 3 days Thu 18/05/17 Mon 22/05/17 FRP Ground Slab
110 FRP Tank Walls 3 days Tue 23/05/17 Thu 25/05/17 FRP Tank Walls
111 FRP Tank Lid 5 days Fri 26/05/17 Thu 1/06/17 FRP Tank Lid
112 Strip Tank Lid Formworks 1 day Fri 16/06/17 Fri 16/06/17 Strip Tank Lid Formworks
113 POOL 17 days Thu 25/05/17 Fri 16/06/17 POOL
114 Form Pool Walls and Base 1 wk Thu 25/05/17 Wed 31/05/17 Form Pool Walls and Base
Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only Critical Split
Project: Seaview Terrace Program
Split Project Summary Inactive Task Manual Task Manual Summary Deadline Progress
Date: Fri 5/08/16
Milestone External Tasks Inactive Milestone Duration-only Start-only Critical
Page 2