Seaview Terrace Target Program Rev 2 MM
Attached to the e-mail MCU14/0084 & OPW16/0021 Construction Management Plan - 71 Seaview Terrace.
SEAVIEW TERRACE
CONSTRUCTION PROGRAM - TARGET
DRAFT
ID Task Name Duration Start Finish July August September
OctoberNovember
December
January February
March April May June July August September
OctoberNovember
December
January February
March April May June July August September
OctoberNovember
December
January February
Ma
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
1 KEY DATES 540 days Tue 9/08/16 Thu 25/10/18 KEY DATES
2 Op Works Approval 0 days Tue 9/08/16 Tue 9/08/16 Op Works Approval
3 Site Possession 0 days Tue 23/08/16 Tue 23/08/16 Site Possession
4 Target Practical Completion 0 days Thu 27/09/18 Thu 27/09/18 Target Practical Completion
5 Trade / Weather Delays 4 wks Fri 28/09/18 Thu 25/10/18 Trade / Weather Delays
6 Completion 0 days Thu 25/10/18 Thu 25/10/18 Completion
7
8 OPWORKS HOLD POINTS / INSPECTIONS 10 days Tue 9/08/16 Tue 23/08/16 OPWORKS HOLD POINTS / INSPECTIONS
9 Notify Council for Prestart (5 Days Notice) 0 days Thu 11/08/16 Thu 11/08/16 Notify Council for Prestart (5 Days Notice)
10 Prestart Meeting 0 days Thu 18/08/16 Thu 18/08/16 Prestart Meeting
11 Issue copies of Signed Engineering Drawings to Council 0 days Thu 18/08/16 Thu 18/08/16 Issue copies of Signed Engineering Drawings to Council
12 Issue copy of Builders Insurances 0 days Thu 18/08/16 Thu 18/08/16 Issue copy of Builders Insurances
13 Issue Construction Management Plan 0 days Thu 18/08/16 Thu 18/08/16 Issue Construction Management Plan
14 RPEQ Earthwork Report 0 days Thu 18/08/16 Thu 18/08/16 RPEQ Earthwork Report
15 Install Open Space Conservation Fence 0 days Tue 16/08/16 Tue 16/08/16 Install Open Space Conservation Fence
16 Issue Landscape Installation Confirmation [Prior to Use] 0 days Tue 9/08/16 Tue 9/08/16 Issue Landscape Installation Confirmation [Prior to Use]
17 RPEQ Inspect Erosion and Sediment Control 0 days Mon 22/08/16 Mon 22/08/16 RPEQ Inspect Erosion and Sediment Control
18 Council Inspect Erosion and Sediment Control 0 days Tue 23/08/16 Tue 23/08/16 Council Inspect Erosion and Sediment Control
19 Issue Bio Retention Basin Dissipators Design to Council 0 days Tue 9/08/16 Tue 9/08/16 Issue Bio Retention Basin Dissipators Design to Council
20 Council Inspection of Impervious Liner to Bio Retention Basins 0 days Tue 9/08/16 Tue 9/08/16 Council Inspection of Impervious Liner to Bio Retention Basins
21 Submit As-Constructed Drawings to Council 0 days Tue 9/08/16 Tue 9/08/16 Submit As-Constructed Drawings to Council
22
23 PROCUREMENT / FABRICATION 130 days Tue 9/08/16 Thu 23/02/17 PROCUREMENT / FABRICATION
24 STRUCTURAL STEEL 50 days Tue 9/08/16 Wed 19/10/16 STRUCTURAL STEEL
25 Procure Structural Steel 2 wks Tue 9/08/16 Tue 23/08/16 Procure Structural Steel
26 Structural Steel Shop Drawings 2 wks Wed 24/08/16 Tue 6/09/16 Structural Steel Shop Drawings
27 Submit Structural Steel Shop Drawings for Approval 0 days Tue 6/09/16 Tue 6/09/16 Submit Structural Steel Shop Drawings for Approval
28 Structural Steel Shop Drawings Approval 2 wks Wed 7/09/16 Tue 20/09/16 Structural Steel Shop Drawings Approval
29 Fabricate Structural Steel 4 wks Wed 21/09/16 Wed 19/10/16 Fabricate Structural Steel
30 Fabricate Steel Stair Treads 6 wks Wed 7/09/16 Wed 19/10/16 Fabricate Steel Stair Treads
31 ALUMINIUM WINDOWS 90 days Tue 9/08/16 Wed 14/12/16 ALUMINIUM WINDOWS
32 Procure Aluminium Windows 2 wks Tue 9/08/16 Tue 23/08/16 Procure Aluminium Windows
33 Aluminium Window Shop Drawings 3 wks Wed 24/08/16 Tue 13/09/16 Aluminium Window Shop Drawings
34 Submit Aluminium Window Shop Drawings 0 days Tue 13/09/16 Tue 13/09/16 Submit Aluminium Window Shop Drawings
35 Approve Aluminium Window Shop Drawings 3 wks Wed 14/09/16 Wed 5/10/16 Approve Aluminium Window Shop Drawings
36 Fabricate Aluminium Windows 10 wks Thu 6/10/16 Wed 14/12/16 Fabricate Aluminium Windows
37 CABINETWORK 90 days Tue 9/08/16 Wed 14/12/16 CABINETWORK
38 Procure Cabinetwork 2 wks Tue 9/08/16 Tue 23/08/16 Procure Cabinetwork
39 Cabinetwork Shop Drawings 3 wks Wed 24/08/16 Tue 13/09/16 Cabinetwork Shop Drawings
40 Submit Cabinetwork Shop Drawings 0 days Tue 13/09/16 Tue 13/09/16 Submit Cabinetwork Shop Drawings
41 Approva Cabinetwork Shop Drawings 3 wks Wed 14/09/16 Wed 5/10/16 Approva Cabinetwork Shop Drawings
42 Fabricate Cabinetwork 10 wks Thu 6/10/16 Wed 14/12/16 Fabricate Cabinetwork
43 PROCURE LIFT 130 days Tue 9/08/16 Thu 23/02/17 PROCURE LIFT
44 Procure Lift 2 wks Tue 9/08/16 Tue 23/08/16 Procure Lift
45 Lift Shop Drawings 2 wks Wed 24/08/16 Tue 6/09/16 Lift Shop Drawings
46 Submit Lift Shop Drawings 0 days Tue 6/09/16 Tue 6/09/16 Submit Lift Shop Drawings
47 Approve Lift Shop Drawings 2 wks Wed 7/09/16 Tue 20/09/16 Approve Lift Shop Drawings
48 Manufacture / Deliver Lift 20 wks Wed 21/09/16 Thu 23/02/17 Manufacture / Deliver Lift
49 PROCURE HEMPCRETE 80 days Tue 9/08/16 Wed 30/11/16 PROCURE HEMPCRETE
50 Prepare Shop Drawings [NRA] 2 wks Tue 9/08/16 Tue 23/08/16 Prepare Shop Drawings [NRA]
51 Fabrication and Delivery 14 wks Wed 24/08/16 Wed 30/11/16 Fabrication and Delivery
52 ESTABLISHMENT 15 days Tue 9/08/16 Tue 30/08/16 ESTABLISHMENT
53 SITE ESTABLISHMENT 15 days Tue 9/08/16 Tue 30/08/16 SITE ESTABLISHMENT
54 Dilapidation Survey 1 wk Tue 9/08/16 Mon 15/08/16 Dilapidation Survey
55 Services Identification 1 wk Tue 9/08/16 Mon 15/08/16 Services Identification
56 Establish Sheds 1 wk Wed 24/08/16 Tue 30/08/16 Establish Sheds
57 Esrtablish Fences 1 wk Wed 24/08/16 Tue 30/08/16 Esrtablish Fences
Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only Critical Split
Project: Seaview Terrace Program
Split Project Summary Inactive Task Manual Task Manual Summary Deadline Progress
Date: Fri 5/08/16
Milestone External Tasks Inactive Milestone Duration-only Start-only Critical
Page 1
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.