Seaview Terrace Target Program Rev 2 MM

Attached to the e-mail MCU14/0084 & OPW16/0021 Construction Management Plan - 71 Seaview Terrace.

of 6

Page text shows just the words. Original shows the document exactly as it was published.

                                                                                                                                                                     SEAVIEW TERRACE
                                                                                                                                                              CONSTRUCTION PROGRAM - TARGET
                                                                                                                                                                          DRAFT
ID           Task Name                                                            Duration   Start          Finish              July      August September
                                                                                                                                                       OctoberNovember
                                                                                                                                                                    December
                                                                                                                                                                          January February
                                                                                                                                                                                         March April                 May      June    July    August September
                                                                                                                                                                                                                                                           OctoberNovember
                                                                                                                                                                                                                                                                        December
                                                                                                                                                                                                                                                                              January February
                                                                                                                                                                                                                                                                                             March April    May       June    July    August September
                                                                                                                                                                                                                                                                                                                                                   OctoberNovember
                                                                                                                                                                                                                                                                                                                                                                 December
                                                                                                                                                                                                                                                                                                                                                                       January February
                                                                                                                                                                                                                                                                                                                                                                                      Ma
                                                                                                                                  Jul      Aug    Sep    Oct   Nov   Dec    Jan    Feb     Mar  Apr                   May       Jun     Jul    Aug    Sep    Oct   Nov   Dec    Jan    Feb    Mar   Apr      May        Jun     Jul    Aug    Sep    Oct   Nov    Dec    Jan    Feb
     1       KEY DATES                                                            540 days   Tue 9/08/16    Thu 25/10/18                                                                                                                                                                                                                                  KEY DATES
     2          Op Works Approval                                                 0 days     Tue 9/08/16    Tue 9/08/16                     Op Works Approval
     3          Site Possession                                                   0 days     Tue 23/08/16 Tue 23/08/16                          Site Possession
     4          Target Practical Completion                                       0 days     Thu 27/09/18 Thu 27/09/18                                                                                                                                                                                                                              Target Practical Completion
     5          Trade / Weather Delays                                            4 wks      Fri 28/09/18   Thu 25/10/18                                                                                                                                                                                                                                  Trade / Weather Delays
     6          Completion                                                        0 days     Thu 25/10/18 Thu 25/10/18                                                                                                                                                                                                                                     Completion
     7
     8       OPWORKS HOLD POINTS / INSPECTIONS                                    10 days    Tue 9/08/16    Tue 23/08/16                        OPWORKS HOLD POINTS / INSPECTIONS
     9          Notify Council for Prestart (5 Days Notice)                       0 days     Thu 11/08/16 Thu 11/08/16                       Notify Council for Prestart (5 Days Notice)
     10         Prestart Meeting                                                  0 days     Thu 18/08/16 Thu 18/08/16                         Prestart Meeting
     11         Issue copies of Signed Engineering Drawings to Council            0 days     Thu 18/08/16 Thu 18/08/16                         Issue copies of Signed Engineering Drawings to Council
     12         Issue copy of Builders Insurances                                 0 days     Thu 18/08/16 Thu 18/08/16                         Issue copy of Builders Insurances
     13         Issue Construction Management Plan                                0 days     Thu 18/08/16 Thu 18/08/16                         Issue Construction Management Plan
     14         RPEQ Earthwork Report                                             0 days     Thu 18/08/16 Thu 18/08/16                         RPEQ Earthwork Report
     15         Install Open Space Conservation Fence                             0 days     Tue 16/08/16 Tue 16/08/16                        Install Open Space Conservation Fence
     16         Issue Landscape Installation Confirmation [Prior to Use]          0 days     Tue 9/08/16    Tue 9/08/16                     Issue Landscape Installation Confirmation [Prior to Use]
     17         RPEQ Inspect Erosion and Sediment Control                         0 days     Mon 22/08/16 Mon 22/08/16                         RPEQ Inspect Erosion and Sediment Control
     18         Council Inspect Erosion and Sediment Control                      0 days     Tue 23/08/16 Tue 23/08/16                          Council Inspect Erosion and Sediment Control
     19         Issue Bio Retention Basin Dissipators Design to Council           0 days     Tue 9/08/16    Tue 9/08/16                     Issue Bio Retention Basin Dissipators Design to Council
     20         Council Inspection of Impervious Liner to Bio Retention Basins    0 days     Tue 9/08/16    Tue 9/08/16                     Council Inspection of Impervious Liner to Bio Retention Basins
     21         Submit As-Constructed Drawings to Council                         0 days     Tue 9/08/16    Tue 9/08/16                     Submit As-Constructed Drawings to Council
     22
     23      PROCUREMENT / FABRICATION                                            130 days   Tue 9/08/16    Thu 23/02/17                                                                             PROCUREMENT / FABRICATION
     24         STRUCTURAL STEEL                                                  50 days    Tue 9/08/16    Wed 19/10/16                                       STRUCTURAL STEEL
     25            Procure Structural Steel                                       2 wks      Tue 9/08/16    Tue 23/08/16                       Procure Structural Steel
     26            Structural Steel Shop Drawings                                 2 wks      Wed 24/08/16 Tue 6/09/16                              Structural Steel Shop Drawings
     27            Submit Structural Steel Shop Drawings for Approval             0 days     Tue 6/09/16    Tue 6/09/16                             Submit Structural Steel Shop Drawings for Approval
     28            Structural Steel Shop Drawings Approval                        2 wks      Wed 7/09/16 Tue 20/09/16                                  Structural Steel Shop Drawings Approval
     29            Fabricate Structural Steel                                     4 wks      Wed 21/09/16 Wed 19/10/16                                         Fabricate Structural Steel
     30            Fabricate Steel Stair Treads                                   6 wks      Wed 7/09/16 Wed 19/10/16                                          Fabricate Steel Stair Treads
     31         ALUMINIUM WINDOWS                                                 90 days    Tue 9/08/16    Wed 14/12/16                                                       ALUMINIUM WINDOWS
     32            Procure Aluminium Windows                                      2 wks      Tue 9/08/16    Tue 23/08/16                       Procure Aluminium Windows
     33            Aluminium Window Shop Drawings                                 3 wks      Wed 24/08/16 Tue 13/09/16                               Aluminium Window Shop Drawings
     34            Submit Aluminium Window Shop Drawings                          0 days     Tue 13/09/16 Tue 13/09/16                                Submit Aluminium Window Shop Drawings
     35            Approve Aluminium Window Shop Drawings                         3 wks      Wed 14/09/16 Wed 5/10/16                                      Approve Aluminium Window Shop Drawings
     36            Fabricate Aluminium Windows                                    10 wks     Thu 6/10/16    Wed 14/12/16                                                      Fabricate Aluminium Windows
     37         CABINETWORK                                                       90 days    Tue 9/08/16    Wed 14/12/16                                                       CABINETWORK
     38            Procure Cabinetwork                                            2 wks      Tue 9/08/16    Tue 23/08/16                       Procure Cabinetwork
     39            Cabinetwork Shop Drawings                                      3 wks      Wed 24/08/16 Tue 13/09/16                               Cabinetwork Shop Drawings
     40            Submit Cabinetwork Shop Drawings                               0 days     Tue 13/09/16 Tue 13/09/16                                Submit Cabinetwork Shop Drawings
     41            Approva Cabinetwork Shop Drawings                              3 wks      Wed 14/09/16 Wed 5/10/16                                      Approva Cabinetwork Shop Drawings
     42            Fabricate Cabinetwork                                          10 wks     Thu 6/10/16    Wed 14/12/16                                                      Fabricate Cabinetwork
     43         PROCURE LIFT                                                      130 days   Tue 9/08/16    Thu 23/02/17                                                                             PROCURE LIFT
     44            Procure Lift                                                   2 wks      Tue 9/08/16    Tue 23/08/16                       Procure Lift
     45            Lift Shop Drawings                                             2 wks      Wed 24/08/16 Tue 6/09/16                              Lift Shop Drawings
     46            Submit Lift Shop Drawings                                      0 days     Tue 6/09/16    Tue 6/09/16                             Submit Lift Shop Drawings
     47            Approve Lift Shop Drawings                                     2 wks      Wed 7/09/16 Tue 20/09/16                                  Approve Lift Shop Drawings
     48            Manufacture / Deliver Lift                                     20 wks     Wed 21/09/16 Thu 23/02/17                                                                               Manufacture / Deliver Lift
     49         PROCURE HEMPCRETE                                                 80 days    Tue 9/08/16    Wed 30/11/16                                                   PROCURE HEMPCRETE
     50            Prepare Shop Drawings [NRA]                                    2 wks      Tue 9/08/16    Tue 23/08/16                       Prepare Shop Drawings [NRA]
     51            Fabrication and Delivery                                       14 wks     Wed 24/08/16 Wed 30/11/16                                                     Fabrication and Delivery
     52      ESTABLISHMENT                                                        15 days    Tue 9/08/16    Tue 30/08/16                          ESTABLISHMENT
     53         SITE ESTABLISHMENT                                                15 days    Tue 9/08/16    Tue 30/08/16                          SITE ESTABLISHMENT
     54            Dilapidation Survey                                            1 wk       Tue 9/08/16    Mon 15/08/16                     Dilapidation Survey
     55            Services Identification                                        1 wk       Tue 9/08/16    Mon 15/08/16                     Services Identification
     56            Establish Sheds                                                1 wk       Wed 24/08/16 Tue 30/08/16                           Establish Sheds
     57            Esrtablish Fences                                              1 wk       Wed 24/08/16 Tue 30/08/16                           Esrtablish Fences


                                     Task                                  Summary                                   External Milestone                              Inactive Summary                                Manual Summary Rollup                     Finish-only                           Critical Split
Project: Seaview Terrace Program
                                     Split                                 Project Summary                           Inactive Task                                   Manual Task                                     Manual Summary                            Deadline                              Progress
Date: Fri 5/08/16
                                     Milestone                             External Tasks                            Inactive Milestone                              Duration-only                                   Start-only                                Critical

                                                                                                                                                                                            Page 1
Log in to download the original file

Seaview Terrace Target Program Rev 2 MM.pdf · 654 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.