Seaview Terrace Target Program Rev 2 MM
Attached to the e-mail MCU14/0084 & OPW16/0021 Construction Management Plan - 71 Seaview Terrace.
SEAVIEW TERRACE
CONSTRUCTION PROGRAM - TARGET
DRAFT
ID Task Name Duration Start Finish July August September
OctoberNovember
December
January February
March April May June July August September
OctoberNovember
December
January February
March April May June July August September
OctoberNovember
December
January February
Ma
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
286 Rough-In Electrical 3 days Thu 24/05/18 Mon 28/05/18 Rough-In Electrical
287 Rough-In Mechanical 4 days Thu 10/05/18 Tue 15/05/18 Rough-In Mechanical
288 Gyprock Wall Linings 6 days Tue 29/05/18 Tue 5/06/18 Gyprock Wall Linings
289 Gyprock Ceiling Linings 6 days Tue 29/05/18 Tue 5/06/18 Gyprock Ceiling Linings
290 Waterproofing 4 days Wed 6/06/18 Mon 11/06/18 Waterproofing
291 Carpentry - Doors and Hardware 5 days Wed 6/06/18 Tue 12/06/18 Carpentry - Doors and Hardware
292 Floor Tiling - Entry Lobby 5 days Wed 13/06/18 Tue 19/06/18 Floor Tiling - Entry Lobby
293 Floor Tiling - Workshop / Study 5 days Wed 20/06/18 Tue 26/06/18 Floor Tiling - Workshop / Study
294 Floor Tiling Bed 06 5 days Wed 27/06/18 Tue 3/07/18 Floor Tiling Bed 06
295 Floor Tiling - Bathroom 5 days Tue 12/06/18 Mon 18/06/18 Floor Tiling - Bathroom
296 Floor Tiling - Guest Ensuite 5 days Tue 19/06/18 Mon 25/06/18 Floor Tiling - Guest Ensuite
297 Wall Tiling Bathroom 3 days Tue 19/06/18 Thu 21/06/18 Wall Tiling Bathroom
298 Wall Tiling Guest Ensuite 3 days Tue 26/06/18 Thu 28/06/18 Wall Tiling Guest Ensuite
299 Install vanity Benches & Stone Tops 2 days Fri 29/06/18 Mon 2/07/18 Install vanity Benches & Stone Tops
300 Install Shower Screens & Mirrors 2 days Fri 29/06/18 Mon 2/07/18 Install Shower Screens & Mirrors
301 Paint Finish 2 wks Fri 29/06/18 Thu 12/07/18 Paint Finish
302 Electrical Fit-Off 1 wk Fri 13/07/18 Thu 19/07/18 Electrical Fit-Off
303 Hydraulic Fit-Off 1 wk Fri 13/07/18 Thu 19/07/18 Hydraulic Fit-Off
304 Mechanical Fit-Off 1 wk Fri 13/07/18 Thu 19/07/18 Mechanical Fit-Off
305 ROOF 121 days Thu 12/10/17 Tue 24/04/18 ROOF
306 Waterproof Basement Roof Gardens 2 wks Thu 12/10/17 Wed 25/10/17 Waterproof Basement Roof Gardens
307 Waterproo Level 1 Roof Gardens 2 wks Wed 17/01/18 Wed 31/01/18 Waterproo Level 1 Roof Gardens
308 Waterproof Level 2 Roof Gardens 2 wks Wed 4/04/18 Tue 17/04/18 Waterproof Level 2 Roof Gardens
309 Install Glass Skylights 1 wk Wed 18/04/18 Tue 24/04/18 Install Glass Skylights
310 Install Solar Panels to Roof 1 wk Wed 18/04/18 Tue 24/04/18 Install Solar Panels to Roof
311 EXTERNAL 11 days Tue 6/03/18 Tue 20/03/18 EXTERNAL
312 Bin Store Structure 3 days Tue 6/03/18 Thu 8/03/18 Bin Store Structure
313 Turning Bay Retaining Wall 6 days Tue 6/03/18 Tue 13/03/18 Turning Bay Retaining Wall
314 FRP Turning Bay Stairs 5 days Tue 6/03/18 Mon 12/03/18 FRP Turning Bay Stairs
315 Split Face Blockwork Wall to Boundary 10 days Tue 6/03/18 Mon 19/03/18 Split Face Blockwork Wall to Boundary
316 FRP Plantroom Slab 3 days Tue 6/03/18 Thu 8/03/18 FRP Plantroom Slab
317 FRP Driveway 8 days Tue 6/03/18 Thu 15/03/18 FRP Driveway
318 Plantroom Structure 5 days Tue 6/03/18 Mon 12/03/18 Plantroom Structure
319 Plantroom Roof 3 days Tue 13/03/18 Thu 15/03/18 Plantroom Roof
320 Plantroom Screens 3 days Fri 16/03/18 Tue 20/03/18 Plantroom Screens
321 FRP Footings Bin Store / Gate Walls 2 days Tue 6/03/18 Wed 7/03/18 FRP Footings Bin Store / Gate Walls
322 Split Face Blockwork Bin Store / Gate Walls 5 days Fri 9/03/18 Thu 15/03/18 Split Face Blockwork Bin Store / Gate Walls
323 LANDSCAPING 148 days Thu 12/10/17 Mon 4/06/18 LANDSCAPING
324 Waterproof Basement Roof 10 days Thu 12/10/17 Wed 25/10/17 Waterproof Basement Roof
325 Waterproof Level 1 Roof 10 days Wed 14/02/18 Tue 27/02/18 Waterproof Level 1 Roof
326 Waterproof Level 2 Roof 10 days Wed 4/04/18 Tue 17/04/18 Waterproof Level 2 Roof
327 Install tiered garden metalwork to front entry 5 days Wed 18/04/18 Tue 24/04/18 Install tiered garden metalwork to front entry
328 Install Wire Landscape Terllis 10 days Wed 28/02/18 Tue 13/03/18 Install Wire Landscape Terllis
329 Install Vegetable Garden Planters 5 days Tue 8/05/18 Mon 14/05/18 Install Vegetable Garden Planters
330 Install roof angles 15 days Wed 28/02/18 Tue 20/03/18 Install roof angles
331 Install Roof Drainage 10 days Wed 21/03/18 Thu 5/04/18 Install Roof Drainage
332 Install Soil Mediums 20 days Fri 6/04/18 Fri 4/05/18 Install Soil Mediums
333 Install Planting 20 days Tue 8/05/18 Mon 4/06/18 Install Planting
334 COMMISSION & HANDOVER 105 days Thu 3/05/18 Thu 27/09/18 COMMISSION & HANDOVER
335 Commission & Test Electrical 2 wks Fri 17/08/18 Thu 30/08/18 Commission & Test Electrical
336 Commission & Test Mechanical 2 wks Fri 17/08/18 Thu 30/08/18 Commission & Test Mechanical
337 Commission & Test Hydraulic 2 wks Fri 17/08/18 Thu 30/08/18 Commission & Test Hydraulic
338 Commission & Test Lift 2 wks Thu 3/05/18 Thu 17/05/18 Commission & Test Lift
339 Builders Quality Review 4 wks Fri 31/08/18 Thu 27/09/18 Builders Quality Review
340 Client Inspections 0 days Thu 27/09/18 Thu 27/09/18 Client Inspections
Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only Critical Split
Project: Seaview Terrace Program
Split Project Summary Inactive Task Manual Task Manual Summary Deadline Progress
Date: Fri 5/08/16
Milestone External Tasks Inactive Milestone Duration-only Start-only Critical
Page 6