Seaview Terrace Target Program Rev 2 MM
Attached to the e-mail MCU14/0084 & OPW16/0021 Construction Management Plan - 71 Seaview Terrace.
SEAVIEW TERRACE
CONSTRUCTION PROGRAM - TARGET
DRAFT
ID Task Name Duration Start Finish July August September
OctoberNovember
December
January February
March April May June July August September
OctoberNovember
DecemberJanuary February
March April May June July August September
OctoberNovember
December
January February
Ma
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
229 Terrace Tiling 4 days Mon 4/12/17 Thu 7/12/17 Terrace Tiling
230 Sauna Fit-Off 2 wks Wed 8/11/17 Tue 21/11/17 Sauna Fit-Off
231 Steam Room Fit-Off 2 wks Wed 8/11/17 Tue 21/11/17 Steam Room Fit-Off
232 Ice Bath Fit-Off 3 days Wed 15/11/17 Fri 17/11/17 Ice Bath Fit-Off
233 Kitchenette / Bar Joinery 1 wk Wed 15/11/17 Tue 21/11/17 Kitchenette / Bar Joinery
234 Wall Tiling Change Room 3 days Tue 21/11/17 Thu 23/11/17 Wall Tiling Change Room
235 Wall Tiling WC 3 days Fri 24/11/17 Tue 28/11/17 Wall Tiling WC
236 Wall Tiling Powder 3 days Wed 29/11/17 Fri 1/12/17 Wall Tiling Powder
237 Install vanity Benches & Stone Tops 2 days Mon 4/12/17 Tue 5/12/17 Install vanity Benches & Stone Tops
238 Install Shower Screens & Mirrors 2 days Wed 6/12/17 Thu 7/12/17 Install Shower Screens & Mirrors
239 Paint Finish 2 wks Fri 8/12/17 Thu 21/12/17 Paint Finish
240 Electrical Fit-Off 1 wk Wed 6/12/17 Tue 12/12/17 Electrical Fit-Off
241 Hydraulic Fit-Off 1 wk Wed 6/12/17 Tue 12/12/17 Hydraulic Fit-Off
242 Mechanical Fit-Off 1 wk Fri 15/12/17 Thu 21/12/17 Mechanical Fit-Off
243 Carpet Installation 2 days Fri 22/12/17 Mon 15/01/18 Carpet Installation
244 LEVEL 1 105 days Fri 16/03/18 Thu 16/08/18 LEVEL 1
245 Watertight 0 days Fri 16/03/18 Fri 16/03/18 Watertight
246 Install Hempcrete Walls 2 wks Mon 19/03/18 Tue 3/04/18 Install Hempcrete Walls
247 Metal Wall Framing 3 wks Wed 4/04/18 Tue 24/04/18 Metal Wall Framing
248 Ceiling Framing 2 wks Wed 4/04/18 Tue 17/04/18 Ceiling Framing
249 Rough-In Hydraulic 1 wk Thu 26/04/18 Wed 2/05/18 Rough-In Hydraulic
250 Rough-In Electrical 2 wks Thu 26/04/18 Thu 10/05/18 Rough-In Electrical
251 Rough-In Mechanical 2 wks Mon 19/03/18 Tue 3/04/18 Rough-In Mechanical
252 Gyprock Wall Linings 2 wks Fri 11/05/18 Thu 24/05/18 Gyprock Wall Linings
253 Gyprock Ceiling Linings 2 wks Wed 4/04/18 Tue 17/04/18 Gyprock Ceiling Linings
254 Waterproofing 1 wk Fri 25/05/18 Thu 31/05/18 Waterproofing
255 Carpentry - Doors and Hardware 2 wks Fri 25/05/18 Thu 7/06/18 Carpentry - Doors and Hardware
256 Floor Tiling - Living, Dining, Kitchen, Pantry 2 wks Fri 8/06/18 Thu 21/06/18 Floor Tiling - Living, Dining, Kitchen, Pantry
257 Floor Tiling Bedrooms 4 wks Fri 8/06/18 Thu 5/07/18 Floor Tiling Bedrooms
258 Floor Tiling Laundry 4 days Fri 1/06/18 Wed 6/06/18 Floor Tiling Laundry
259 Floor Tiling Ensuites 18 days Fri 1/06/18 Tue 26/06/18 Floor Tiling Ensuites
260 Terrace Tiling 1 wk Fri 1/06/18 Thu 7/06/18 Terrace Tiling
261 Install Balustrade 1 wk Fri 8/06/18 Thu 14/06/18 Install Balustrade
262 Wall Tiling - Ensuite Master 4 days Wed 27/06/18 Mon 2/07/18 Wall Tiling - Ensuite Master
263 Wall Tiling - Ensuite Bed 02 4 days Tue 3/07/18 Fri 6/07/18 Wall Tiling - Ensuite Bed 02
264 Wall Tiling - Ensuite Bed 03 4 days Mon 9/07/18 Thu 12/07/18 Wall Tiling - Ensuite Bed 03
265 Wall Tiling - Ensuite Bed 04 4 days Fri 13/07/18 Wed 18/07/18 Wall Tiling - Ensuite Bed 04
266 Wall Tiling - Ensuite Bed 05 4 days Thu 19/07/18 Tue 24/07/18 Wall Tiling - Ensuite Bed 05
267 Wall Tiling - Powder 2 days Wed 25/07/18 Thu 26/07/18 Wall Tiling - Powder
268 Wall Tiling - Laundry 2 days Wed 25/07/18 Thu 26/07/18 Wall Tiling - Laundry
269 Install Master Robes, Ensuite & Stdy Joinery 4 days Tue 3/07/18 Fri 6/07/18 Install Master Robes, Ensuite & Stdy Joinery
270 Install Bed 02 Robe, Ensuite & Study 4 days Mon 9/07/18 Thu 12/07/18 Install Bed 02 Robe, Ensuite & Study
271 Install Bed 03 Robe, Ensuite & Study 4 days Fri 13/07/18 Wed 18/07/18 Install Bed 03 Robe, Ensuite & Study
272 Install Bed 04 Robe, Ensuite & Study 4 days Thu 19/07/18 Tue 24/07/18 Install Bed 04 Robe, Ensuite & Study
273 Install Bed 05 Robe, Ensuite & Study 4 days Wed 25/07/18 Mon 30/07/18 Install Bed 05 Robe, Ensuite & Study
274 Install Laundry Joinery 3 days Fri 27/07/18 Tue 31/07/18 Install Laundry Joinery
275 Install Shower Screen and Mirrors 5 days Wed 25/07/18 Tue 31/07/18 Install Shower Screen and Mirrors
276 Paint Finish 3 wks Fri 27/07/18 Thu 16/08/18 Paint Finish
277 Electrical Fit-Off 2 wks Fri 3/08/18 Thu 16/08/18 Electrical Fit-Off
278 Mechanical Fit-Off 2 wks Fri 3/08/18 Thu 16/08/18 Mechanical Fit-Off
279 Hydraulic Fit-Off 2 wks Fri 3/08/18 Thu 16/08/18 Hydraulic Fit-Off
280 LEVEL 2 52 days? Wed 9/05/18 Thu 19/07/18 LEVEL 2
281 Watertight 1 day? Wed 9/05/18 Wed 9/05/18 Watertight
282 Install Hempcrete Walls 5 days Thu 10/05/18 Wed 16/05/18 Install Hempcrete Walls
283 Metal Wall Framing 5 days Thu 17/05/18 Wed 23/05/18 Metal Wall Framing
284 Ceiling Framing 5 days Thu 17/05/18 Wed 23/05/18 Ceiling Framing
285 Rough-In Hydraulic 3 days Thu 24/05/18 Mon 28/05/18 Rough-In Hydraulic
Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only Critical Split
Project: Seaview Terrace Program
Split Project Summary Inactive Task Manual Task Manual Summary Deadline Progress
Date: Fri 5/08/16
Milestone External Tasks Inactive Milestone Duration-only Start-only Critical
Page 5