MCU16/0079 Town Planning Report
Town Planning Report
“Undefined Use”
Staged Extension & Refurbishment of Existing RSL Club
5 Memorial Ave, Tewantin QLD 4565
Lot 3 on T16319 and Lot 10 on SP273411
14.165 Design and construction (sewer)
O8 Sewerage reticulation infrastructure— S8.1 Sewerage reticulation infrastructure is designed in Complies with the Probable Solutions – all sewer
a) meets the needs of the users; accordance with PSP6 Engineering Design Standards – infrastructures has been designed in accordance with PSP6.
b) is designed to be compatible with existing infrastructure; Water and Sewerage. Council is directed to Appendix B – Architectural Plans for
and further details.
c) is designed using materials that are suitable of the use,
durable, easy to maintain and cost effective, taking into
account the whole of life cycle cost and Council’s
maintenance inventory.
O9 Sewerage reticulation infrastructure is constructed— S9.1 Sewerage reticulation infrastructure is constructed in Complies with the Probable Solutions – The proposed
a) in accordance with appropriate engineering standards; and accordance with PSP6 –Engineering Design Standards — sewer connections has been designed in accordance with
b) to minimise adverse environmental impacts Water and Sewerage and As Constructed data submitted in PSP6. All documentation will be provided during the
accordance with PSP6 –Engineering Design Standards — Operational Works, Building and Plumbing application stage.
Water and Sewerage;
AND All erosion and sediment control measures have been
S9.2 Erosion and sediment control measures are designed designed in accordance with the control guidelines. All
and implemented in accordance with the Institution of documentation will be provided during the Operational Works,
Engineers Australia (Queensland Division) Soil Erosion and Building and Plumbing application stage.
Sediment Control - Guidelines for Queensland Construction
Sites.
O10 Sewerage reticulation infrastructure is proven to be No solution provided. Complies with the Specific Outcome – The proposed
suitable for its use prior to Council accepting the dedicated development includes an upgrade to the existing sewer line
asset. which services the site. It is considered all new access will be
developed to Council’s standards and appropriate inspections
will be carried out to prove its standard of development.
O11 Sewerage reticulation infrastructure is provided with all No solution provided. Complies with the Specific Outcome – The proposed
supporting technical documentation. development includes an upgrade to the existing sewer line
which services the site. All new sewer connections will be
completed in accordance with Council standards. All
documentation will be provided during the Operation Works
application and Building and plumbing Application.
July 2016 Page | 58
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (MCU16_0079 Town Planning Report.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.