MCU16/0079 Town Planning Report

of 64

Page text read automatically using OCR, there may be inaccuracies

                                                                                                                                                                                   Town Planning Report
                                                                                                                                                                                          “Undefined Use”
                                                                                                                                                     Staged Extension & Refurbishment of Existing RSL Club
                                                                                                                                                                       5 Memorial Ave, Tewantin QLD 4565
                                                                                                                                                                  Lot 3 on T16319 and Lot 10 on SP273411

O2 Water supply infrastructure is constructed—                    S2.1 Water supply infrastructure is constructed in accordance      Complies – The proposed water connections and water
a) in accordance with appropriate engineering standards; and      with PSP6 –Engineering Design Standards — Water and                supply infrastructure has been designed in accordance with
b) to minimise adverse environmental impacts.                     Sewerage; AND                                                      PSP6. All documentation will be provided during the
                                                                  S2.2 Erosion and sediment control measures are designed            Operational Works, Building and Plumbing application stage.
                                                                  and implemented in accordance with the Institution of
                                                                  Engineers Australia (Queensland Division) Soil Erosion and         All erosion and sediment control measures have been
                                                                  Sediment Control - Guidelines for Queensland Construction          designed in accordance with the control guidelines. All
                                                                  Sites.                                                             documentation will be provided during the Operational Works,
                                                                                                                                     Building and Plumbing application stage.
O3 Water supply infrastructure is proven to be suitable for its   No solution provided.                                              N/A - The proposed development does not include any items
use prior to Council accepting the dedicated asset.                                                                                  dedicated to Council
O4 Water supply infrastructure is provided with all supporting    No solution provided.                                              Complies – The proposed development does not include the
technical documentation.                                                                                                             construction or realignment of any of Council’s trunk
                                                                                                                                     infrastructure. The where new connections are proposed, all
                                                                                                                                     alignment will be completed in accordance with Councils
                                                                                                                                     PSP6.
O5 Where buildings or other structures are in proximity to        S5.1 The footing of any building or structure is located clear     Complies – The proposed development does not include any
State or Council’s water supply infrastructure, provision is      of the zone of influence but no closer than 1.5m (measured         footings or structures that are within close proximity to
made to protect the infrastructure from physical damage and       horizontally) from infrastructure including sewers, water          Council’s infrastructure. The development does not propose
to allow ongoing maintenance by Council.                          mains and stormwater structures; AND                               any easements. Council is directed to Appendix B-
                                                                  S5.2 A registered easement in favour of Council is created         Architectural Plans for further details.
                                                                  over all underground infrastructure located in private property;
                                                                  AND
                                                                  S5.3 The width of the easement is the greater of 3m or the
                                                                  width of the zone of influence; AND
                                                                  S5.4 The easement is centred over the centreline of the
                                                                  infrastructure.
O6 Alignment of water supply infrastructure allows for easy       S6.1 Infrastructure is designed and constructed on the             Complies – The proposed development does not include the
access for the ongoing maintenance by Council.                    preferred alignments in accordance with PSP6 Engineering           construction or realignment of any of Council’s trunk
                                                                  Design Standards – Water and Sewerage.                             infrastructure. The where new connections are proposed, all
                                                                                                                                     alignment will be completed in accordance with Councils
                                                                                                                                     PSP6.
O7 Any alterations or repairs to infrastructure as a result of    S7.1 Any alterations or repair to infrastructure as a result of    Noted.
the development are made at no cost to Council.                   the development are completed at the developer’s expense.
Table 14-63 Sewerage reticulation
                         Column 1                                                          Column 2
                                                                                                                                                              Compliance
                   Specific Outcomes                                        Probable solutions (if code assessable)


July 2016                                                                                                          Page | 57

Log in to download the original (MCU16_0079 Town Planning Report.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.