MCU16/0079 Town Planning Report
Town Planning Report
“Undefined Use”
Staged Extension & Refurbishment of Existing RSL Club
5 Memorial Ave, Tewantin QLD 4565
Lot 3 on T16319 and Lot 10 on SP273411
O2 Water supply infrastructure is constructed— S2.1 Water supply infrastructure is constructed in accordance Complies – The proposed water connections and water
a) in accordance with appropriate engineering standards; and with PSP6 –Engineering Design Standards — Water and supply infrastructure has been designed in accordance with
b) to minimise adverse environmental impacts. Sewerage; AND PSP6. All documentation will be provided during the
S2.2 Erosion and sediment control measures are designed Operational Works, Building and Plumbing application stage.
and implemented in accordance with the Institution of
Engineers Australia (Queensland Division) Soil Erosion and All erosion and sediment control measures have been
Sediment Control - Guidelines for Queensland Construction designed in accordance with the control guidelines. All
Sites. documentation will be provided during the Operational Works,
Building and Plumbing application stage.
O3 Water supply infrastructure is proven to be suitable for its No solution provided. N/A - The proposed development does not include any items
use prior to Council accepting the dedicated asset. dedicated to Council
O4 Water supply infrastructure is provided with all supporting No solution provided. Complies – The proposed development does not include the
technical documentation. construction or realignment of any of Council’s trunk
infrastructure. The where new connections are proposed, all
alignment will be completed in accordance with Councils
PSP6.
O5 Where buildings or other structures are in proximity to S5.1 The footing of any building or structure is located clear Complies – The proposed development does not include any
State or Council’s water supply infrastructure, provision is of the zone of influence but no closer than 1.5m (measured footings or structures that are within close proximity to
made to protect the infrastructure from physical damage and horizontally) from infrastructure including sewers, water Council’s infrastructure. The development does not propose
to allow ongoing maintenance by Council. mains and stormwater structures; AND any easements. Council is directed to Appendix B-
S5.2 A registered easement in favour of Council is created Architectural Plans for further details.
over all underground infrastructure located in private property;
AND
S5.3 The width of the easement is the greater of 3m or the
width of the zone of influence; AND
S5.4 The easement is centred over the centreline of the
infrastructure.
O6 Alignment of water supply infrastructure allows for easy S6.1 Infrastructure is designed and constructed on the Complies – The proposed development does not include the
access for the ongoing maintenance by Council. preferred alignments in accordance with PSP6 Engineering construction or realignment of any of Council’s trunk
Design Standards – Water and Sewerage. infrastructure. The where new connections are proposed, all
alignment will be completed in accordance with Councils
PSP6.
O7 Any alterations or repairs to infrastructure as a result of S7.1 Any alterations or repair to infrastructure as a result of Noted.
the development are made at no cost to Council. the development are completed at the developer’s expense.
Table 14-63 Sewerage reticulation
Column 1 Column 2
Compliance
Specific Outcomes Probable solutions (if code assessable)
July 2016 Page | 57
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (MCU16_0079 Town Planning Report.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.