               33.    A small sign shall be installed within the site (in a clearly visible location for all vehicles to
                      see near the entry to the car parking area) to advise visitors that visitor car parking spaces
                      are provided within the basement car park and to use the intercom system (if applicable) to
                      contact the unit manager or the unit occupier they are visiting to enable entry to the basement
                      and to these spaces.
               34.    The Ground Level car parking area alignment shall be revised to be perpendicular to the
                      access driveway. The revised layout shall provide sufficient manoeuvring area within the
                      carspaces and access driveway to permit vehicles to access the spaces, manoeuvre and
                      leave the site in a forward gear in a total of 3 movements.
               35.    A minimum of 3 uncovered car park spaces and 41 covered car park spaces shall be
                      provided on site, including 2 clearly defined disabled car park spaces.
               36.    The car parking area shall be designed to comply with the provisions of AS/NZS 2890.1-
                      2004 for user class 1A with allowance for vehicles to enter and leave the site in a forward
                      gear and with a minimum head clearance (headroom) at any point of 2.3m.
               37.    The proposed turning area at the end of the aisle that serves proposed car park spaces 8 to
                      14 shall be line-marked with chevrons and have the words “No Parking” painted on the
                      pavement. A sign shall also be provided to indicate that the area is a “Turning Area Only”
                      and that “No Parking is Permitted”.
               38.    All car parking shall be kept, maintained and line-marked in a condition fit for use.
               Frontage Works
               39.    Footpath improvements such as topsoiling, grassing, and tree planting are required to the
                      Serenity Close frontage of the site in accordance with Planning Scheme Policy PSP03
                      Landscaping Plants & Guidelines. Grass shall be couch, free of weeds.
               40.    All redundant vehicular crossings to the site shall be removed and replaced by kerb and
                      channel, footpath paving and landscaping such as trees and grasses in accordance with
                      Council’s Standard specifications prior to commencement of the use permitted by this permit.
               Roof Water & Stormwater Drainage
               41.    A stormwater management plan shall be prepared by a RPEQ, specialising in stormwater
                      and water quality management incorporating the principles of the Environmental
                      Management Plan for the Settlers Cove Development (23118 DA), that demonstrates water
                      reuse strategies, infrastructure capacity and effective treatment methodology. The use of
                      rainwater harvesting tanks for irrigation purposes shall be incorporated in the overall design
                      plans. These plans shall be submitted to Council for approval prior to obtaining a
                      Development Permit for Operational Works.
               42.    Roof runoff from any new building should be directed to a rainwater storage system or tank
                      (minimum 23,000 litres) that is installed to ensure water from the rainwater storage system
                      or tank is used for external uses (such as watering gardens, irrigation, ornamental ponds,
                      water features, topping-up swimming pools, outdoor cleaning, etc) and for internal (ground
                      floor) use in washing machine cold taps and toilet cisterns. All rainwater tanks are to be
                      designed and installed in accordance with the approved Stormwater and Water Quality
                      Management Plan and the Queensland Development Code (QDC) current at the time of
                      building approval, and shall be part of the plumbing application for approval. The location
                      and capacity of the tanks shall be clearly shown on the plans submitted for Building
                      Works/Operational Works approval and any overflow shall be directed to the stormwater
                      drainage system.
               43.    All stormwater drainage shall be collected on site and discharged so there is no net increase
                      in stormwater runoff from the site.




                                                                                                         Page 6 of 24
Document Set ID: 20945331
Version: 4, Version Date: 07/08/2019                                                                  Print Date: 8 August 2019, 8:59 AM

Used in these records

About this file

File size
2.3 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment A - Existing Approval.pdf · 2.3 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.