               Erosion and Sediment Control
               65.    Any person acting on this permit shall prevent erosion and sediment export from leaving the
                      site. Site control measures such as silt fencing, controlled gravel access to the site and
                      controlled disposal of waste, will be necessary.
                      In this regard plans detailing the methods of controlling erosion and sediment prepared in
                      accordance with the “Manual for Erosion and Sediment Control” Version 1.2 prepared by the
                      Sunshine Coast Regional Council are required to be submitted to the Council prior to
                      obtaining a Development Permit for Operational Works.
               General (Engineering)
               66.    A suitably qualified registered professional engineer shall prepare engineering drawings and
                      specifications for all engineering works that will become Council infrastructure, which shall
                      be submitted in conjunction with an application for a Development Permit for Operational
                      Works. In this regard a DXF/DWG file on GDA94 zone 56 grid of the proposed cadastre
                      layout is to be submitted in conjunction with any application for Operational Works.
               67.    Digital detailed designs, including drawings, calculations, specifications and a schedule of
                      works, shall be submitted with any application for a Development Permit for Operational
                      Works in respect of roadworks and stormwater drainage works. The design shall be in
                      accordance with Council’s Planning Scheme Policy PSP05 – Engineering Design Standards
                      – Roads, Drainage and Earthworks. To avoid conflict with underground pipes or services,
                      all existing and proposed services required by the development shall be shown on the plans.
                      To facilitate production of As Constructed drawings it is suggested that all design drawings
                      are submitted in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on
                      the use of ADAC are available at www.adac.com.au).
               68.    A construction management plan/strategy to ensure no damage occurs to Council services
                      shall be prepared by a suitably qualified registered professional engineer and submitted to
                      Council in conjunction with any application for Operational Works.
               69.    Any damage caused to any public utility during the course of construction shall be repaired
                      to Council’s standards and at no cost to Council.
               70.    Any alteration of any public utility or other facilities necessitated by the development of the
                      land or associated construction works external to the site shall be at no cost to Council.
               71.    The transportation of all materials to and from the site shall be undertaken in a manner such
                      that no particle matter escapes onto a public road. All vehicles carrying materials either to
                      or from the site shall be covered to prevent materials including dust being windblown from
                      the vehicle.
               72.    As Constructed drawings and data shall be certified by a qualified experienced civil engineer
                      for design intent, and a licensed surveyor shall certify the cadastre and the location, level
                      and type of all services and structures, all of which shall be submitted to Council for checking
                      and for Council’s records.
                      The data must fully detail levels for all engineering works including but not limited to drainage
                      structures, finished ground levels and pavement surface levels. The data shall be submitted
                      in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the use of
                      ADAC are available at www.adac.com.au).
                      Approval of works shall not be granted until all As Constructed information has been supplied
                      and accepted by Council.
               Refuse
               73.    General refuse and recycling collection and storage system to include:
                      73.1. Use of 1.1 cubic metre low noise bulk bins.
                      73.2.      A bin wash facility within each of the three basement waste storage areas.




                                                                                                        Page 9 of 24
Document Set ID: 20945331
Version: 4, Version Date: 07/08/2019                                                                 Print Date: 8 August 2019, 8:59 AM

Used in these records

About this file

File size
2.3 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment A - Existing Approval.pdf · 2.3 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.