ORDINARY MEETING MINUTES 18 APRIL 2019
9. Shower and toilet facilities must be in accordance with the approved plans and
available at the commencement of the use.
Landscaping Works
10. The development site must be landscaped. The works must be undertaken in
accordance with an Operational Works approval and the Noosa Plan for that
specific area and must include in particular:
a. The extent of works shown on the approved Site Plan (D-11801-01A);
b. An average of a 2 metre wide landscaping strip is to be provided along the
Project Avenue road frontage of the subject site, exclusive of the access
driveway and generally uncompromised by infrastructure items;
c. All landscape works must be established and maintained in accordance with
the approved design for the life of the development, and in a manner that
ensures healthy, sustained and vigorous plant growth. All plant material
must be allowed to grow to full form and be refurbished when its life
expectancy is reached;
d. All landscape works must be maintained generally in accordance with the
approved design for the life of the development.
Site Access and Driveways
11. A sealed access driveway must be provided from Project Avenue to all parking and
manoeuvring areas of the development. The works must be undertaken in
accordance with an Operational Works approval and must include in particular a
driveway crossover in accordance with Council’s Standard Drawing RS-051 and
any associated addendums.
Car Parking
12. A minimum of 13 car parking spaces must be provided and marked on the site and
made available and accessible at all times while the use is open for business. The
works must be undertaken in accordance with an Operational Works approval and
must include in particular:
a. 11 visitor parking spaces (including scooter) within the total, which are clearly
marked for that purpose and accessible at all times for visitor use;
b. Car spaces 10 & 11 dedicated as staff parking spaces, which are clearly
marked for that purpose;
c. Dimensions, crossfalls and gradients in accordance with Australian Standard
AS/NZS2890.1:2004 for the relevant user class.
13. All car parking areas and access driveways must be maintained exclusively for
vehicle parking and manoeuvring and kept in a tidy and safe condition at all times.
14. Directional signage must be provided to direct visitors and customers to the car
parking spaces provided on site.
Stormwater Drainage
15. The site must be provided with a stormwater drainage system connecting to a
lawful point of discharge. The works must be undertaken in accordance with an
Operational Works approval and must include in particular:
a. Collection of runoff from the building and hardstand areas;
b. Discharge to Council’s drainage system in Project Avenue and/or to a
suitable easement.
Page 6 of 17
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.