           5. The building work is to be located and the footings/foundations to be constructed as detailed
              within the approved drawings listed below, which are to be integral to the building development
              approval issued by the building certifier for the work.

                                                     Approved Drawings

             Drawing Number
                                          Drawing Title                      Prepared by                   Date
             (Revision/Issue)
                 WD 100
                                            Site Plan                   Macchia Design Studio          21/05/2020
                 Rev. A

                 30115-S1             Footing and Slab Plan            SCG Consulting Engineers        June 2020

                 30115-S2             Footing & Slab details           SCG Consulting Engineers        June 2020
           NB – Approved Drawings are enclosed

           6. Any variation to the approved drawings will require a further referral to Unitywater for
              consideration prior to commencing the building work. Such amended proposals will be considered
              on their individual merits and may or may not be considered favourably.

           7. To ensure the design clearance is attained; the line of the infrastructure, including the sewer
              sewerage property connection point, must be accurately located on the property prior to
              commencing the building work. In the event the actual clearance is less than design clearance, a
              further referral to Unitywater is required and the resultant response shall be acted upon
              accordingly.

           REASONS FOR CONDITIONS

           The conditions as listed must attach to the building development approval so as to ensure there is
           no damage caused to the building works and the infrastructure, there is sufficient ventilation for
           individuals in close proximity to the infrastructure and adequate access for inspecting, maintaining
           or replacing the infrastructure is provided.

           Should you require any further information regarding this response, please contact Unitywater at
           [email protected] or alternatively telephone 1300 086489.

           Yours sincerely




           Mark Kettley
           Team Leader Development Works
           Development Services

           ENC        Approved Drawings




                                                                                                             Page 2 of 2




Revision No: 6                              Revised Date: 02/12/2019                        Next Review Date: 02/12/2021

Used in these records

About this file

File size
427 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Unity Water Referral Response Approval Letter with Conditions - Received 24-07-2020.pdf · 427 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.