SPECIAL MEETING AGENDA 16 DECEMBER 2019
Finance
Council has allocated a total of $1,318,214 in the current (FY2019/20) budget. The below table
identifies the estimated project costs.
Item Cost (excl. GST)
Costs to date (November 2019) $19,659
Tendered Contract Value (ex. GST) $1,230,934
Staff and other project costs $45,000
SUB TOTAL $1,295,593
Contingency $129,559
TOTAL BUDGET $1,425,152
A budget review submission will be required at BR3 to reflect the $106,938 shortfall in the current
approved budget, should the full contingency amount be required.
Risks & Opportunities
RISKS MITIGATION
Finance
Council request for scope increases. This will be mitigated through the Capital Works Project
Control Group and Capital Works Executive management and
limitation of client requested scope variations.
Geotechnical conditions give rise for Previous site conditions have been considered and significant
contractor claiming variation costs. latent conditions are not expected.
Clashes with underground services give There are no major underground services expected within the
rise for contractor claiming variation area of work. The contractor is required to identify and protect
costs. those that are discovered.
Contingency amount being insufficient This risk may be mitigated through the adoption of further
value engineering to occur during the construction phase
process.
Program
There is the potential that the project is The contractor is required to include “wet weather” allowances
delayed due to wet weather into their schedule.
Construction takes longer due to site In the event of delays the contractor is able to mobilise
being more constrained than allowed. additional equipment to bring the program on track.
Resource risk The contractor is utilising local subcontractors and is confident
in their ability to resource effectively from the local market.
Safety
This is a medium risk project due to Prior to construction commencing, work place health and
proximity to rural traffic environment. safety and traffic management plans will be required to be
submitted to Council for review. Regular audits on contractor
compliance with these approved plans will be undertaken by
Council throughout construction.
Environmental Harm
There is risk that the works impact on The works are in the existing road corridor which is typically
existing vegetation. clear of mature trees.
Risk of sedimentation/run-off. Contractors are required to have an environment management
plan which will be reviewed and approved by Council prior to
commencement.
Page 10 of 25
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.