SPECIAL MEETING AGENDA 16 DECEMBER 2019
Phase 1
The expression of interest was released via Vendor Panel on 2 September 2019 and closed 24
September 2019. Five (5) conforming and one (1) non-conforming responses were received.
Phase 2
The Invitation to (closed) tender was released via Vendor Panel on 22 October 2019 and closed
on 20 November 2019. Four (4) conforming and one (1) alternate tenders were received.
3. Tender Assessment
The tender evaluation panel undertook an assessment of the tender submissions in the closed
tender from the following respondents (listed in alphabetical order);
ARK Construction Group Pty Ltd
Davbridge Properties Pty Ltd T/A Davbridge Constructions
CRAGCORP Pty Ltd T/A Queensland Bridge & Civil
SGQ Pty Ltd (conforming bid)
SGQ Pty Ltd (conforming alternate bid)
Each evaluation panel member undertook an independent review and analysis of the respondent’s
technical submission and rated them according to established criteria. The evaluation panel then
met to review and discuss each panel member’s evaluation and agree scoring for each
respondents criteria, ultimately informing the evaluation outcome.
A summary of the scoring (combined price and non-price elements) as agreed by the evaluation
panel is provided in the table below. For further details including pricing refer to attachment 1.
Respondent Total
ARK Construction Group 83.85
Davbridge Constructions 93.57
Queensland Bridge & Civil 71.61
SGQ Pty Ltd 95.71
SGQ Pty Ltd (alternate bid) 100.00
The tender evaluation panel finalised tender evaluations and considered the tender (alternate bid)
of SGQ Pty Ltd to be the most advantageous to Council and presenting the best value for money.
This tender submission is favourable on the following basis:
They were able to demonstrate previous experience with successful construction of several
similar projects in the recent past;
The proposed methodology responded to the requirement to minimise the impact to motorists
by reducing the duration of the closure of David Low Way.
SGQ’s alternate bid provides a cost saving compared to SGQ’s conforming tender due to the
use of modified precast deck units which will provide improved inspection access during the
future maintenance of the structure.
Further, SGQ’s alternate proposes an advanced foundation system, which should deliver a
shorter construction duration. This will ultimately reduce the impact and nuisance to residents
by shortening the duration of the detour by a few days and reduce the amount and/or duration
of heavy machinery required on site during the construction phase.
They demonstrated a considered methodology and bridge design, offering high quality and
minimising Work Health and Safety risks;
Page 19 of 25
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.