SPECIAL MEETING AGENDA 16 DECEMBER 2019
They demonstrated that they have the necessary resources to meet Council’s contractual
timeframes for practical completion;
The project team is located within the Noosa Shire and greater Sunshine Coast and has local
experience with bridge design and construction.
The tender evaluation panel considers this alternate tender submission to be the most
advantageous to Council and presents the best total score of combined price and non-price
elements.
4. Access during construction
The project will cause some disruption to traffic and pedestrian movements on and around David
Low Way and Orealla Crescent. Very specific requirements have been developed and set through
the tender phase by Council in consultation with experienced traffic consultants. The contractor
must ensure access to businesses and residences is maintained throughout the works. Motorists
will be encouraged to use alternate routes via Facebook and mobile message boards at major
intersections to prevent potential lengthy delays through the detour route.
5. Program
SGQ propose to design and construct the project (pending adverse weather) in approximately six
months. The design process is planned to commence in January 2020. Site establishment and
construction will commence in May 2020 with expected completion in late July 2020.
This aggressive timeframe is required to comply with the Federal Grant funding requirements
applicable to this project.
In the design phase, Council’s project team will work with the contractor to determine the
aesthetics, such as curved bridge railings, patterns on the vertical abutment wall and will look for
opportunities to improve the current amenity.
6. Previous Council Consideration
Ordinary Meeting Minutes, 15 August 2019, Item 7, Page 18
That Council note the report by the Project Officer to the General Committee Meeting dated 12
August 2019 and authorise staff to call for Expressions of Interest for the Design and Construction
of the Orealla Crescent Bridge, Sunrise Beach.
7. Finance
Council has provisionally allocated a total of $1,754,514 for the project, comprising $754,514 in
this current 2019/20 financial year and $1,000,000 in the 2020/21 financial year.
The Federal Government through its Bridge Renewal Program will contribute 50% of the project
cost up to a maximum of $3,180,840. UnityWater is covering expenses related to temporary
relocation and reinstatement of their water main asset due to the planned renewal aligning with the
bridge replacement timing.
Page 20 of 25
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.