Specific Pollutant Export Parameters must be applied to each node type as cited in the Water By Design
MUSIC Modelling Guidelines. The values shown in Table 3 are for split catchment commercial areas.
Runoff pollutant concentrations are generated stochastically from the defined mean and standard
deviation.
Land Use – Commercial Log10 TSS (mg/L) Log10 TP (mg/L) Log10 TN (mg/L)
Storm Storm Storm
Base Flow Base Flow Base Flow
Flow Flow Flow
Roof Mean 0 1.30 0 -0.89 0 0.37
Std. Dev. 0 0.38 0 0.34 0 0.34
Roads Mean 0.78 2.43 -0.6 -0.30 0.32 0.37
Std. Dev. 0.39 0.38 0.5 0.34 0.30 0.34
Ground Mean 0.78 2.16 -0.6 -0.39 0.32 0.37
Level/Open
Space Std. Dev. 0.39 0.38 0.5 0.34 0.30 0.34
Table 3 – Pollutant Export Parameters (Commercial)
5.3.3.5 Water Quality Objectives
The Water Quality Objectives of the receiving waters for the proposed development have been
obtained from State Planning Policy July 2017. The State Planning Policy load reduction targets are
summarised in Table 4 below.
WATER QUALITY OBJECTIVES
Total Suspended Total Litter/Gross
Total Nitrogen
Solids (TSS) % Phosphorous (TP) Pollutants % Oils/Grease
(TN) % Reduction
Reduction % Reduction Reduction
No visible films or
80 45 60 90
odours
Table 4 – Water Quality Objectives
5.3.3.6 Treatment Plan
In order to achieve the Water Quality Objectives for the proposed development, it is proposed to use
mechanical treatment method to treat the runoff prior to discharge from the site. Mechanical treatment
devices have been chosen for the site in order to maximise the developable space within the site and
achieve the best design outcome.
Stormwater runoff from the proposed development will be captured in a new underground pit and pipe
network which will discharge to the proposed combined treatment / detention tank located under the
drop off area at the front of the building
Excellence with Economy in Engineering 12
l:\7000-7999\7700-7799\7700\reports\15-05-19 stormwater management plan_issue c.docx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.