RFI - Attachment H - Stormwater Management Plan_Issue C_
The original of this document is very large (15.9 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn15 May 2019
The Stormwater 360 stormfilters operate by filtering stormwater through media-filled filter cartridges.
As the stormwater percolates through the cartridges, pollutants, particulates, surface scums and
floating oil and greases are captured within the filter media. Once filtered through the media, the
treated stormwater is directed to a collection pipe.
The collection pipe discharges the treated water from site once the state planning policy requirements
are met.
Enviropods will be fitted to each field inlet.
The Enviropods consist of a screening bag supported by a filter box and structural cage. Modular plastic
deflector panels attach to the filter box and guide the flow of water to the screening bag. The screening
bag captures pollutants and allows water to pass through to the outlet pipe. Absorbent material inside
the screening bag captures oil and grease. Openings in the filter box allow water to bypass the screening
bag during high flow conditions.
5.4.4 Maintenance
For the Stormwater 360 Enviropods and Stormfilters, maintenance can be performed with a vacuum
truck to remove captured soil, sediment and floatables. Detailed maintenance techniques can be found
in the Stormwater 360 Operations and Maintenance Manual attached in Appendix 4.
Maintenance will be completed regularly to ensure that the devices are performing as designed to
ensure that the stormwater discharged from site is meeting the requirements of the State Planning
Policy and Noosa Council. This will be monitored as part of the development requirements.
5.5 Construction Phase (Sediment and Erosion Control)
5.5.1 Intent of Erosion and Sediment Control Management Plan
To prevent stormwater contamination (of watercourses) and the release of contaminated stormwater
and wastewater by ensuring compliance with the Environmental Protection Act 1994 and
Environmental Protection (Water) Policy 2009.
5.5.2 Implementation Strategy
Establish control measures and best practice approaches to prevent stormwater contamination and
minimise the risk and adverse effects of erosion and sedimentation. All Erosion and Sediment Control
measures must be designed, constructed and maintained in a manner that is commensurate with the
site’s erosion risk.
5.5.3 Erosion and Sediment Control Measures
Obtain a licence or approval to operate activities that are classed as environmental relevant
activities (i.e. they have the potential to cause environmental harm).
Implement and maintain appropriate control measures to prevent sediment leaden wastewater
and other potential pollutants such as oil, paint and wet concrete from entering the stormwater
system via stormwater drains and gullies. The control measures which must be considered to be
adopted are:
Limit site access during construction to minimise disruption to traffic
Excellence with Economy in Engineering 15
l:\7000-7999\7700-7799\7700\reports\15-05-19 stormwater management plan_issue c.docx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.