5.6.5 Erosion and Sediment Control Implementation Program

    •     Licenses, permits or approvals for each environmentally relevant activity must be obtained
          prior to the commencement of the particular activity.
    •     Appropriate control measures such as sediment fences, temporary construction entry/ exit
          sediment traps, pollution containment devices (e.g. sandbags), stormwater diversion and
          administrative controls must be installed and established prior to commencement of the
          earthworks and construction activities.
    •     Pollution control devices such as spill control equipment must be inspected on a regular
          basis (at least weekly).
    •     Other sediment and pollution control equipment such as containment bunds, hay bales and
          sediment fences must be inspected on a regular basis (at least daily).
    •     Inspection for any leaks, spills or potential contaminating activity must be performed on a
          regular basis (at least daily).
    •     Remove accumulated sediment or other contaminants from sediment/ pollution control
          devices on a regular basis.
    •     All erosion and sediment control measures must be inspected within 24 hours of expected
          rain and within 18 hours of a rainfall event.

5.6.6 Responsible Person or Organisation

The contractor shall be responsible for the implementation and maintenance of the Erosion and
Sediment Control Measures.

5.6.7 Reporting / Review

Records such as licences, approvals, permits and inspection reports must be reviewed on a regular
basis (e.g. at least monthly) to ensure that legal compliance is met, complaints are reviewed and
systems are working to prevent contamination.

5.6.8 Corrective Actions

    •     Perform clean-up of any spills immediately.
    •     Any mud or sediment which is tracked onto public roads is to be immediately removed
          using dry clean-up methods i.e. shovel and broom.
    •     Remove or relocate any stockpiles of waste where there is a reasonable risk of erosion and
          sedimentation.
    •     Replace or repair sediment or pollution control devices if they are not maintained in good
          working condition.




 Excellence with Economy in Engineering                                                                 15
 l:\9000-9999\9300-9399\9307\reports\20-05-22 stormwater management plan_issue a.docx

Used in these records

About this file

File size
4.4 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Item 11 Appendix E - Stormwater Management Plan-1.0.pdf · 4.4 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.