Minor Change Existing Approval 51901 3604 03 · 51901.3604.03

of 12

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

                      with a sealed pavement and designed, drained, constructed and maintained in
                      accordance with the Planning Scheme, Council's Policies and to the reasonable
                      satisfaction of the Shire Engineer. Plans and specifications for these works are to be
                      submitted to the Shire Engineer for approval in conjunction with the Building
                      Application. A Building Approval shall not be granted until the Shire Engineer has
                      approved of the carparking and access scheme.
               4.     There is to be no detrimental effect upon the amenity of the neighbourhood by reason
                      of the creation of excessive noise, lighting nuisance or other emissions.
               5.     The open space and setback areas are to be landscaped in accordance with Council's
                      Policy on Landscaping Guidelines and a properly prepared landscape plan to be
                      submitted to and approved by the Shire Planner, prior to the issue of a Building
                      Approval. Such landscaping is to be completed in accordance with the approved
                      landscape plan, prior to the premises being occupied and maintained at all times
                      thereafter to the reasonable satisfaction of the Shire Planner.
               6.     Existing trees on the site and within road reserves are to be retained, except where
                      required to be removed due to building operations or the conduct of the approved use.
               7.     Construction work and other associated activities are permitted only during the hours
                      of 7.00 a.m. to 6.00 p.m. Monday to Saturday. No work is permitted on public holidays,
                      except where extended hours are approved by the Building Surveyor.
               8.     Roof and surface water is to be collected on site and is to be discharged through a
                      single underground drain line into existing drainage to the satisfaction of the Shire
                      Engineer. A Building Approval shall not be granted until the Shire Engineer has
                      approved of the drainage scheme.
               9.     Submission of a cash bond or trading bank guarantee to the sum of $2000 to secure
                      performance of conditions, prior to the issue of Building Approval. The cash bond or
                      trading bank guarantee will be returned upon performance of the conditions of
                      approval.
               10.    The provisions of this approval are to be effected, prior to the commencement of the
                      approved use. Council reserves the right to call upon the bond or guaranteed sum
                      referred to in this approval for the purposes of litigation should the use not be conducted
                      in accordance with this approval.
               Additional conditions – 2 May 2019
                      When Conditions must be Complied With
               11.    Unless otherwise stated, all conditions of this Decision Notice must be complied with prior
                      to the use commencing, and then compliance maintained at all times while the use
                      continues.
                      Approved Plans
               12.    Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                        Plan No.            Rev.   Plan/Document Name                             Date

                        WD 1.4              A      Ground Floor Plan drawn by Sparks 17/07/2018
                                                   Architects

                        WD1.5               A      First floor and Roof Plan                      17/07/2018




                                                                                                    Page 2 of 12
Document Set ID: 23003343
Version: 4, Version Date: 03/05/2024

Used in these records

About this file

File size
1.5 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval 51901 3604 03.pdf · 1.5 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.