13. The developer must obtain all of the other Development Permits referred to in the Decision
Notice, prior to obtaining a Development Permit for Building Works.
Vehicle Access
14. Access to the site shall be maintained in accordance with AS/NZS 2890.1-2004 and Council
Standards.
15. The driveway shall be sealed for a minimum length of 10m from the edge of bitumen of Black
Mountain Road and any section of driveway with a grade greater that 12%.
16. A Road/Footpath Permit shall be completed and submitted for the construction of the access
driveway in accordance with Council’s Local Law No.8. If approval is given the driveway shall
be constructed in accordance with Council’s standard drawings, which will be provided at time
of approval.
Car Parking
17. A minimum of 1 carparking space per cabin shall be constructed to comply with AS/NZS
2890.1-2004 with regard to grades.
Roof Water & Stormwater Drainage
18. Roof runoff from the proposed new cabins shall be directed to a rainwater storage system with
a minimum storage capacity of 60,000.
Effluent Disposal
19. The design and construction of any on-site effluent disposal system and disposal area (land
application area) shall be in accordance with Council’s Planning Scheme Policy PSP24 -
Effluent Disposal and the recommendations of the report by Domestic Waste Water Design
th
dated 5 March 2008.
Contributions Towards Council Infrastructure
20. Monetary contributions shall be paid to Noosa Council towards the cost of providing and/or
upgrading various infrastructure at the rates applicable at the time of payment. An estimate
only of the contribution amounts under the current Council policies and requirements is
outlined in the table below:
Contribution Required For: Amount:
PSP12 – Public Open Space Contributions (Park) $1,075
Local Roadworks Contributions $845
$1,075
Land Use to update to
TOTAL Contribution Amount =
include any Land Use
contribution amounts.
Please note, that these amounts are all subject to variations in the Consumer Price Index, All
Groups Brisbane from June 2008 until the date of payment.
All contributions must be paid prior to the issue of a Development Permit for Operational
Works commencement of the use.
General
21. Any damage caused to any public utility during the course of construction shall be repaired to
Council’s standards and at no cost to Council.
22. Any alteration of any public utility or other facilities necessitated by the development of the
land or associated construction works external to the site shall be at no cost to Council.
3 of 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Negotiated Decision Notice - Concurrence Agency - DNRW [As Published]Related documentApplication case desk ↗
About this file
- File size
- 153 KB (small file)
- File type
No other editions are linked here.