Earthworks
19. Earthworks required on-site must be carried out under Council’s Planning
Scheme Policy PSP5 Engineering Design Standards, so as not to cause the
additional ponding of water on any adjoining lands or concentrate or direct
overland flow on to an adjoining property.
Coastal Protection
20. A mix of native endemic coastal vegetation consisting of ground covers, shrubs
and trees shall be planted for the width of the property, from the edge of the
dwelling to the seaward boundary. The landscaping works is to be consistent with
Planning Scheme Policy PSP3 - Landscaping Plants and Guidelines. The
planted vegetation must have a minimum pot size of 200mm and must be planted
at the following density:
a. trees must have a maximum spacing of 5m;
b. shrubs must have a maximum spacing of 1.5m; and
c. ground covers planted between the trees and shrub stems from providing
dense coverage.
The development is to provide adequate landscape buffering to protect the
character of the beachfront, to the reasonable satisfaction of the Manager
Development Assessment.
Pedestrian Access
21. A pedestrian access gate must not be installed along the seaward property
boundary with direct access by residents to the beachfront area not being
permitted.
Significant Weather Event
22. Should a significant weather event occur which results in substantial erosion
within the site, and undermines the structure and/or renders the Detached House
uninhabitable, the owner must
22.1 Immediately secure the perimeter of the property to prevent
unauthorised access and then undertake necessary works upon the
land to make the detached house safe and suitable for habitation in a
timely manner.
a. Any work proposed must be designed to ensure that the work will
not cause adverse impacts on other lands or on coastal
processes.
b. Rock, concrete and like hard materials must not be used for the
construction of beach protection works.
c. Any work proposed to be carried out must undertaken in
accordance with a Development Permit for Operational Works.
22.2 or remove the Detached House and all associated structures including
the footpath crossover and make the land safe at no cost to the Council.
Carried unanimously.
The meeting closed at 12.37pm.
Page 17 of 17
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.