Attachment 9 - Traffic Engineering Report
6.5.4 Future Year (2034) Project Traffic Scenario
The opening year project case scenario is obtained by the addition of development traffic generation shown
in Figure 6.4 to the base traffic volumes shown in Figure 6.7. These expected traffic movements are shown in
Figure 6.8.
2034 Project Volumes
AM Peak Site Access
PM Peak
90 81
39 84
65 16
Myall Street Nandroya Road
33 72 67 17 110 87
566 743 534 671 550 688 564 702 454 614 129 114
659 615 18 6 610 556 624 561 113 83 143 112
592 550 511 27 30 28
477 19
537 482
496 644
State Route 6
Figure 6.8: Estimated 2034 Peak Hour Ultimate Traffic, With Development
Site: Lot 2 & 3 Myall Street, Cooroy 23
Reference: 19BRT0357
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.