Council archive · source document
Minor Change Existing Approval - RAL18/0023 02 (As Published) · RAL18/0023.02
Acoustic Measures for Residential Lots & Office Lot
5. Prepare and submit to Council for approval with an Operational Works application a revised
acoustic report which includes measures to mitigate noise generate from the shopping centre
operations and equipment, including deliveries, truck movements and rubbish collection.
This report should consider attenuation at the noise source as well as a noise barrier along
the shared boundary of Lots 19 and 21. All measures to mitigate noise must be implemented
prior the submission of the subdivision plan to Council.
Noise attenuation is required to achieve the following acoustic quality for potential residential
uses on Lots 17-19. The measurement location must include receivers being placed at the
closest point to the future residential and office buildings.
Criteria (measured at the receptor) dB(A)
Sensitive receptor Time of Day
LAeq,adj,1hr 1 LA1,adj,1hr2
Daytime and evening
35 45
(habitable spaces)
Dwelling (indoors)
Night-time (sleeping
30 40
areas)
1Acoustic descriptor/noise target for continuous noise sources (eg. Mechanical plant).
2Acoustic descriptor/noise target for transient impacts arising from loading dock activities
(e.g. truck movements, reversing alarms, compactor, trolley etc.)
Water & Sewer Connections
6. An underground connection to reticulated water and sewerage must be provided to each lot
in accordance with the standards and requirements of Northern SEQ Distributor– Retailer
Authority (Unitywater).
A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
must be submitted to Council that certifies an underground connection to reticulated water
and sewerage has been provided to each lot.
External Works
7. Prior to the sealing of the survey plan a vehicle access to proposed Lot 23 must be
constructed at no cost to Council. The works must be undertaken in accordance with an
Operational Works approval, be generally in accordance with drawing number 1856-R08
Revision J prepared by Barlow Shelley and include an access extending from the existing
roundabout in Walter Hay Drive to the property boundary.
8. Prior to the sealing of the survey plan a new emergency vehicle exit from proposed Lot 23
must be constructed at no cost to Council. The works must be undertaken in accordance
with an Operational Works approval. The exit must extend from the property boundary to the
existing formation of the south bound lanes of Walter Hay Drive and be for emergency
vehicles only. The exit must:
8.1. be located in the north western section of the Walter Hay Drive frontage
8.2. include a crossing in the median of Walter Hay Drive that is sufficient to permit
emergency vehicles to exit the site and access the north bound lanes of Walter Hay
Drive
Page 3 of 18
Document Set ID: 24498083
Version: 5, Version Date: 02/02/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval - RAL18/0023 02 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 432 KB (small file)
- File type
No other editions are linked here.