25. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
5. REFERRAL AGENCIES
Not applicable.
6. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
Infrastructure Charges
1. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
made pursuant to the planning legislation and regulations current at the time of issue. For
further information, please refer to https://www.noosa.qld.gov.au/planning-
development/development-tools-guidelines/infrastructure-charges
Building and Construction Industry (Portable Long Service Leave) Levy
2. The QLeave levy must be paid prior to the issue of a development permit where it is required.
Council will not be able to issue a Decision Notice without receipt of details that the Levy has
been paid.
Co-ordination of Operational Works Assessment
3. Additional application fees apply to Operational Work applications where the different
aspects of the works are lodged separately. Significant savings in application fees will result
if all works are lodged in a single application.
Qualified Person
4. For the purpose of preparing a Geotechnical Report, and for certifying geotechnical stability
for the development, a qualified person is considered to be a person who:
a. is a Registered Professional Engineer of Queensland (RPEQ); and
b. has a degree in civil engineering or engineering geology; and
c. has a minimum of 5 years’ experience in the field of geotechnical engineering or
engineering geology.
Turtle Habitat Protection
5. To minimise the impact of development on turtle nesting sites and the sea-finding behaviour
of hatchlings, the following actions are recommended to be undertaken during construction of
the development:
a. Construction works are to be restricted to daylight hours during the turtle nesting and
hatching season (October – May).
b. Flood lighting must not be used from October – May (turtle nesting and hatching
season).
Page 5 of 8
Document Set ID: 23314163
Version: 3, Version Date: 22/10/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original