CN00375 - RETAINING WALL RECONSTRUCTION - ARKANA DRIVE · Report

of 6

Page text shows just the words. Original shows the document exactly as it was published.

SERVICES & ORGANISATION COMMITTEE MEETING                                                11 JULY 2023


5.1       CN00375 - RETAINING WALL RECONSTRUCTION - ARKANA DRIVE


Author               Project Officer, James Santifort
                     Infrastructure Services Department
Index                ECM/Projects & Contracts/CN00375 Retaining Wall Reconstruction -
                     Arkana Drive / Reports to Council
Attachments          1.   CN00375 - Weighted
                          Attribute Evaluation Workbook - Final Outcome


EXECUTIVE SUMMARY
      •   This report provides a recommendation for the contract award of the preferred contractor for
          Contract No. CN00375 fo Retaining Wall Reconstruction - Arkana Drive, Noosa Heads.
      •   This is a lump sum price contract that will include all materials and services required for the
          reconstruction of the retaining wall.
      •   In accordance with Local Government Legislation and Council Procurement Policy, an
          Invitation to Tender was initiated and which attracted three (3) tender responses. All three of
          these responses were conforming.
      •   The tender evaluation panel completed the evaluation process and considered the tender
          submission from Sunshine Civil Solutions Pty Ltd the most advantageous to Council,
          representing value for money. The Sunshine Civil Solutions Pty Ltd tender submission
          demonstrated compliance with the requirements of the invitation to tender. Sunshine Civil
          Solutions Pty Ltd has the suitable experience, capability, and resourcing to complete the
          works.
RECOMMENDATION
That Council note the report by the Project Officer to the Services & Organisation Committee Meeting
dated 11 July 2023 and:
A. Award contract no. CN00375 Retaining Wall Reconstruction - Arkana Drive to Sunshine Civil
   Solutions Pty Ltd for the lump sum price of $409,904.22 (excl. GST); and
B. Authorise the CEO to negotiate the final contract with Sunshine Civil Solutions Pty Ltd.


REPORT
Failure of the retaining wall in the median strip of Arkana Drive was first observed in 2015.
Further geotechnical investigations have found that the bank instability is not limited to the
extents of the existing retaining wall but rather extends 131m. The slope in its current position
is considered ‘marginal’ in terms of global instability with an assessed risk of ‘moderate’ to ‘high’
in accordance with Australian Geomechanics Society (AGS) guidelines.

Council engaged a structural engineering consultant who designed a grouted rock wall solution
to improve stability and prevent further slips in the median strip. The rock wall stretches the
whole 131m section, and is approximately 1.2m high.
Log in to download the original file

Report.pdf · 103 KB (small file)

Full text of the other 5 pages

Page 2

SERVICES & ORGANISATION COMMITTEE MEETING                                        11 JULY 2023


1. Tender Process

In accordance with Chapter 6, Part 3 of the Local Government Regulations and Council’s
Procurement Policy, Council invited written tenders for the retaining wall reconstruction. The
invitation to tender was issued as a lump sum construction-only contract.

Council invited written tenders via the Council VendorPanel e-portal on 15 May 2023 and
included an advertisement within the Noosa Today publication on 19 May 2023, with responses
closing on 6 June 2023.

The Invitation to Tender attracted three (3) tender responses. All three of these responses were
conforming.

2. Tender Assessment

The evaluation was conducted by the Evaluation Panel that consisted of the following members
of staff:
    • Project Officer (Contract Administrator)
   •     Designer - Capital Works
   •     Workplace Health and Safety Officer (Safety Only)
   •     Project Manager – Capital Works
   •     Contract & Projects Superintendent
Each member of the Evaluation Panel read and declared that they understood and accepted the
probity requirements, which includes a declaration of conflicts of interest and confidentiality.

The tender evaluation panel undertook an assessment of the following conforming tender
submissions, listed in alphabetical order:
   • Bellwether Contractors Pty Ltd
   •     Durack Civil Pty Ltd
   •     Sunshine Civil Solutions Pty Ltd.
 All three (3) conforming tenders progressed to a full weighted evaluation using the following
criteria and weightings:

 Criteria                                                            Weighting
 Experience and Technical Capability                                    15.0%
 Methodology – Delivery of Scope                                        15.0%
 Methodology - Resources                                                5.0%
 Quality                                                                5.0%
 Health & Safety                                                        5.0%
 Environment & Sustainability                                           7.5%
 Contribution to Local Economy                                          7.5%
 Price                                                                  40.0%

Page 3

SERVICES & ORGANISATION COMMITTEE MEETING                                               11 JULY 2023


The evaluation panel completed the evaluation process and considered Sunshine Civil Solutions
Pty Ltd to be most advantageous to Council, presenting the best value for money. Their
submission scored the highest over the non-priced elements whilst being significantly cheaper
than the other two (2) submissions.

Sunshine Civil Solutions Pty Ltd’s tender demonstrated the following:
   • Full compliance with the tender requirements.
      •   A good understanding of the project constraints and risks.
      •   Previous experience, capability, and resourcing to carry out the contract works.
      •   A detailed construction methodology and program which aligns to the contract specifications.
      •   Detailed plans in place to manage quality, safety and the environment over the course of the
          contract.
      •   Contribution to the local economy being owned and operated within the Noosa Shire LGA.


3. Next steps

Reconstruction of the retaining wall is planned to be commence in September 2023 and aims to
be completed in November 2023. Arkana Drive will remain open during the works with minor
traffic delays expected.

Link to Corporate Plan

Theme No. 2. - Liveability

Liveability encompasses housing, facilities and services, transport, health and wellbeing to enable an
inclusive, connected and vibrant community.

2.7 Fund and deliver sustainable assets and facilities and associated services responding to the
changing needs of the community and the challenges and opportunities of the future.


Previous Council Consideration
Nil
Finance
The Arkana Drive Median Strip project received an initial budget allocation of $247,000 as part
of the Federal Governments Local Roads and Community Infrastructure (LRCI) Phase 3 grant.
An additional $208,000 has been allocated to the project from the LRCI Phase 4 – Part B grant
fund to allow for the award of this tender. This was approved through Capital Works Executive
in the form of a Flying Minute dated 26 June 2023.

The increase in price has arisen from:
- legacy issues as the initial budget was established in 2019
- significant increases in construction prices in recent years as experienced across the market.

A value engineering exercise was undertaken to reduce the height of the wall and increased the
angle of the batter to reduce costs and improve maintainability, which has assisted to bring the
budget closer to the original allocation.

The revised project budget is summarised and detailed in the table below:

Page 4

SERVICES & ORGANISATION COMMITTEE MEETING                                          11 JULY 2023



 Item                                        Cost (ex GST)
 Current spend to date                                   $9,295
 Construction Contract - Civil                         $409,904
 Staff Time                                             $15,301
 Contingency (5%)                                       $20,500

 TOTAL BUDGET:                                         $ 455,000




Risk & Opportunities


 Finance Risks               Mitigation
 Changes to scope            This is to be mitigated through the Capital Works Project Control
                             Group and Capital Works Executive meetings, and limitation
                             requested scope variations.
 Geotechnical conditions     A detailed Geotechnical investigation report has been completed
 give rise for contractor    and the report provided as part of the tender documentation.
 claiming variation costs.

 Clashes with public         The contractor is aware of potential UnityWater clashes with the
 utility provider Unity      scope of works and will investigate the full relocation
 Water give rise for         requirements immediately after contract award. An allowance for
 contractor claiming         lowering of services has been made in the schedule of rates.
 variation costs.
 Contingency amount          This risk is mitigated through Council's highly experienced project
 being insufficient.         team and the appointment of an experienced contractor and
                             contract supervision by an experienced Superintendent. If the
                             contingency amount is insufficient to cover the cost, this is to be
                             mitigated through the budget approval process.



 Program Risks               Mitigation
 There is the potential      Contractor has submitted a time-generous program which will
 that the project is         allow for wet days to be absorbed within the program. The works
 delayed due to wet          are also scheduled in the dry season.
 weather.
 Resource risk.              The contractor has nominated a capable and experienced project
                             team to undertake the required construction works.
 Construction takes          The contractor is well-resourced and has the available resources
 longer than allowed for     to deliver this project successfully in conjunction with current
                             works on hand.
 Lead time of materials      Many associated risks are mitigated by ordering the materials as
 pushing the program         soon as possible after the tender award.
 out.

Page 5

SERVICES & ORGANISATION COMMITTEE MEETING                                       11 JULY 2023




 Safety Risks             Mitigation
 Site safety.             The contractor has submitted extensive safety documentation as
                          part of their submission and will be appointed as the Principal
                          Contractor, being responsible for all Workplace Health and Safety
                          of the site.

                          Prior to construction commencing, workplace health and safety
                          and construction management plans will be required to be
                          submitted to Council for review.

                          Regular audits on contractor compliance with these approved
                          plans will be undertaken by Council and WH&S teams throughout
                          the construction.

 Environmental Harm        Mitigation
 Risks
 Works impact on the      The contractor is responsible for the development and
 environment.             implementation of strategies to minimise impacts such as noise,
                          dust, vibration, sediment, and erosion. The contractor is required
                          to submit a detailed Environmental Management Plan as well as
                          a CPESC approved Erosion and Sediment Control Plan prior to
                          construction.

 Scope and Quality        Mitigation
 Risks
 Risk of not meeting      To be managed through reviews performed by an experienced
 project objectives.      Project Manager, Superintendent, and other project team
                          members.

 Public Disruption        Mitigation
 Risks
 Traffic disruption.      Arkana Drive will remain open during the works with minor delays
                          to be expected. Resident access will be available at all times.

 Communication issues.    Council’s internal Infrastructure communications and consultation
                          Officer is appointed to the project and will help coordinate the
                          communications and consultation to community members.
 Noise from plant and     This will be minimised by working during normal working hours
 equipment may be a       where possible.
 cause of disruption to
 residents.

Consultation
External Consultation - Community & Stakeholder
Nil
Internal Consultation
Departments/Sections Consulted:

Page 6

SERVICES & ORGANISATION COMMITTEE MEETING                                               11 JULY 2023


   Mayor                        Community Services                          Corporate Services

   Councillors                  Director                                    Director

                                Community Development                       Financial Services

   Chief Executive Officer      Community Facilities                        Fleet

   Executive Support            Libraries & Galleries                       ICT

                                Local Laws                              X Procurement
                                Waste & Environmental Health                Property

                                                                            Revenue Services



   Executive Services           Environment & Sustainable Development       Infrastructure Services

   Director                     Director                                    Director

   Community Engagement         Building & Plumbing Services                Asset Management

   Customer Service             Development Assessment                      Buildings and Facilities

   Governance                   Economic Development                    X Civil Operations
   People and Culture        X Environmental Services                       Disaster Management

                                Strategic Land Use Planning             X Infrastructure Planning,
                                                                            Design and Delivery

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.