Attachment H - Environmental Values Assesment
Callaghan and Toth Consulting Engineers______________________________________________________
Biodiversity Overlay
c) maintaining wildlife corridors along OR vegetation communities both upstream and downstream
watercourses and drainage lines for S5.2 Where constructing a Detached house or of the Lower Mill site. This riparian zone does provide a
native fauna movement; Community residence and on an allotment situated wildlife corridor along Cooroy Creek and down to Six Mile
d) avoiding edge effects and wholly within the Riparian Buffer Area, Creek.
incompatible uses in riparian zones; a) fronting the Noosa River – development is
e) maintaining bank stability by setback a minimum of 40m from mean high water As part of the proposed development water quality will be
minimising bank erosion and spring or as otherwise prescribed by the managed as per the attached Stormwater Quality
slumping; Environmental Protection Agency’s Erosion prone Management Plan (SWQMP) by Callaghan and Toth Pty
f) maintaining water quality by filtering Area Maps; Ltd. The proposed treatment systems will treat sediment
sediments, nutrients and other b) not fronting Noosa River – and nutrients loads in the stormwater flows, to protect the
pollutants; and development is located outside the riparian zone water quality of the adjacent watercourse.
g) removing undesirable plant species and setback a suitable distance from the
and replacing them with vegetation of watercourse having regard to the development
local origin; constraints of the property and the need to protect
environmental and riparian values;
OR
S5.3 For Animal husbandry on premises in the
Rural Zone –
a) stock proof fencing is installed along watercourses
at a distance of no less than 10m from the top of
the bank;
b) stock watering points are located no less than
15m away from the top of the bank of
watercourses; and
c) stock crossing points across watercourses are
defined and controlled with stock proof fencing, to
prevent stock from damaging riparian vegetation
or banks to watercourses;
OR
S5.4 Recreational facilities (including playgrounds,
pergolas, barbeques etc) are setback a minimum of
30m from the top of the bank of a watercourse and
10m from the top of the bank of a drainage line;
OR
S5.5 For Forestry uses the cultivated area is
separated from watercourses by a distance not less
than the distances identified below, measured from
high water mark or the top the bank, whichever is the
greater distance –
1. X:\JOBS\CT Projects in progress\2001 env reports for cooroy playground carparks\Correspondence\Reports\ENV\Playground\Biodiversity Overlay_HInterlandPlayground.docx pg. 10
pg. 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Attachment H - Environmental Values Assesment.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.