Original source · versioned page text
Att11 - Land Suitability (effluent) Report
Very large file (13.4 MB): the original may take a few minutes to open or download. The page text below is quick to read.
FPE Ref: 6195-220404-1.0
The hydraulic loading for the proposed development has been estimated using Table H4 of AS1547:2012.
This Guideline provides the most accurate assessment for flow rates from a campsite like this, and is
based on the use of on-site roof water and dam water as the primary potable water sources.
Indicative hydraulic loading based on this Guideline and type of the development activity has been
adopted to calculate the average daily sewage flows resulting from the proposed development and is
detailed in Table 4 below:
Table 4: Calculated Hydraulic Wastewater Flows
Sewage Flows per Table Equivalent
Proposed Total Sewage
Type H4 – AS1547:2012 Population (EP) -
Population Flows (L/day)
(L/day/person) 200L
Campers 300 100 30,000 150
Staff Members 20 100 2,000 10
Total Daily Sewage Flows and Equivalent Population 32,000 L/day 160
Table 4 above shows that a total daily sewage flow calculated for the project of 32,000 L/day (160
Equivalent Persons) will be generated as a result of the proposed development.
APPROVAL PROCESS
Based on the estimated hydraulic loading calculated in Section 3.3 above, the proposed development will
trigger the need to obtain an Environmentally Relevant Activity (ERA 63) approval from Department of
Environment and Science due to the sites daily wastewater loading exceeding 21 equivariant persons.
The ERA 63 application will be undertaken during the Building Approval (BA) phase of the development.
TREATMENT SYSTEM
Treatment of wastewater to a minimum of advanced secondary effluent quality in accordance with the
Queensland Plumbing and Wastewater Code may be achieved by the installation of either an aerobic
wastewater treatment system or biological sand filtration system.
ADDITIONAL DESIGN CONSIDERATIONS
A number of other design considerations should be made in relation to the following key elements
associated with this type of development.
20 April 2022 Land Suitability Report 7
CYC Campsite
48 Kabi Road, Cootharaba
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.