SUPERSEDED Decision Notice - Approved by Delegation of Authority MCU20/0021 [As Published]
Condition 46 is imposed pursuant to s128 of the Planning Act 2016 being necessary trunk
infrastructure identified by Council’s LGIP to service the development.
Site Access and Driveways
47. A sealed access driveway must be provided from Hilton Terrace to all parking and
manoeuvring areas of the development. The works must be undertaken in accordance with
an Operational Works approval and must include in particular:
a. a driveway crossover generally in accordance with Council’s standard drawing RS-
051 and any associated addendum
b. an internal driveway generally in accordance with the approved plans
c. suitable signage at the southern (garaging) end advising drivers to “give way” to
incoming vehicles.
Car Parking
48. A minimum of 6 car parking spaces (including 2 visitor spaces) must be provided and
marked on the site and made available and accessible at all times. The works must be
undertaken in accordance with an Operational Works approval and must include in
particular:
a. 2 visitor parking spaces within the total, which are clearly marked for that purpose
and accessible at all times for visitor use
b. dimensions, openings, crossfalls and gradients in accordance with Australian
Standard AS/NZS2890.1:2004
49. All car parking areas and access driveways must be maintained exclusively for vehicle
parking and manoeuvring and kept in a tidy and safe condition at all times.
50. Directional signage must be provided to direct visitors to the car parking spaces provided
on site.
Pedestrian and Bicycle Facilities
51. Pedestrian and bicycle facilities must be provided for the development. The works must be
undertaken in accordance with an Operational Works approval and must include in
particular:
a. a new 1.5 metre wide footpath within the road verge for the entire length of the site’s
frontage to Hilton Terrace. The path must be in accordance with Council’s standard
drawing RS-065 and any associated addendum
Condition 51 is imposed pursuant to s128 of the Planning Act 2016 being necessary trunk
infrastructure identified by Council’s LGIP to service the development.
Stormwater Drainage
52. The site must be provided with a stormwater drainage system connecting to a lawful point
of discharge. The works must be undertaken in accordance with an Operational Works
approval and be generally in accordance with the drawing titled “Stormwater Management
plan” No. 30101-SW1.1 prepared by SCG Consulting Engineers dated May 2020, and must
include in particular:
a. extension of the site stormwater system to collect and convey ponded water from the
area of the site between the proposed retaining wall and the rear boundary.
b. the use of gravity stormwater drainage and not surcharge pits.
Condition 52 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Page 7 of 12
Document Set ID: 21280390
Version: 4, Version Date: 30/10/2020