Engineering RFI Response

of 2

Page text shows just the words. Original shows the document exactly as it was published.

Our Ref: S21-074                                                                                                      Westera Partners Pty Ltd
                                                                                                                        Sunshine Coast Office
                                                                                                                                   P 0437 335 403
5 November 2021

Noosa Council
PO Box 141
Tewantin QLD 4565

Attention:                    Maxwell Potter

Council Ref:                  MCU21/0170


RE: RESPONSE TO COUNCIL’S REQUEST FOR INFORMATION ASSOCIATED WITH THE APPLICATION
LODGED FOR THE PROPOSED DEVELOPMENT AT 183 WEYBA ROAD, NOOSAVILLE


Requested Information:
    Issue – Onsite Manoeuvring
    On the submitted vehicle manoeuvring plan, the swept paths of both vehicles appear to potentially
    conflict with the adjacent parking space in each garage. In addition, the rear of the vehicles for both
    swept paths, conflict with the landscaping in the front gardens. Council has concerns manoeuvrability
    may be limited once the landscaping in the front garden reaches a mature height.
    Information Required
     8. Please demonstrate the design vehicle can still manoeuvre onsite and leave in a forward gear with
         a second vehicle in each garage and without encroaching into the front landscaping or
         alternatively reposition the footprint of the dwelling to allow more space for manoeuvring at the
         front.

    Issue – Stormwater Management Plan
    The submitted Stormwater Management Report only addresses water quality. Filling of the site has the
    potential to impact on existing overland flow paths and create additional ponding and/or diversion of
    overland flow paths onto adjoining properties.
    Information Required
     9. Please demonstrate the development and filling of the site will not create off-site stormwater
         impacts (ponding or diversion of overland flow paths onto adjoining properties) and/or include
         appropriate stormwater drainage infrastructure to convey stormwater from adjoining properties,
         through the site and to the lawful point of discharge.

    Issue - Earthworks
    The proposed works include fill to the site however no plans have been submitted that provide any
    detail of these works. The submitted acid sulfate soil report only provides an analysis of the soil
    characteristics.

 SUNSHINE COAST                            B RIS BA NE                          GOLD COAST                              NORTHE RN NSW
 Suite 2, Norval Corporate Centre          Level 2, 33 Langland Street          Level 3, 17 Welch Street                Suite 24 Level 2
 13 Norval Court                           Newstead QLD 4006                    Southport QLD 4215                      11-13 Pearl Street
                                                                                                                        Kingscliff NSW 2487
 Maroochydore QLD 4558

 P: 07 5391 3777 F: 07 5646 5857           P: 07 3852 4333 F : 07 5646 5857     P: 07 5571 1599 F : 07 5646 5857        P: 02 6674 8047 F: 07 5646 5857

 PO Box 2016                               PO Box 2016                          PO Box 6138                             PO Box 1131
 Fortitude Valley BC, QLD 4006             Fortitude Valley BC, QLD 4006        Southport Mail Centre 9726              Kingscliff NSW 2487

 E: [email protected]   E: [email protected]   E: [email protected]     E: [email protected]
Log in to download the original file

Engineering RFI Response.pdf · 279 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 1 page

Page 2

   Information Required
    10. Please provide a preliminary earthworks plan that indicates the volume of fill required for the site
        and where necessary (if fill volume triggers the requirement against the Acid Sulfate Soil Overlay
        Code), provide an Acid Sulfate Soil Management Plan prepared by an RPEQ that provides
        recommendations to address the potential risks associated with the fill works.

   Issue – Footpath Width
   The submitted plan only indicates a small portion of the footpath being replaced at the existing width.
   The current Noosa Planning Scheme and Councils standard drawings require footpaths along
   Distributor roads to be at a width of 3.0m desirable or 2.0m minimum.
   Information Required
    11. With existing features restricting the width of the verge area available for a 3.0m wide footpath,
        please amend the engineering plan/s to include a 2.0m wide footpath across the frontage of the
        development.


Response
Responses to the above matters are as follows:
8. Refer to the updated vehicle turnpaths included on the updated engineering drawings that
    accompany this response.
9. The property to the south at 8 Pipi Crescent, Noosaville currently achieves a lawful point of discharge
    through kerb adaptor to Pipi Crescent which is clearly visible via Google Street View. The whole site
    should have been profiled to fall towards the frontage at the subdivision phase though as detailed
    survey information is not available it is agreed that small volumes of nuisance runoff may reach the
    development site. As a result all fill walls are proposed to be offset 150mm off the property
    boundaries to allow this small volume of runoff to pass along the base of the wall within the
    development site out to Weyba Rd.
10. The fill volume has now been included on the updated engineering drawings that accompany this
    response. As the calculated volume is below 500m3 it does not trigger an acid sulphate soils
    investigation.
11. The requested 2.0m wide footpath has been added to the updated engineering drawings that
    accompany this response.

Should you require further information in this regard, please do not hesitate to contact me at the Sunshine
Coast office.

Yours faithfully,




Jared Hill CPEng | RPEQ 19891
Associate | Senior Civil Engineer
Westera Partners Pty Ltd




                                                                                                          2

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.