Noosa Shire Council ATTACHMENT 2
2018/19 Capital Budget Review 3 - Capital Submissions
For the period ending 30 June
Project Current Proposed Revised Category er eli r)
Budget BR3 Budget
Adjustment
ber TLL A)
Bridges _|
Cooroy Mountain Bridge 142,400 - 56,400 | 86,000 Emergent ‘Identified savings on Cooroy Mountain Bridge Road
Works Project.
Gumtree Drive Bridge Removal . 36,125 36,125 Emergent Cost of removing the bridge with future investigation
- ee | ____ Works ! works underway for replacement options.
Mary River Road Bridge Replacement 1,157,365 629,380 | 1,786,745 ft Cost overrun for project reflective of adopted tender and
Increases | variation above budget and grant allocation.
Old Noosa Road Bridge Replacement 1,532,896 - 351,955 1,180,941 Cost Saving Cost saving for project reflective of adopted tender and
" | variation above budget and grant allocation.
Orealla Crescent Overpass 11,961 80,000 91,961 Timing - Bring Costs associated with revised design brought forward
Refurbishment Forward to from 2019/20 budget.
2018/19
Bridges Total 2,844,622 337,150 3,189,772 0
Car Parks | | | |
Tewantin - Read Park Carpark 150,000 11,738 161,738 Cost Overspend to deliver additional site works outside
Surfacing - Increases | scope.
Car Parks Total 150,000 11,738 164,788
Cemeteries | |
Coffin Lowering Device . 8,200 8,200 Emergent “Acquisition of a coffin lowering device to meet WHS
Works requirements at cemetery sites.
Cemeteries Total : |
Coastal Canals and Waterways | |
Beach Access Shower Renewal Claude 45,980 45,980 Emergent Emergent safety works to replace two beach shower
Batten Drive _ __ | Works facilities on Claude Batten Drive. _
Peregian Beach Boardwalk Renewal 70,000 - 50,000 20,000 Timing - Delay Timing of construction delayed to 2019/20 to align with
North of Tower to access | | to 2019/20 |amenities project and other Peregian Beach precinct
| works later in 2019 calendar year.
Coastal Canals and Waterways Total 70,000 - 4,020 — 65,980
Commercial Land & Prope | | |
Rufous Street Stage 3 100,000 | 110,000 © 210,000 Timing - Bring Additional pre-construction costs forecast to occur during
Forward to the remainder of 2018/19 year.
2018/19
Commercial Land & Property Total 100,000 110,000 210,000 0
Community Facilities
Community Facilities Minor Works - 291,500 291,500 Emergent vA range of identified emergent works from 2019/20
Brought Forward | Works ‘capital works program brought forward to offset timing
delays in other projects.
NAC & NLC Roof Restoration (to 172,500 - 132,500 40,000 Timing - Delay Timing of construction delayed to 2019/20 to align with
Support Solar Panels a to 2019/20 | NAC closure and 50m pool renewal over winter 2019.
Noosa Heads Demolition of Lifeguard 49,271 38,890 88,161 Emergent Updated cost estimate to undertake the demolition work
Service/ SLSQ operations | Works ‘a cover unplanned asbestos removal and relocation of
electrical services
Tewantin SES Termite Damage 6,977 8,784 15,761 Emergent Additional costs associated with the resolution of termite
Works icons at Tewantin SES and subject to a successful
QFES grant application.
Community Facilities Total 228,748 206,674 4354220
Corporate Buildings |
Noosaville Depot - Kitchen Renewal 30,000 | 30,000 Emergent Emergent works request to renew the Noosaville Depot
Works kitchen.
Tewantin Admin Building - Security - 75,000 75,000 Emergent Emergent safety and security works for access control
Upgrade Works and disability access in the administration building.
Tewantin Administration Building - 200,000 - 200,000 - Timing - rd | Deferral of masterplan to the 2019/20 budget due to
masterplan | to 2019/20 prioritisation of immediate WHS works.
Corporate Buildings Total 200,000 - 95,000 105000
Holiday Parks | |
Noosa North Shore Campground 700,000 - 600,000 | 100,000 Timing - wiggly Uaioe to be awarded toward the end of 2019/20 year,
Redevelopment | to 2019/20 however majority of construction to occur in 2019/20.
Noosaville, Noosa River Holiday Park 428,000 247,500 675,500 Cost Savings from small amenities to fund partially fund
Large Amenities Refurbishment | Increases variations and cost increases at large amenities.
Noosaville, Noosa River Holiday Park 224,387 - 120,000 104,387 Cost Saving Savings from small amenities to fund partially fund
Small Amenities Replace variations and cost increases at large amenities.
Holiday Parks Total 1,352,387 - 472,500 879,887
Libraries & Galleries _ - ee
Cooroy Library Air Conditioner Plant 30,000 43,628 73,628 Emergent ‘at increase to reflect fit-for-purpose design of the
Room Enclosure Works enclosure.
Page 39 of 63See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.